Last update at: 2024-09-13T01:30:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 2 3 4 5 6 > | |||||||||
Great Island |
Great Island |
Other_0000000000000008203_002 | Dismissed | 2023-06-19T10:34:59+01:00 | 2023-06-19T10:07:00+01:00 | 2023-07-28T10:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Great Island |
Great Island |
Other_0000000000000008203_001 | Dismissed | 2023-06-19T10:13:07+01:00 | 2023-06-19T10:07:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
|||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_006 | Dismissed | 2023-09-22T15:13:14+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_005 | Dismissed | 2023-09-21T17:33:37+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_004 | Dismissed | 2023-09-21T17:03:58+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_003 | Dismissed | 2023-09-21T16:48:56+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_002 | Dismissed | 2023-09-21T14:26:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 550MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_001 | Dismissed | 2023-09-20T08:32:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | Running at Circa 550MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_003 | Dismissed | 2023-09-21T14:38:30+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_002 | Dismissed | 2023-09-21T14:27:09+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_001 | Dismissed | 2023-09-20T08:29:55+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008420_002 | Dismissed | 2023-09-18T12:19:36+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008420_001 | Dismissed | 2023-09-15T15:01:11+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008421_002 | Dismissed | 2023-09-18T12:19:17+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008421_001 | Dismissed | 2023-09-15T15:02:40+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |
||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_002 | Dismissed | 2023-09-07T17:00:31+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_001 | Dismissed | 2023-09-06T16:25:23+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_004 | Dismissed | 2023-08-09T14:21:16+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_003 | Dismissed | 2023-08-09T14:15:15+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_002 | Dismissed | 2023-08-09T14:14:24+01:00 | 2023-08-09T14:09:00+01:00 | 2023-08-10T14:14:00+01:00 | This is a test message |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_001 | Dismissed | 2023-08-09T14:11:02+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_002 | Active | 2023-08-04T17:30:10+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_001 | Dismissed | 2023-05-10T08:50:25+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_002 | Dismissed | 2023-07-19T13:26:01+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
||
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_001 | Dismissed | 2023-05-18T14:01:15+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_018 | Dismissed | 2023-07-19T13:23:52+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_017 | Dismissed | 2022-11-04T12:50:38+00:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_016 | Dismissed | 2022-09-20T14:16:02+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_015 | Dismissed | 2022-09-20T12:16:29+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_014 | Dismissed | 2022-08-05T16:52:37+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_013 | Dismissed | 2022-07-21T17:11:40+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_012 | Dismissed | 2022-06-17T11:53:11+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_011 | Dismissed | 2022-04-27T13:19:42+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_010 | Dismissed | 2022-03-29T16:49:45+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_009 | Dismissed | 2022-03-07T10:12:53+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_008 | Dismissed | 2022-02-07T16:15:11+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_007 | Dismissed | 2022-02-07T11:55:37+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_006 | Dismissed | 2022-01-13T17:07:41+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_005 | Dismissed | 2021-12-07T13:46:29+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_004 | Dismissed | 2021-11-30T10:14:00+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
|||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_003 | Dismissed | 2021-08-16T12:27:40+01:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
||||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_002 | Dismissed | 2021-03-09T13:55:35+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Seagreen wind energy Ltd |
Other_0000000000000000029_001 | Dismissed | 2021-03-09T13:41:20+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Other_0000000000000007814_002 | Inactive | 2023-07-06T01:02:32+01:00 | 2022-12-22T17:39:00+00:00 | 2023-07-06T00:00:00+01:00 | Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023 |
||||
Medway |
T_MEDP-1 |
Other_0000000000000007814_001 | Dismissed | 2022-12-22T17:45:01+00:00 | 2022-12-22T17:39:00+00:00 | 2023-07-06T00:00:00+01:00 | Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023 |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_009 | Dismissed | 2023-05-18T13:59:17+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_008 | Dismissed | 2023-05-16T09:17:28+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |