Market Participant Market Participant Code Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 >
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_014 Dismissed 2022-08-05T16:52:37+01:00 2021-03-09T13:33:00+00:00
Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_013 Dismissed 2022-07-21T17:11:40+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_012 Dismissed 2022-06-17T11:53:11+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_011 Dismissed 2022-04-27T13:19:42+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_010 Dismissed 2022-03-29T16:49:45+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_009 Dismissed 2022-03-07T10:12:53+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_008 Dismissed 2022-02-07T16:15:11+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_007 Dismissed 2022-02-07T11:55:37+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_006 Dismissed 2022-01-13T17:07:41+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_005 Dismissed 2021-12-07T13:46:29+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P Other_0000000000000000029_004 Dismissed 2021-11-30T10:14:00+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_003 Dismissed 2021-08-16T12:27:40+01:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_003 Inactive 2022-10-17T16:02:33+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_002 Dismissed 2022-10-17T14:46:02+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_001 Dismissed 2022-10-14T15:47:02+01:00 2022-10-14T15:35:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE GENERATION
48X000000000077M Other_0000000000000000040_002 Inactive 2022-08-26T09:01:54+01:00 2022-08-26T00:00:00+01:00 2022-08-26T08:00:00+01:00
Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage.
SSE GENERATION
48X000000000077M Other_0000000000000000040_001 Dismissed 2022-08-17T16:13:32+01:00 2022-08-26T00:00:00+01:00 2022-08-26T08:00:00+01:00
Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_003 Dismissed 2021-06-10T12:31:45+01:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_002 Dismissed 2021-03-01T15:11:31+00:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_001 Dismissed 2020-11-24T11:35:27+00:00 2021-12-09T23:59:00+00:00 2022-05-02T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M Other_0000000000000000031_006 Dismissed 2021-05-31T17:01:14+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M Other_0000000000000000031_005 Dismissed 2021-05-10T13:01:06+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M Other_0000000000000000031_004 Dismissed 2021-05-05T20:53:41+01:00 2021-05-12T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 12 May 2021. End date of 20 August 2021 remains unchanged. Original: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M Other_0000000000000000031_003 Dismissed 2021-05-04T10:57:17+01:00 2021-05-11T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 11 May 2021. End date of 20 August 2021 remains unchanged. Original Remarks: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M Other_0000000000000000031_002 Dismissed 2021-04-20T11:44:37+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
SSE GENERATION
48X000000000077M Other_0000000000000000031_001 Dismissed 2021-04-20T11:32:25+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
SSE GENERATION
48X000000000077M Other_0000000000000000037_002 Inactive 2021-05-22T00:01:53+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000037_001 Dismissed 2021-05-13T13:23:19+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000036_002 Inactive 2021-05-19T09:01:54+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000036_001 Dismissed 2021-05-13T13:22:03+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000035_002 Inactive 2021-05-17T09:01:53+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000035_001 Dismissed 2021-05-13T13:20:34+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000034_002 Inactive 2021-05-15T00:01:53+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000034_001 Dismissed 2021-05-12T13:04:36+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000033_002 Inactive 2021-05-14T00:01:52+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000033_001 Dismissed 2021-05-11T11:39:02+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M Other_0000000000000000032_002 Inactive 2021-05-13T00:01:51+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M Other_0000000000000000032_001 Dismissed 2021-05-10T12:49:52+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_003 Inactive 2021-01-11T01:02:32+00:00 2020-09-02T00:01:00+01:00 2021-01-10T23:59:00+00:00
Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_002 Dismissed 2020-09-01T13:43:16+01:00 2020-09-02T00:01:00+01:00 2021-01-10T23:59:00+00:00
Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_001 Dismissed 2020-08-20T08:26:48+01:00 2020-10-09T23:59:00+01:00 2021-03-08T14:00:00+00:00
A phased array test on Keadby GT1 R1 compressor blade root has identified a subsurface anomaly which needs to be monitored with further phase array tests in August and September. We will begin preparations for rectification of this issue from October 2020 onwards inline with the published outage program. Should the ongoing tests provide further information then we will adjust the outage program accordingly.
MEDWAY POWER LTD
48X000000000076O Other_0000000000000000028_002 Inactive 2020-12-01T20:01:53+00:00 2020-12-01T09:30:00+00:00 2020-12-01T19:00:00+00:00
Following PN to allow GT Tuning. some variation from PN expected.
MEDWAY POWER LTD
48X000000000076O Other_0000000000000000028_001 Dismissed 2020-12-01T09:29:14+00:00 2020-12-01T09:30:00+00:00 2020-12-01T19:00:00+00:00
Following PN to allow GT Tuning. some variation from PN expected.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_003 Inactive 2020-10-28T01:01:54+00:00 2020-10-26T07:45:00+00:00 2020-10-27T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_002 Dismissed 2020-10-26T09:06:10+00:00 2020-10-26T07:45:00+00:00 2020-10-27T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_001 Dismissed 2020-10-23T08:25:15+01:00 2020-10-25T07:45:00+00:00 2020-10-26T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000024_001 Active 2019-06-13T12:30:13+01:00 2019-06-13T12:30:00+01:00
Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020.
SSE GENERATION
48X000000000077M Other_0000000000000000018_002 Dismissed 2019-04-19T12:04:54+01:00 2019-04-19T09:08:00+01:00
SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications.