Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | |||||||||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_004 | Dismissed | 2022-09-20T12:19:09+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_003 | Dismissed | 2021-11-18T10:21:30+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
Other_0000000000000000038_002 | Dismissed | 2021-11-02T14:08:36+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Dogger Bank A |
Other_0000000000000000038_001 | Dismissed | 2021-11-02T11:32:15+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008120_001 | Active | 2023-05-10T08:47:39+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008119_001 | Active | 2023-05-10T08:46:36+01:00 | 2023-05-10T08:43:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
Tawnaghmore |
TAWN1 |
Other_0000000000000008024_002 | Inactive | 2023-03-16T09:40:56+00:00 | 2027-03-16T09:39:00+00:00 | 2027-03-16T09:40:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Tawnaghmore |
TAWN1 |
Other_0000000000000008024_001 | Dismissed | 2023-03-16T09:40:16+00:00 | 2027-03-16T09:39:00+00:00 | 2027-03-16T09:40:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Rhode |
RHODE1 |
Other_0000000000000008023_002 | Inactive | 2023-03-16T09:39:01+00:00 | 2027-03-16T09:37:00+00:00 | 2027-03-16T09:38:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Rhode |
RHODE1 |
Other_0000000000000008023_001 | Dismissed | 2023-03-16T09:38:18+00:00 | 2027-03-16T09:37:00+00:00 | 2027-03-16T09:38:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Tarbert |
TB3 |
Other_0000000000000008022_002 | Inactive | 2023-03-16T09:36:20+00:00 | 2027-03-16T09:33:00+00:00 | 2027-03-16T09:34:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Tarbert |
TB3 |
Other_0000000000000008022_001 | Dismissed | 2023-03-16T09:34:37+00:00 | 2027-03-16T09:33:00+00:00 | 2027-03-16T09:34:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Great Island |
Great Island |
Other_0000000000000008021_002 | Inactive | 2023-03-15T13:51:41+00:00 | 2027-03-15T13:47:00+00:00 | 2027-03-15T13:48:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Great Island |
Great Island |
Other_0000000000000008021_001 | Dismissed | 2023-03-15T13:49:55+00:00 | 2027-03-15T13:47:00+00:00 | 2027-03-15T13:48:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Great Island |
Great Island |
Other_0000000000000008020_002 | Inactive | 2023-03-15T12:11:38+00:00 | 2027-03-15T11:45:00+00:00 | 2027-03-15T11:46:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
Great Island |
Great Island |
Other_0000000000000008020_001 | Dismissed | 2023-03-15T11:40:21+00:00 | 2027-03-15T11:45:00+00:00 | 2027-03-15T11:46:00+00:00 | ***TEST ONLY*** Testing publishing Other Market Information at Unit level |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_011 | Dismissed | 2022-11-22T12:07:38+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-14T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_010 | Dismissed | 2022-09-21T16:51:34+01:00 | 2022-01-12T00:00:00+00:00 | 2023-01-10T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_009 | Dismissed | 2022-09-20T11:17:25+01:00 | 2022-01-12T00:00:00+00:00 | 2022-12-19T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_008 | Dismissed | 2022-09-15T16:20:45+01:00 | 2022-01-12T00:00:00+00:00 | 2022-11-14T23:59:00+00:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_007 | Dismissed | 2022-05-16T15:35:06+01:00 | 2022-01-12T00:00:00+00:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_006 | Dismissed | 2022-05-16T15:33:37+01:00 | 2022-05-23T00:00:00+01:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_005 | Inactive | 2023-03-15T10:02:32+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-15T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_005 | Dismissed | 2021-11-29T13:21:53+00:00 | 2022-05-23T00:00:00+01:00 | 2022-09-03T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_004 | Dismissed | 2021-09-07T16:27:51+01:00 | 2022-04-19T00:00:00+01:00 | 2022-07-31T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_004 | Dismissed | 2023-03-10T15:59:26+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-15T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_003 | Dismissed | 2021-08-05T16:06:16+01:00 | 2022-02-28T00:00:00+00:00 | 2022-07-21T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_003 | Dismissed | 2023-03-10T15:58:32+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-10T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_002 | Dismissed | 2023-02-06T08:49:47+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-12T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_002 | Dismissed | 2021-06-10T12:30:47+01:00 | 2022-02-09T00:00:00+00:00 | 2022-07-02T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Dismissed | 2022-12-19T16:02:46+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-11T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Dismissed | 2021-04-13T14:42:27+01:00 | 2022-01-06T00:00:00+00:00 | 2022-05-30T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000041_003 | Active | 2023-02-28T10:01:18+00:00 | 2022-09-01T00:00:00+01:00 | 2023-12-31T23:59:00+00:00 | Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000041_002 | Dismissed | 2022-09-02T09:34:18+01:00 | 2022-09-01T00:00:00+01:00 | 2023-12-31T23:59:00+00:00 | Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000041_001 | Dismissed | 2022-09-01T16:31:20+01:00 | 2024-01-01T00:00:00+00:00 | 2030-01-01T00:00:00+00:00 | Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly |
||
Viking Energy Wind Farm LLP |
48X000000000314Y | Other_0000000000000000039_003 | Active | 2023-02-10T11:57:40+00:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|||
Viking |
48X000000000314Y | Other_0000000000000000039_002 | Dismissed | 2022-09-20T12:28:17+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|||
Viking Wind Farm |
Other_0000000000000000039_001 | Dismissed | 2022-07-14T17:25:58+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
||||
Keadby |
T_KEAD-1 |
Other_0000000000000007785_001 | Dismissed | 2022-12-19T13:59:31+00:00 | 2025-03-01T13:53:00+00:00 | 2025-03-01T13:55:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
Keadby |
T_KEAD-1 |
Other_0000000000000007785_001 | Dismissed | 2022-12-21T11:51:47+00:00 | 2025-03-01T13:53:00+00:00 | 2025-03-01T13:55:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-21T11:51:24+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-19T14:04:00+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
Keadby |
T_KEAD-1 |
Other_0000000000000007760_001 | Dismissed | 2022-12-05T14:58:16+00:00 | 2026-12-06T00:00:00+00:00 | 2026-12-06T00:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
Keadby |
T_KEAD-1 |
Other_0000000000000007760_001 | Dismissed | 2022-12-05T14:44:18+00:00 | 2026-12-05T00:00:00+00:00 | 2026-12-05T00:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
Keadby |
T_KEAD-1 |
Other_0000000000000007760_001 | Dismissed | 2022-12-05T14:51:07+00:00 | 2026-12-06T00:00:00+00:00 | 2026-12-06T00:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:29:36+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:01+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:35:29+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|