Last update at: 2021-01-11T01:30:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_003 | Inactive | 2021-01-11T01:02:32+00:00 | 2020-09-02T00:01:00+01:00 | 2021-01-10T23:59:00+00:00 | Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_002 | Dismissed | 2020-09-01T13:43:16+01:00 | 2020-09-02T00:01:00+01:00 | 2021-01-10T23:59:00+00:00 | Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_001 | Dismissed | 2020-08-20T08:26:48+01:00 | 2020-10-09T23:59:00+01:00 | 2021-03-08T14:00:00+00:00 | A phased array test on Keadby GT1 R1 compressor blade root has identified a subsurface anomaly which needs to be monitored with further phase array tests in August and September. We will begin preparations for rectification of this issue from October 2020 onwards inline with the published outage program. Should the ongoing tests provide further information then we will adjust the outage program accordingly. |
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_002 | Inactive | 2020-12-01T20:01:53+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_001 | Dismissed | 2020-12-01T09:29:14+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_001 | Active | 2020-11-24T11:35:27+00:00 | 2021-12-09T23:59:00+00:00 | 2022-05-02T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000026_003 | Inactive | 2020-10-28T01:01:54+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000026_002 | Dismissed | 2020-10-26T09:06:10+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000026_001 | Dismissed | 2020-10-23T08:25:15+01:00 | 2020-10-25T07:45:00+00:00 | 2020-10-26T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000024_001 | Active | 2019-06-13T12:30:13+01:00 | 2019-06-13T12:30:00+01:00 | Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020. |
|
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000000023_002 | Inactive | 2019-05-18T15:02:31+01:00 | 2019-05-17T17:00:00+01:00 | 2019-05-18T14:00:00+01:00 | Due to major IT system changes within SSE from the evening of 17th of May & over the weekend, SSE’s participation in the N2EX UK Day-ahead auction on 18th of May (for volumes delivered on 19th) will be limited, compared to its usual participation levels. We expect all systems to be fully operational by 14:00 on 18th of May, so we anticipate normal participation in the auction on 19th of May (for volumes delivered on the 20th of May). |
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000000023_001 | Dismissed | 2019-05-17T13:32:36+01:00 | 2019-05-17T17:00:00+01:00 | 2019-05-18T14:00:00+01:00 | Due to major IT system changes within SSE from the evening of 17th of May & over the weekend, SSE’s participation in the N2EX UK Day-ahead auction on 18th of May (for volumes delivered on 19th) will be limited, compared to its usual participation levels. We expect all systems to be fully operational by 14:00 on 18th of May, so we anticipate normal participation in the auction on 19th of May (for volumes delivered on the 20th of May). |
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_002 | Dismissed | 2019-04-19T12:04:54+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_001 | Dismissed | 2019-04-19T09:10:02+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000019_001 | Active | 2019-04-19T12:04:36+01:00 | 2019-04-19T12:03:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_002 | Dismissed | 2019-04-19T09:08:42+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_001 | Dismissed | 2019-04-18T19:00:28+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000016_004 | Inactive | 2019-04-18T20:02:32+01:00 | 2019-04-18T11:00:00+01:00 | 2019-04-18T19:00:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications |
SSE GENERATION |
48X000000000077M | Other_0000000000000000016_003 | Dismissed | 2019-04-18T18:58:42+01:00 | 2019-04-18T11:00:00+01:00 | 2019-04-18T19:00:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications |
SSE GENERATION |
48X000000000077M | Other_0000000000000000016_002 | Dismissed | 2019-04-18T16:56:25+01:00 | 2019-04-18T11:00:00+01:00 | 2019-04-19T12:00:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications |
SSE GENERATION |
48X000000000077M | Other_0000000000000000016_001 | Dismissed | 2019-04-18T11:01:15+01:00 | 2019-04-18T11:00:00+01:00 | 2019-04-18T23:59:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000015_001 | Active | 2019-03-19T14:46:49+00:00 | 2019-03-19T12:55:00+00:00 | T_FIDL-1 - With immediate effect, unit 1 will be withdrawn from service. |
|
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000014_003 | Inactive | 2019-03-01T01:02:31+00:00 | 2019-02-12T23:00:00+00:00 | 2019-02-28T23:59:00+00:00 | Great Island availability currently limited to 225MW. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000014_002 | Dismissed | 2019-02-12T08:13:04+00:00 | 2019-02-12T23:00:00+00:00 | 2019-02-28T23:59:00+00:00 | Great Island availability currently limited to 225MW. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000014_001 | Dismissed | 2019-02-12T08:12:24+00:00 | 2019-02-12T23:00:00+00:00 | 2019-02-28T23:59:00+00:00 | Great Island Maximum Export Capacity currently limited to 225MW. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000013_002 | Inactive | 2018-12-23T12:02:32+00:00 | 2018-12-22T17:00:00+00:00 | 2018-12-23T10:59:00+00:00 | Great Island anticipated to commence on load test at 5pm |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000013_001 | Dismissed | 2018-12-22T15:14:46+00:00 | 2018-12-22T17:00:00+00:00 | 2018-12-23T10:59:00+00:00 | Great Island anticipated to commence on load test at 5pm |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_007 | Inactive | 2018-12-22T11:02:31+00:00 | 2018-12-20T12:00:00+00:00 | 2018-12-22T09:59:59+00:00 | Great Island (GI$, GU_400762) is seeking to perform on load testing from December 21st [17:30] until return time. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_006 | Dismissed | 2018-12-21T12:18:52+00:00 | 2018-12-20T12:00:00+00:00 | 2018-12-22T09:59:59+00:00 | Great Island (GI$, GU_400762) is seeking to perform on load testing from December 21st [17:30] until return time. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_005 | Dismissed | 2018-12-20T09:12:50+00:00 | 2018-12-20T12:00:00+00:00 | 2018-12-22T09:59:59+00:00 | Great Island (GI$, GU_400762) is seeking to perform on load testing from December 21st [06:00] until return time. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_004 | Dismissed | 2018-12-19T18:59:47+00:00 | 2018-12-20T12:00:00+00:00 | 2018-12-22T09:59:59+00:00 | Great Island (GI$, GU_400762) will undergo on load testing from 20th December [12:00] until return time. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_003 | Dismissed | 2018-12-19T08:55:42+00:00 | 2018-12-20T06:00:00+00:00 | 2018-12-22T02:59:59+00:00 | Great Island (GI$, GU_400762) will undergo on load testing from 20th December [06:00] until return time. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_002 | Dismissed | 2018-12-18T22:43:19+00:00 | 2018-12-19T12:00:00+00:00 | 2018-12-21T02:59:00+00:00 | Great Island (GI$, GU_400762) will undergo on load testing from 19th-21st December 2018. |
SSE Generation Ireland |
47X0000000000592 | Other_0000000000000000012_001 | Dismissed | 2018-12-04T12:05:06+00:00 | 2018-12-19T12:00:00+00:00 | 2018-12-21T09:59:00+00:00 | Great Island (GI$, GU_400762) will undergo on load testing from 19th-21st December 2018. |
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000000009_002 | Inactive | 2018-06-10T19:01:53+01:00 | 2018-06-08T18:00:00+01:00 | 2018-06-10T18:00:00+01:00 | Due to major IT system changes within SSE from the evening of 8th of June & over the weekend, SSE’s participation in the N2EX UK Day-ahead auction on 9th of June (for volumes delivered on 10th) and 10th of June (for volumes delivered on 11th) will be limited, compared to its usual participation levels. We expect all systems to be fully operational by 18:00 on 10th of June, so we anticipate normal participation in the auction on 11th of June (for volumes delivered on the 12th of June). |
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000000009_001 | Dismissed | 2018-06-06T12:04:29+01:00 | 2018-06-08T18:00:00+01:00 | 2018-06-10T18:00:00+01:00 | Due to major IT system changes within SSE from the evening of 8th of June & over the weekend, SSE’s participation in the N2EX UK Day-ahead auction on 9th of June (for volumes delivered on 10th) and 10th of June (for volumes delivered on 11th) will be limited, compared to its usual participation levels. We expect all systems to be fully operational by 18:00 on 10th of June, so we anticipate normal participation in the auction on 11th of June (for volumes delivered on the 12th of June). |
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_003 | Active | 2017-12-19T12:08:01+00:00 | 2018-04-01T00:00:00+01:00 | Peterhead TEC has been increased to 1180MW on an enduring basis from 1st April 2018 and will continue operations at 1180MW going forward. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_002 | Dismissed | 2017-11-07T13:55:07+00:00 | 2018-04-01T00:00:00+01:00 | Subject to CMP268 not being legally challenged, we intend to increase TEC at Peterhead to 1180MW on an enduring basis commencing 1st April 2018 and continue operations at 1180MW going forward. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_001 | Dismissed | 2017-03-23T14:04:44+00:00 | 2018-04-01T00:00:00+01:00 | From the 1st April 2018 we will be reducing the TEC at Peterhead to zero. The cancellation of our TEC at this time is a risk mitigation measure to avoid a substantial cancellation charge if we were to cancel later in the year, once we have completed our review of the stations future, which we announced on 6 February 2017. We will reapply for TEC and subject to receiving a satisfactory offer from NGET, reinstate TEC should our review conclude that the station has an enduring future. |
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000008_002 | Dismissed | 2017-11-03T14:45:48+00:00 | 2017-10-16T09:30:00+01:00 | 2018-04-01T00:00:00+01:00 | SSE Generation is applying to increase TEC at Fiddlers Ferry to 1834MW over the remainder of Winter ’17 |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000008_001 | Dismissed | 2017-10-16T09:32:01+01:00 | 2017-10-16T09:30:00+01:00 | 2018-04-01T00:00:00+01:00 | SSE Generation is applying to increase TEC at Fiddlers Ferry to 1834MW over the remainder of Winter ’17 |
SSE GENERATION |
48X000000000077M | Other_0000000000000000007_004 | Inactive | 2017-09-11T11:11:52+01:00 | 2017-10-02T00:00:00+01:00 | 2018-04-01T00:00:00+01:00 | SSE Generation is applying to increase TEC at Peterhead to 1180MW over Winter ‘17. SSE currently anticipates having available capacity of 1180MW from 2 October 2017 to 31 March 2018 |
SSE GENERATION |
48X000000000077M | Other_0000000000000000007_003 | Dismissed | 2017-07-20T08:59:00+01:00 | 2017-10-02T00:00:00+01:00 | 2018-04-01T00:00:00+01:00 | SSE Generation is applying to increase TEC at Peterhead to 1180MW over Winter ‘17. SSE currently anticipates having available capacity of 1180MW from 2 October 2017 to 31 March 2018 |
SSE GENERATION |
48X000000000077M | Other_0000000000000000007_002 | Dismissed | 2017-07-13T15:20:26+01:00 | 2017-10-01T00:00:00+01:00 | 2018-04-01T00:00:00+01:00 | SSE Generation is applying to increase TEC at Peterhead to 1180MW over Winter ‘17. SSE currently anticipates having available capacity of 1180MW from 1 October 2017 to 31 March 2018 |
SSE GENERATION |
48X000000000077M | Other_0000000000000000007_001 | Dismissed | 2017-07-13T08:53:19+01:00 | 2017-10-01T00:00:00+01:00 | 2018-03-31T23:59:00+01:00 | SSE Generation is applying to increase TEC at Peterhead to 1180MW over Winter ‘17. SSE currently anticipates having available capacity of 1180MW from 1 October 2017 to 31 March 2018 |