Last update at: 2023-11-22T01:30:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
1 2 3 4 5 > | |||||||||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000008178_002 | Inactive | 2023-11-22T01:02:36+00:00 | 2023-11-14T00:00:00+00:00 | 2023-11-21T23:59:00+00:00 | Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000008178_001 | Dismissed | 2023-06-07T16:31:26+01:00 | 2023-11-14T00:00:00+00:00 | 2023-11-21T23:59:00+00:00 | Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed. |
||
Doggerbank Offshore Wind Farm Project 2 Projco Limited |
48X0000000003121 | Other_0000000000000008538_001 | Active | 2023-11-10T15:42:44+00:00 | 2023-11-10T12:44:00+00:00 | 2024-12-31T00:00:00+00:00 | It is expected that Dogger Bank B commissioning will start in H2 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000008476_002 | Inactive | 2023-10-24T23:47:32+01:00 | 2023-10-24T22:36:00+01:00 | 2023-10-24T22:40:00+01:00 | end of outage |
||
SSE Energy Supply Limited |
A0001004V.UK | Other_0000000000000008476_001 | Dismissed | 2023-10-24T22:39:53+01:00 | 2023-10-24T22:36:00+01:00 | 2023-10-24T22:40:00+01:00 | end of outage |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_039 | Dismissed | 2023-10-07T21:51:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | Other market information message withdrawn with first generation achieved 07/10/23 All REMIT submitted by BMU on SSE Remit portal. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_038 | Dismissed | 2023-10-06T16:23:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_037 | Dismissed | 2023-10-06T15:46:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_036 | Dismissed | 2023-10-06T15:08:54+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_035 | Dismissed | 2023-10-05T16:49:11+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_034 | Dismissed | 2023-10-03T16:16:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_033 | Dismissed | 2023-10-03T11:39:12+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T20:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_032 | Dismissed | 2023-10-03T07:08:50+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T12:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_031 | Dismissed | 2023-10-02T08:51:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_030 | Dismissed | 2023-10-01T17:10:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_029 | Dismissed | 2023-09-30T16:22:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-02T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 02nd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_028 | Dismissed | 2023-09-29T16:49:18+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-30T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 30th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_027 | Dismissed | 2023-09-28T14:32:16+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-29T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 29th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_026 | Dismissed | 2023-09-27T15:26:24+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-28T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 28th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_025 | Dismissed | 2023-09-26T15:41:57+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_024 | Dismissed | 2023-09-25T17:45:52+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_023 | Dismissed | 2023-09-23T12:53:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-26T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_022 | Dismissed | 2023-09-22T17:41:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_021 | Dismissed | 2023-09-19T18:32:22+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_020 | Dismissed | 2023-09-18T17:45:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-20T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_019 | Dismissed | 2023-09-17T18:18:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-19T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_018 | Dismissed | 2023-09-14T21:28:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-18T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_017 | Dismissed | 2023-09-12T08:50:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:45:43+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:48:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:14+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_014 | Dismissed | 2023-09-05T17:41:03+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_013 | Dismissed | 2023-08-30T16:05:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-06T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_012 | Dismissed | 2023-08-25T21:32:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_011 | Dismissed | 2023-08-25T10:13:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_010 | Dismissed | 2023-08-22T11:18:09+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_009 | Dismissed | 2023-08-18T09:18:00+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-23T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_008 | Dismissed | 2023-08-14T14:39:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-20T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_007 | Dismissed | 2023-08-09T17:31:28+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-15T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_006 | Dismissed | 2023-08-04T15:49:36+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-11T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_005 | Dismissed | 2023-08-01T14:41:23+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-07T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_004 | Dismissed | 2023-07-28T16:16:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_003 | Dismissed | 2023-07-28T16:14:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_002 | Dismissed | 2023-07-24T13:53:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_001 | Dismissed | 2023-07-18T13:28:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-07-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Great Island |
Great Island |
Other_0000000000000008475_002 | Active | 2023-10-02T17:20:09+01:00 | 2023-10-02T17:05:00+01:00 | 2024-05-17T22:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
Great Island |
Great Island |
Other_0000000000000008475_001 | Dismissed | 2023-10-02T17:06:20+01:00 | 2023-10-02T17:05:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
|||
Great Island |
Great Island |
Other_0000000000000008203_004 | Dismissed | 2023-10-02T17:07:15+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Great Island |
Great Island |
Other_0000000000000008203_003 | Dismissed | 2023-07-27T12:34:51+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |