Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 1 2 3 4 5 >
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009530_003 Dismissed Planned Production unavailability 2024-10-18T17:30:46+01:00 2024-10-13T08:00:00+01:00 2024-10-18T19:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009530_002 Dismissed Planned Production unavailability 2024-10-18T14:41:38+01:00 2024-10-13T08:00:00+01:00 2024-10-18T18:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009530_001 Dismissed Planned Production unavailability 2024-10-09T10:15:40+01:00 2024-10-13T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_008 Inactive Planned Production unavailability 2024-10-18T18:02:32+01:00 2024-09-20T23:00:00+01:00 2024-10-18T17:00:00+01:00 MW 66 91 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_007 Dismissed Planned Production unavailability 2024-10-11T14:00:34+01:00 2024-09-20T23:00:00+01:00 2024-10-18T17:00:00+01:00 MW 66 91 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_007 Inactive Planned Production unavailability 2024-10-18T18:02:32+01:00 2024-09-20T23:00:00+01:00 2024-10-18T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_006 Dismissed Planned Production unavailability 2024-10-04T11:30:37+01:00 2024-09-20T23:00:00+01:00 2024-10-11T17:00:00+01:00 MW 66 91 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_006 Dismissed Planned Production unavailability 2024-10-11T14:00:14+01:00 2024-09-20T23:00:00+01:00 2024-10-18T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_005 Dismissed Planned Production unavailability 2024-10-04T11:31:54+01:00 2024-09-20T23:00:00+01:00 2024-10-11T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_005 Dismissed Planned Production unavailability 2024-10-03T12:19:37+01:00 2024-09-20T23:00:00+01:00 2024-10-04T17:00:00+01:00 MW 157 0 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_004 Dismissed Planned Production unavailability 2024-10-03T12:19:37+01:00 2024-09-20T23:00:00+01:00 2024-10-04T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_004 Dismissed Planned Production unavailability 2024-10-01T10:55:08+01:00 2024-09-20T23:00:00+01:00 2024-10-04T17:00:00+01:00 MW 157 0 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_003 Dismissed Planned Production unavailability 2024-09-27T12:35:26+01:00 2024-09-20T23:00:00+01:00 2024-10-04T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_003 Dismissed Planned Production unavailability 2024-09-27T12:35:15+01:00 2024-09-20T23:00:00+01:00 2024-10-04T17:00:00+01:00 MW 105 52 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_002 Dismissed Planned Production unavailability 2024-09-20T13:59:06+01:00 2024-09-20T23:00:00+01:00 2024-09-27T17:00:00+01:00 MW 118 39 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_002 Dismissed Planned Production unavailability 2024-09-20T13:58:44+01:00 2024-09-20T23:00:00+01:00 2024-09-27T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-2 48W00000DBAWO-2H
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009454_001 Dismissed Planned Production unavailability 2024-09-20T10:49:52+01:00 2024-09-20T20:00:00+01:00 2024-09-27T17:00:00+01:00 MW 39 0 39 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_DBAWO-1 48W00000DBAWO-1J
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000009453_001 Dismissed Planned Production unavailability 2024-09-20T10:48:35+01:00 2024-09-20T20:00:00+01:00 2024-09-27T17:00:00+01:00 MW 118 39 157 Shutdown
Commissioning
Wind Offshore 10YGB----------A
T_VKNGW-1 48W00000VKNGW-14
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009413_003 Inactive Planned Production unavailability 2024-10-18T17:02:32+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-2 48W00000VKNGW-22
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009414_003 Inactive Planned Production unavailability 2024-10-18T17:02:32+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009415_003 Inactive Planned Production unavailability 2024-10-18T17:02:32+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-4 48W00000VKNGW-4Z
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009416_003 Inactive Planned Production unavailability 2024-10-18T17:02:32+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009415_002 Dismissed Planned Production unavailability 2024-10-03T12:21:00+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-4 48W00000VKNGW-4Z
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009416_002 Dismissed Planned Production unavailability 2024-10-03T12:21:00+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-1 48W00000VKNGW-14
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009413_002 Dismissed Planned Production unavailability 2024-10-03T12:21:00+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-2 48W00000VKNGW-22
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009414_002 Dismissed Planned Production unavailability 2024-10-03T12:21:00+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-2 48W00000VKNGW-22
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009414_001 Dismissed Planned Production unavailability 2024-09-13T11:17:59+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-3 48W00000VKNGW-30
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009415_001 Dismissed Planned Production unavailability 2024-09-13T11:18:56+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-4 48W00000VKNGW-4Z
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009416_001 Dismissed Planned Production unavailability 2024-09-13T11:19:56+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_VKNGW-1 48W00000VKNGW-14
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009413_001 Dismissed Planned Production unavailability 2024-09-13T11:16:46+01:00 2024-10-15T08:00:00+01:00 2024-10-18T16:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009552_004 Inactive Planned Production unavailability 2024-10-18T16:17:33+01:00 2024-10-17T16:15:00+01:00 2024-10-18T15:10:00+01:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009552_003 Dismissed Planned Production unavailability 2024-10-18T15:08:59+01:00 2024-10-17T16:15:00+01:00 2024-10-18T15:10:00+01:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009552_002 Dismissed Planned Production unavailability 2024-10-18T13:43:20+01:00 2024-10-17T16:15:00+01:00 2024-10-18T16:00:00+01:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009552_001 Dismissed Planned Production unavailability 2024-10-17T15:18:04+01:00 2024-10-17T16:15:00+01:00 2024-10-18T20:00:00+01:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009550_002 Inactive Planned Production unavailability 2024-10-17T17:17:32+01:00 2024-10-17T15:25:00+01:00 2024-10-17T16:15:00+01:00 MW 820 360 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009550_001 Dismissed Planned Production unavailability 2024-10-17T14:55:27+01:00 2024-10-17T15:25:00+01:00 2024-10-17T16:15:00+01:00 MW 820 360 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009549_004 Inactive Unplanned Production unavailability 2024-10-17T16:32:32+01:00 2024-10-17T13:00:00+01:00 2024-10-17T15:25:00+01:00 MW 900 280 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009549_003 Dismissed Unplanned Production unavailability 2024-10-17T14:16:00+01:00 2024-10-17T13:00:00+01:00 2024-10-17T15:25:00+01:00 MW 900 280 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009549_002 Dismissed Unplanned Production unavailability 2024-10-17T13:40:41+01:00 2024-10-17T13:00:00+01:00 2024-10-17T14:15:00+01:00 MW 1180 0 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009551_002 Inactive Unplanned Production unavailability 2024-10-17T16:32:32+01:00 2024-10-17T14:56:00+01:00 2024-10-17T15:25:00+01:00 MW 755 0 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009551_001 Dismissed Unplanned Production unavailability 2024-10-17T14:56:29+01:00 2024-10-17T14:56:00+01:00 2024-10-17T15:25:00+01:00 MW 755 0 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000009549_001 Dismissed Unplanned Production unavailability 2024-10-17T13:05:23+01:00 2024-10-17T13:00:00+01:00 2024-10-17T13:45:00+01:00 MW 1180 0 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_008 Active Planned Production unavailability 2024-10-17T13:44:20+01:00 2024-08-27T08:00:00+01:00 2024-12-31T18:00:00+00:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_007 Dismissed Planned Production unavailability 2024-10-03T12:22:29+01:00 2024-08-27T08:00:00+01:00 2024-10-30T18:00:00+00:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_006 Dismissed Planned Production unavailability 2024-09-24T09:46:54+01:00 2024-08-27T08:00:00+01:00 2024-10-30T18:00:00+00:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_005 Dismissed Planned Production unavailability 2024-09-05T14:06:13+01:00 2024-08-27T08:00:00+01:00 2024-09-30T18:00:00+01:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_004 Dismissed Planned Production unavailability 2024-09-02T10:12:00+01:00 2024-08-27T08:00:00+01:00 2024-09-10T18:00:00+01:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_003 Dismissed Planned Production unavailability 2024-08-30T17:01:58+01:00 2024-08-27T08:00:00+01:00 2024-09-03T18:00:00+01:00 MW 165 0 165 Foreseen Maintenance
Outage Overrun
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_002 Dismissed Planned Production unavailability 2024-08-20T18:07:36+01:00 2024-08-27T08:00:00+01:00 2024-08-31T08:00:00+01:00 MW 165 0 165 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_GRGBW-3 48W00000GRGBW-3R
Greater Gabbard Offshore Winds Limited
48X000000000331Y 0000000000000000000009326_001 Dismissed Planned Production unavailability 2024-08-06T17:27:13+01:00 2024-08-26T07:00:00+01:00 2024-08-30T16:00:00+01:00 MW 165 0 165 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A