| Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 2 3 4 5 > | ||||||||||||||||||
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_007 | Active | Planned | Production unavailability | 2026-06-12T11:12:27+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T14:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_006 | Dismissed | Planned | Production unavailability | 2026-06-12T09:19:16+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T15:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_005 | Dismissed | Planned | Production unavailability | 2026-06-11T14:16:19+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T18:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_004 | Dismissed | Planned | Production unavailability | 2026-05-06T11:06:10+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_003 | Dismissed | Planned | Production unavailability | 2026-04-20T15:44:20+01:00 | 2026-06-08T07:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_002 | Dismissed | Planned | Production unavailability | 2026-03-17T16:21:35+00:00 | 2026-06-01T07:00:00+01:00 | 2026-06-10T19:30:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010720_001 | Dismissed | Planned | Production unavailability | 2025-12-02T17:26:08+00:00 | 2026-05-20T06:00:00+01:00 | 2026-05-29T06:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_007 | Active | Planned | Production unavailability | 2026-06-12T11:12:08+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T14:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_006 | Dismissed | Planned | Production unavailability | 2026-06-12T09:21:01+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T15:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_005 | Dismissed | Planned | Production unavailability | 2026-06-11T14:15:38+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T18:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_004 | Dismissed | Planned | Production unavailability | 2026-05-06T11:06:32+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_003 | Dismissed | Planned | Production unavailability | 2026-04-20T15:43:35+01:00 | 2026-06-08T07:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_002 | Dismissed | Planned | Production unavailability | 2026-03-17T16:22:17+00:00 | 2026-06-01T07:00:00+01:00 | 2026-06-10T19:30:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010721_001 | Dismissed | Planned | Production unavailability | 2025-12-02T17:27:43+00:00 | 2026-05-20T06:00:00+01:00 | 2026-05-29T06:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_007 | Active | Planned | Production unavailability | 2026-06-12T11:11:50+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T14:30:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_006 | Dismissed | Planned | Production unavailability | 2026-06-12T09:21:30+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T15:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_005 | Dismissed | Planned | Production unavailability | 2026-06-11T14:15:04+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-12T18:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_004 | Dismissed | Planned | Production unavailability | 2026-05-06T11:06:56+01:00 | 2026-06-08T08:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_003 | Dismissed | Planned | Production unavailability | 2026-04-20T15:42:30+01:00 | 2026-06-08T07:00:00+01:00 | 2026-06-13T19:30:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_002 | Dismissed | Planned | Production unavailability | 2026-03-17T16:23:08+00:00 | 2026-06-01T07:00:00+01:00 | 2026-06-10T19:30:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010722_001 | Dismissed | Planned | Production unavailability | 2025-12-02T17:29:17+00:00 | 2026-05-20T06:00:00+01:00 | 2026-05-29T06:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010994_002 | Dismissed | Planned | Production unavailability | 2026-06-09T16:42:34+01:00 | 2026-06-10T09:00:23+01:00 | 2026-06-10T18:00:29+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010994_001 | Dismissed | Planned | Production unavailability | 2026-06-02T08:38:58+01:00 | 2026-06-10T09:00:23+01:00 | 2026-06-10T18:00:29+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010995_002 | Dismissed | Planned | Consumption unavailability | 2026-06-09T16:42:15+01:00 | 2026-06-10T09:00:28+01:00 | 2026-06-10T18:00:35+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010995_001 | Dismissed | Planned | Consumption unavailability | 2026-06-02T08:39:58+01:00 | 2026-06-10T09:00:28+01:00 | 2026-06-10T18:00:35+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010996_002 | Dismissed | Planned | Production unavailability | 2026-06-09T16:41:50+01:00 | 2026-06-10T09:00:06+01:00 | 2026-06-10T18:00:11+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010996_001 | Dismissed | Planned | Production unavailability | 2026-06-02T08:42:40+01:00 | 2026-06-10T09:00:06+01:00 | 2026-06-10T18:00:11+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010997_002 | Dismissed | Planned | Consumption unavailability | 2026-06-09T16:41:25+01:00 | 2026-06-10T09:00:19+01:00 | 2026-06-10T18:00:24+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010997_001 | Dismissed | Planned | Consumption unavailability | 2026-06-02T08:43:46+01:00 | 2026-06-10T09:00:19+01:00 | 2026-06-10T18:00:24+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010998_002 | Dismissed | Planned | Production unavailability | 2026-06-09T16:40:37+01:00 | 2026-06-11T09:00:37+01:00 | 2026-06-11T18:00:45+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010998_001 | Dismissed | Planned | Production unavailability | 2026-06-02T08:45:14+01:00 | 2026-06-11T09:00:37+01:00 | 2026-06-11T18:00:45+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010999_002 | Dismissed | Planned | Consumption unavailability | 2026-06-09T16:40:06+01:00 | 2026-06-11T09:00:39+01:00 | 2026-06-11T18:00:47+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-1 | 48W00000FERRB-1V | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000010999_001 | Dismissed | Planned | Consumption unavailability | 2026-06-02T08:46:18+01:00 | 2026-06-11T09:00:39+01:00 | 2026-06-11T18:00:47+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000011000_002 | Dismissed | Planned | Consumption unavailability | 2026-06-09T16:39:17+01:00 | 2026-06-11T09:00:46+01:00 | 2026-06-11T18:00:52+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000011000_001 | Dismissed | Planned | Consumption unavailability | 2026-06-02T08:47:23+01:00 | 2026-06-11T09:00:46+01:00 | 2026-06-11T18:00:52+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000011001_003 | Dismissed | Planned | Production unavailability | 2026-06-09T16:37:31+01:00 | 2026-06-11T09:00:52+01:00 | 2026-06-11T18:00:59+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000011001_002 | Dismissed | Planned | Production unavailability | 2026-06-02T08:49:00+01:00 | 2026-06-11T09:00:52+01:00 | 2026-06-11T18:00:59+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| T_FERRB-2 | 48W00000FERRB-2T | SSE Battery Salisbury Limited |
48X0000000000319 | 0000000000000000000011001_001 | Dismissed | Planned | Consumption unavailability | 2026-06-02T08:48:18+01:00 | 2026-06-11T09:00:52+01:00 | 2026-06-11T18:00:59+01:00 | MW | 75 | 0 | 75 | Foreseen Maintenance | Maintenance |
Other | 10YGB----------A |
| Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000011014_001 | Active | Planned | Production unavailability | 2026-06-09T13:54:17+01:00 | 2026-06-24T08:30:00+01:00 | 2026-06-24T16:30:00+01:00 | MW | 59 | 0 | 59 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011013_001 | Active | Planned | Production unavailability | 2026-06-05T16:41:33+01:00 | 2026-08-15T07:30:59+01:00 | 2026-09-03T17:00:14+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011012_001 | Active | Planned | Production unavailability | 2026-06-05T16:39:03+01:00 | 2026-08-15T07:30:25+01:00 | 2026-09-03T17:00:37+01:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011011_001 | Active | Planned | Production unavailability | 2026-06-05T16:35:42+01:00 | 2026-08-13T07:30:06+01:00 | 2026-08-13T17:00:23+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011010_001 | Active | Planned | Production unavailability | 2026-06-05T16:34:40+01:00 | 2026-08-13T07:30:59+01:00 | 2026-08-13T17:00:18+01:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011009_001 | Active | Planned | Production unavailability | 2026-06-05T16:33:31+01:00 | 2026-07-28T07:30:43+01:00 | 2026-07-29T17:00:59+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011008_001 | Active | Planned | Production unavailability | 2026-06-05T16:32:15+01:00 | 2026-07-28T07:30:06+01:00 | 2026-07-29T17:00:28+01:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011007_001 | Active | Planned | Production unavailability | 2026-06-05T16:30:05+01:00 | 2026-06-25T07:30:13+01:00 | 2026-06-26T17:00:33+01:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000011006_001 | Active | Planned | Production unavailability | 2026-06-05T16:28:47+01:00 | 2026-06-25T07:30:00+01:00 | 2026-06-26T17:00:00+01:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010719_015 | Active | Planned | Production unavailability | 2026-06-05T13:56:19+01:00 | 2026-05-25T08:00:00+01:00 | 2026-06-05T16:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010719_014 | Dismissed | Planned | Production unavailability | 2026-06-05T07:59:11+01:00 | 2026-05-25T08:00:00+01:00 | 2026-06-05T15:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010719_013 | Dismissed | Planned | Production unavailability | 2026-06-05T01:24:13+01:00 | 2026-05-25T08:00:00+01:00 | 2026-06-05T12:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |