SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2026-02-02T16:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 3 4 5 6 7 >
Other_0000000000000009284_005 Dismissed 2025-06-09T01:48:55+00:00 2024-08-02T00:00:00+00:00 2025-06-10T09:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_004 Dismissed 2025-06-09T00:24:09+00:00 2024-08-02T00:00:00+00:00 2025-06-10T01:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_003 Dismissed 2025-05-31T12:59:58+00:00 2024-08-02T00:00:00+00:00 2025-06-09T23:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_002 Dismissed 2024-11-11T14:44:45+00:00 2024-08-02T00:00:00+00:00 2025-06-06T23:59:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_001 Dismissed 2024-07-29T14:17:35+00:00 2024-08-02T00:00:00+00:00 2025-04-30T00:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
SSE GENERATION
48X000000000077M
Other_0000000000000010181_005 Dismissed 2025-06-03T14:38:30+00:00 2025-05-29T07:00:00+00:00 2025-06-06T21:00:00+00:00
Between 29/05/25 & 6/06/25 Foyers M1 & M2 will carry out test runs of pump & generation capability as part of post fault recommissioning of GT2. Test program is subject to suitable grid conditions and water storage positions with testing expected to take place daily between 07:00 & 21:00. M1 & M2 will be available intermittently during the testing period. M1 should be available to market out with testing period. This information is disclosed in accordance with Article 4 of REMIT
SSE GENERATION
48X000000000077M
Other_0000000000000010181_004 Dismissed 2025-05-29T11:56:09+00:00 2025-05-29T07:00:00+00:00 2025-06-06T21:00:00+00:00
Between 29/05/25 & 6/06/25 Foyers M1 & M2 will carry out test runs of pump & generation capability as part of post fault recommissioning of GT2. Test program is subject to suitable grid conditions and water storage positions with testing expected to take place daily between 07:00 & 21:00. M1 & M2 will be available intermittently during the testing period. M1 should be available to market out with testing period. This information is disclosed in accordance with Article 4 of REMIT
SSE GENERATION
48X000000000077M
Other_0000000000000010181_003 Dismissed 2025-05-29T08:26:24+00:00 2025-05-29T07:00:00+00:00 2025-06-06T21:00:00+00:00
Between 29/05/25 & 6/06/25 Foyers M1 & M2 will carry out test runs of pump & generation capability as part of post fault recommissioning of GT2. Test program is subject to suitable grid conditions and water storage positions with testing expected to take place daily between 07:00 & 21:00. M2 will not be commercially available for the duration of the testing, M1 should be available to the market out with the daily testing window. This information is disclosed in accordance with Article 4 of REMIT
SSE GENERATION
48X000000000077M
Other_0000000000000010181_002 Dismissed 2025-05-27T10:31:58+00:00 2025-05-29T09:00:00+00:00 2025-06-06T21:00:00+00:00
Between 29/05/25 & 6/06/25 Foyers M1 & M2 will carry out test runs of pump & generation capability as part of post fault recommissioning of GT2. Test program is subject to suitable grid conditions and water storage positions with testing expected to take place daily between 07:00 & 21:00. M2 will not be commercially available for the duration of the testing, M1 should be available to the market out with the daily testing window. This information is disclosed in accordance with Article 4 of REMIT
SSE GENERATION
48X000000000077M
Other_0000000000000010181_001 Dismissed 2025-05-27T10:28:03+00:00 2025-05-29T09:00:00+00:00 2025-06-06T21:00:00+00:00
Between 29/05/25 & 6/05/25 Foyers M1 & M2 will carry out test runs of pump & generation capability as part of post fault recommissioning of GT2. Test program is subject to suitable grid conditions and water storage positions with testing expected to take place daily between 07:00 & 21:00. M2 will not be commercially available for the duration of the testing, M1 should be available to the market out with the daily testing window. This information is disclosed in accordance with Article 4 of REMIT
Other_0000000000000010169_003 Inactive 2025-05-28T18:02:32+00:00 2025-05-28T13:15:00+00:00 2025-05-28T17:00:00+00:00
Other Market Information message withdrawn – site commissioning complete.
Other_0000000000000010152_002 Inactive 2025-05-23T00:02:32+00:00 2025-05-20T10:00:25+00:00 2025-05-22T23:00:37+00:00
Medway will be carrying out a full speed no load run on 20/05/2025. On completion NDZ value will increase to 720minutes until the start of our planned outage, 23:00 22/05/2025
Other_0000000000000010152_001 Dismissed 2025-05-15T15:58:37+00:00 2025-05-20T10:00:25+00:00 2025-05-22T23:00:37+00:00
Medway will be carrying out a full speed no load run on 20/05/2025. On completion NDZ value will increase to 720minutes until the start of our planned outage, 23:00 22/05/2025
Other_0000000000000010142_002 Inactive 2025-05-14T18:02:32+00:00 2025-05-12T16:00:00+00:00 2025-05-14T17:00:00+00:00
#Commissioning# Current capacity 86MW. Commissioning is scheduled to conclude Q2 2025. Anticipated increase to 101MW on 14/05/2025
Other_0000000000000010099_004 Inactive 2025-05-10T01:02:32+00:00 2025-05-08T23:59:00+00:00 2025-05-09T23:59:00+00:00
For the last shutdown that is within 24 hours prior to the start of the planned outage with a commencement time of 23:59hrs on 09/05/2025, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000010099_003 Dismissed 2025-05-01T10:21:43+00:00 2025-05-08T23:59:00+00:00 2025-05-09T23:59:00+00:00
For the last shutdown that is within 24 hours prior to the start of the planned outage with a commencement time of 23:59hrs on 09/05/2025, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000010099_002 Dismissed 2025-05-01T10:15:16+00:00 2025-05-08T23:59:00+00:00 2025-05-09T23:59:00+00:00
For the last shutdown that is within 24 hours prior to the start of the planned outage with a commencement time of 23:59hrs on 02/05/2025, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000010099_001 Dismissed 2025-04-28T17:31:19+00:00 2025-05-01T23:59:00+00:00 2025-05-02T23:59:00+00:00
For the last shutdown that is within 24 hours prior to the start of the planned outage with a commencement time of 23:59hrs on 02/05/2025, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000010123_002 Inactive 2025-05-10T01:02:32+00:00 2025-05-08T23:59:24+00:00 2025-05-10T00:00:56+00:00
T_PEHE-1 running out of merit in 2+1 configuration circa 780MW due to allow recovery from fuel supply issues.
Other_0000000000000010123_001 Dismissed 2025-05-08T09:20:07+00:00 2025-05-08T23:59:24+00:00 2025-05-10T00:00:56+00:00
T_PEHE-1 running out of merit in 2+1 configuration circa 780MW due to allow recovery from fuel supply issues.
Other_0000000000000009955_002 Inactive 2025-04-02T20:02:32+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000009955_001 Dismissed 2025-03-06T17:04:05+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000009850_013 Inactive 2025-03-31T17:02:32+00:00 2025-01-27T09:25:54+00:00 2025-03-31T16:00:00+00:00
#Commissioning# Current capacity 86MW. Commissioning is scheduled to conclude early Q2 2025.
Other_0000000000000009990_001 Active 2025-03-14T13:00:47+00:00 2025-03-14T12:30:39+00:00
Site is not yet operational but is agreed to be available for emergency dispatch if instructed by EirGrid in line with CRU202346
Other_0000000000000009887_002 Inactive 2025-02-07T10:02:32+00:00 2025-02-06T11:00:00+00:00 2025-02-07T09:00:00+00:00
Due to plant fault, unit currently cannot be restarted. REMIT entered for testing and repair works on Friday 7th of Feb 2025
Other_0000000000000009887_001 Dismissed 2025-02-06T11:00:25+00:00 2025-02-06T11:00:00+00:00 2025-02-07T09:00:00+00:00
Due to plant fault, unit currently cannot be restarted. REMIT entered for testing and repair works on Friday 7th of Feb 2025
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000009881_001 Active 2025-02-04T09:55:51+00:00 2025-02-04T09:55:38+00:00
Tarbert Next Generation biofuel station GU_405790 has now moved to enabling works ahead of construction and commissioning. Planned completion is expected by end of 2027. The unit has received an extension to key CRM milestones from the CRU.
Other_0000000000000009755_004 Dismissed 2025-01-10T13:31:15+00:00 2025-01-11T00:00:00+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 11th & 12th Jan '25.
Other_0000000000000009755_003 Dismissed 2025-01-08T13:00:54+00:00 2025-01-11T00:00:00+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 11th & 12th Jan '25.
Other_0000000000000009755_002 Dismissed 2025-01-07T09:06:15+00:00 2025-01-10T00:00:06+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 10th, 11th & 12th Jan '25.
Other_0000000000000009755_001 Dismissed 2024-12-23T10:32:20+00:00 2025-01-10T00:00:06+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate at MEL in 1+1 configuration for a minimum of 2hrs commencing 4pm on the 10th, 11th & 12th Jan '25.
Other_0000000000000009790_002 Dismissed 2025-01-09T08:28:08+00:00 2025-01-09T00:00:00+00:00 2025-01-09T23:59:59+00:00
For commissioning and gas turbine tuning purposes Keadby 2 will be operating at reduced loads for periods of time. These periods will be visible via MEL & REMIT declarations.
Other_0000000000000009790_001 Dismissed 2025-01-07T19:29:36+00:00 2025-01-09T00:00:00+00:00 2025-01-09T23:59:59+00:00
For commissioning and gas turbine tuning purposes Keadby 2 will be operating at reduced loads for periods of time. These periods will be visible via MEL & REMIT declarations.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009709_002 Inactive 2024-12-13T01:02:32+00:00 2024-12-06T12:55:00+00:00 2024-12-13T00:00:00+00:00
Yellow River Wind Farm is energised and will start generation upto 15MW from December 10th 2024.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009709_001 Dismissed 2024-12-06T12:56:23+00:00 2024-12-06T12:55:00+00:00 2024-12-13T00:00:00+00:00
Yellow River Wind Farm is energised and will start generation upto 15MW from December 10th 2024.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_006 Inactive 2024-12-10T10:02:32+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_005 Dismissed 2024-12-05T18:24:43+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_004 Dismissed 2024-12-05T18:23:19+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
TEST
SSE GENERATION
48X000000000077M
Other_0000000000000009704_003 Dismissed 2024-12-05T18:22:37+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start Q22027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_002 Dismissed 2024-12-05T18:14:15+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_001 Dismissed 2024-12-05T18:12:34+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Other_0000000000000009640_003 Inactive 2024-12-10T01:02:32+00:00 2024-12-09T04:00:00+00:00 2024-12-10T00:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009640_002 Dismissed 2024-12-09T09:43:13+00:00 2024-12-09T04:00:00+00:00 2024-12-10T00:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009640_001 Dismissed 2024-11-21T17:10:54+00:00 2024-12-09T04:00:00+00:00 2024-12-09T23:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009626_002 Inactive 2024-12-03T23:02:32+00:00 2024-12-03T07:00:00+00:00 2024-12-03T22:00:00+00:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 03/12/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000009626_001 Dismissed 2024-11-15T15:58:41+00:00 2024-12-03T07:00:00+00:00 2024-12-03T22:00:00+00:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 03/12/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_003 Inactive 2024-11-28T18:02:32+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_002 Dismissed 2024-11-11T14:48:52+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_001 Dismissed 2024-10-31T09:34:29+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in November 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Other_0000000000000009597_002 Dismissed 2024-11-27T11:23:57+00:00 2024-11-11T08:00:00+00:00 2024-12-06T17:00:00+00:00
Pipeline pigging opperations planned at T_PEHE-1 over period from 11/11/24 to 06/12/24. Anticipated 4 runs at circa 885MW for a duration of 6 hours per run.