Last update at: 2024-05-08T10:30:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | |||||||||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_009 | Dismissed | 2023-05-18T13:59:17+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_008 | Dismissed | 2023-05-16T09:17:28+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_004 | Dismissed | 2022-09-20T12:19:09+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_003 | Dismissed | 2021-11-18T10:21:30+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
Other_0000000000000000038_002 | Dismissed | 2021-11-02T14:08:36+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Dogger Bank A |
Other_0000000000000000038_001 | Dismissed | 2021-11-02T11:32:15+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008120_001 | Active | 2023-05-10T08:47:39+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008119_001 | Active | 2023-05-10T08:46:36+01:00 | 2023-05-10T08:43:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_011 | Dismissed | 2022-11-22T12:07:38+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-14T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_010 | Dismissed | 2022-09-21T16:51:34+01:00 | 2022-01-12T00:00:00+00:00 | 2023-01-10T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_009 | Dismissed | 2022-09-20T11:17:25+01:00 | 2022-01-12T00:00:00+00:00 | 2022-12-19T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_008 | Dismissed | 2022-09-15T16:20:45+01:00 | 2022-01-12T00:00:00+00:00 | 2022-11-14T23:59:00+00:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_007 | Dismissed | 2022-05-16T15:35:06+01:00 | 2022-01-12T00:00:00+00:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_006 | Dismissed | 2022-05-16T15:33:37+01:00 | 2022-05-23T00:00:00+01:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_005 | Dismissed | 2021-11-29T13:21:53+00:00 | 2022-05-23T00:00:00+01:00 | 2022-09-03T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_005 | Inactive | 2023-03-15T10:02:32+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-15T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_004 | Dismissed | 2021-09-07T16:27:51+01:00 | 2022-04-19T00:00:00+01:00 | 2022-07-31T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_004 | Dismissed | 2023-03-10T15:59:26+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-15T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_003 | Dismissed | 2021-08-05T16:06:16+01:00 | 2022-02-28T00:00:00+00:00 | 2022-07-21T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_003 | Dismissed | 2023-03-10T15:58:32+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-10T09:00:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_002 | Dismissed | 2021-06-10T12:30:47+01:00 | 2022-02-09T00:00:00+00:00 | 2022-07-02T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_002 | Dismissed | 2023-02-06T08:49:47+00:00 | 2022-01-12T00:00:00+00:00 | 2023-03-12T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Dismissed | 2022-12-19T16:02:46+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-11T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Dismissed | 2021-04-13T14:42:27+01:00 | 2022-01-06T00:00:00+00:00 | 2022-05-30T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-21T11:51:24+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-19T14:04:00+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:29:36+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:01+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:35:29+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:36:09+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:36:52+00:00 | 2026-12-02T14:22:00+00:00 | 2026-12-02T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:56:55+00:00 | 2026-12-02T14:22:00+00:00 | 2026-12-02T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T11:46:45+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T12:12:07+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:33:28+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:36:04+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_003 | Inactive | 2022-10-17T16:02:33+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_002 | Dismissed | 2022-10-17T14:46:02+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_001 | Dismissed | 2022-10-14T15:47:02+01:00 | 2022-10-14T15:35:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000040_002 | Inactive | 2022-08-26T09:01:54+01:00 | 2022-08-26T00:00:00+01:00 | 2022-08-26T08:00:00+01:00 | Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000000040_001 | Dismissed | 2022-08-17T16:13:32+01:00 | 2022-08-26T00:00:00+01:00 | 2022-08-26T08:00:00+01:00 | Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_003 | Dismissed | 2021-06-10T12:31:45+01:00 | 2021-12-20T00:00:00+00:00 | 2022-05-13T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_002 | Dismissed | 2021-03-01T15:11:31+00:00 | 2021-12-20T00:00:00+00:00 | 2022-05-13T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_001 | Dismissed | 2020-11-24T11:35:27+00:00 | 2021-12-09T23:59:00+00:00 | 2022-05-02T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000000031_006 | Dismissed | 2021-05-31T17:01:14+01:00 | 2021-05-12T17:00:00+01:00 | 2021-08-20T23:00:00+01:00 | Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000000031_005 | Dismissed | 2021-05-10T13:01:06+01:00 | 2021-05-12T17:00:00+01:00 | 2021-08-20T23:00:00+01:00 | Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000000031_004 | Dismissed | 2021-05-05T20:53:41+01:00 | 2021-05-12T00:01:00+01:00 | 2021-08-20T23:59:00+01:00 | Update: Start date of non-firm TEC period changed to 12 May 2021. End date of 20 August 2021 remains unchanged. Original: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC |
||
SSE GENERATION |
48X000000000077M | Other_0000000000000000031_003 | Dismissed | 2021-05-04T10:57:17+01:00 | 2021-05-11T00:01:00+01:00 | 2021-08-20T23:59:00+01:00 | Update: Start date of non-firm TEC period changed to 11 May 2021. End date of 20 August 2021 remains unchanged. Original Remarks: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC |