This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-05-08T10:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:45:43+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:48:41+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:05+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:14+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_014 Dismissed 2023-09-05T17:41:03+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_013 Dismissed 2023-08-30T16:05:41+01:00 2023-07-18T13:30:00+01:00 2023-09-06T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_012 Dismissed 2023-08-25T21:32:06+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_011 Dismissed 2023-08-25T10:13:08+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_010 Dismissed 2023-08-22T11:18:09+01:00 2023-07-18T13:30:00+01:00 2023-08-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_009 Dismissed 2023-08-18T09:18:00+01:00 2023-07-18T13:30:00+01:00 2023-08-23T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_008 Dismissed 2023-08-14T14:39:29+01:00 2023-07-18T13:30:00+01:00 2023-08-20T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_007 Dismissed 2023-08-09T17:31:28+01:00 2023-07-18T13:30:00+01:00 2023-08-15T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_006 Dismissed 2023-08-04T15:49:36+01:00 2023-07-18T13:30:00+01:00 2023-08-11T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_005 Dismissed 2023-08-01T14:41:23+01:00 2023-07-18T13:30:00+01:00 2023-08-07T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_004 Dismissed 2023-07-28T16:16:25+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_003 Dismissed 2023-07-28T16:14:41+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_002 Dismissed 2023-07-24T13:53:38+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_001 Dismissed 2023-07-18T13:28:20+01:00 2023-07-18T13:30:00+01:00 2023-07-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_002 Dismissed 2023-09-07T17:00:31+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_001 Dismissed 2023-09-06T16:25:23+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_004 Dismissed 2023-08-09T14:21:16+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_003 Dismissed 2023-08-09T14:15:15+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_002 Dismissed 2023-08-09T14:14:24+01:00 2023-08-09T14:09:00+01:00 2023-08-10T14:14:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_001 Dismissed 2023-08-09T14:11:02+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_003 Active 2023-08-04T18:05:35+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_002 Dismissed 2023-08-04T17:37:40+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_001 Dismissed 2023-05-10T08:49:10+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_002 Active 2023-08-04T17:30:10+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_001 Dismissed 2023-05-10T08:50:25+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated
Dogger Bank A
48X0000000003113
Other_0000000000000008140_002 Dismissed 2023-07-19T13:26:01+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
Dogger Bank A
48X0000000003113
Other_0000000000000008140_001 Dismissed 2023-05-18T14:01:15+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_018 Dismissed 2023-07-19T13:23:52+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_017 Dismissed 2022-11-04T12:50:38+00:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_016 Dismissed 2022-09-20T14:16:02+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_015 Dismissed 2022-09-20T12:16:29+01:00 2021-03-09T13:33:00+00:00
Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_014 Dismissed 2022-08-05T16:52:37+01:00 2021-03-09T13:33:00+00:00
Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_013 Dismissed 2022-07-21T17:11:40+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_012 Dismissed 2022-06-17T11:53:11+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_011 Dismissed 2022-04-27T13:19:42+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_010 Dismissed 2022-03-29T16:49:45+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_009 Dismissed 2022-03-07T10:12:53+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_008 Dismissed 2022-02-07T16:15:11+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_007 Dismissed 2022-02-07T11:55:37+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_006 Dismissed 2022-01-13T17:07:41+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_005 Dismissed 2021-12-07T13:46:29+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_004 Dismissed 2021-11-30T10:14:00+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_003 Dismissed 2021-08-16T12:27:40+01:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023