SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2026-01-12T15:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 3 4 5 6 7 >
Other_0000000000000010152_001 Dismissed 2025-05-15T15:58:37+00:00 2025-05-20T10:00:25+00:00 2025-05-22T23:00:37+00:00
Medway will be carrying out a full speed no load run on 20/05/2025. On completion NDZ value will increase to 720minutes until the start of our planned outage, 23:00 22/05/2025
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Other_0000000000000009955_002 Inactive 2025-04-02T20:02:32+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000009955_001 Dismissed 2025-03-06T17:04:05+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000010556_003 Inactive 2025-10-10T17:32:32+00:00 2025-10-08T08:30:00+00:00 2025-10-10T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 8th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000010556_002 Dismissed 2025-10-06T08:48:13+00:00 2025-10-08T08:30:00+00:00 2025-10-10T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 8th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000010556_001 Dismissed 2025-09-30T14:56:12+00:00 2025-10-06T08:30:00+00:00 2025-10-08T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 6th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000010561_003 Inactive 2025-10-02T22:02:32+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. It may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000010561_002 Dismissed 2025-10-01T11:00:01+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. It may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000010561_001 Dismissed 2025-10-01T10:59:39+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. A may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+00:00 2024-04-26T00:00:00+00:00 2024-06-06T00:00:00+00:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_008 Dismissed 2024-05-16T17:24:21+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_007 Dismissed 2024-04-14T22:58:55+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW late May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_010 Inactive 2024-07-01T13:02:32+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_009 Dismissed 2024-05-21T12:12:29+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_005 Dismissed 2024-03-07T14:58:39+00:00 2022-07-14T17:23:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation until late April 24 with an increase towards 300MW in early May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_006 Dismissed 2024-04-03T10:47:47+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from late April 24 with an increase towards 300MW in May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_001 Dismissed 2024-10-31T09:34:29+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in November 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_003 Inactive 2024-11-28T18:02:32+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_002 Dismissed 2024-11-11T14:48:52+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_003 Dismissed 2024-12-05T18:22:37+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start Q22027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_001 Dismissed 2024-12-05T18:12:34+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
SSE GENERATION
48X000000000077M
Other_0000000000000009704_002 Dismissed 2024-12-05T18:14:15+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_006 Inactive 2024-12-10T10:02:32+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_005 Dismissed 2024-12-05T18:24:43+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_001 Active 2025-08-21T10:21:58+00:00 2025-08-21T10:30:00+00:00 2025-12-19T10:00:00+00:00
It is expected that Ferrybridge BESS commissioning will start in August 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 150MW being available during Q4 2025. As relevant details of the commissioning plans become firmer REMIT will be updated
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000010696_001 Active 2025-11-22T11:27:06+00:00 2025-11-22T11:25:00+00:00 2027-02-28T11:25:00+00:00
It is expected that Drumnahough commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 58MW being available during Q4 2027. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000010455_002 Active 2025-12-11T08:53:56+00:00 2025-08-29T13:35:00+00:00 2026-12-31T16:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2026. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available for generation during H1 2027. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000010455_001 Dismissed 2025-08-29T13:38:33+00:00 2025-08-29T13:35:00+00:00 2026-03-31T16:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2026. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H2 2026. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_002 Dismissed 2024-03-22T16:27:38+00:00 2023-11-10T12:44:00+00:00 2025-01-30T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available, As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_007 Dismissed 2024-09-27T09:23:17+00:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_006 Dismissed 2024-09-27T09:04:57+00:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_005 Dismissed 2024-09-27T09:04:33+00:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_004 Dismissed 2024-09-27T08:55:31+00:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000009473_002 Inactive 2025-07-31T11:02:32+00:00 2024-09-27T09:18:00+00:00 2025-07-31T10:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000009473_001 Dismissed 2024-09-27T09:23:00+00:00 2024-09-27T09:18:00+00:00 2025-07-31T10:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_001 Dismissed 2023-11-10T15:42:44+00:00 2023-11-10T12:44:00+00:00 2024-12-31T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_003 Dismissed 2024-06-21T14:22:29+00:00 2023-11-10T12:44:00+00:00 2025-03-31T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_003 Dismissed 2023-02-10T11:57:40+00:00 2022-07-14T17:23:00+00:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking
48X000000000314Y
Other_0000000000000000039_002 Dismissed 2022-09-20T12:28:17+00:00 2022-07-14T17:23:00+00:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+00:00 2022-07-14T17:23:00+00:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_004 Dismissed 2024-02-13T16:06:55+00:00 2022-07-14T17:23:00+00:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. From April 2024 Viking will generate at the required MW levels to commission the windfarm to provide the power required to support commissioning of the SSEN HVDC link to the mainland. The commissioning profile of Viking will be subject to a number of factors, including the progress on the HVDC link as well as any associated works.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_009 Dismissed 2022-03-07T10:12:53+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_008 Dismissed 2022-02-07T16:15:11+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_007 Dismissed 2022-02-07T11:55:37+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.