SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2025-11-24T15:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 3 4 5 6 7 >
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_002 Dismissed 2024-03-22T16:27:38+00:00 2023-11-10T12:44:00+00:00 2025-01-30T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available, As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000010455_001 Active 2025-08-29T13:38:33+00:00 2025-08-29T13:35:00+00:00 2026-03-31T16:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2026. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H2 2026. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000010696_001 Active 2025-11-22T11:27:06+00:00 2025-11-22T11:25:00+00:00 2027-02-28T11:25:00+00:00
It is expected that Drumnahough commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 58MW being available during Q4 2027. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000010438_001 Active 2025-08-21T10:21:58+00:00 2025-08-21T10:30:00+00:00 2025-12-19T10:00:00+00:00
It is expected that Ferrybridge BESS commissioning will start in August 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 150MW being available during Q4 2025. As relevant details of the commissioning plans become firmer REMIT will be updated
SSE GENERATION
48X000000000077M
Other_0000000000000009704_006 Inactive 2024-12-10T10:02:32+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_005 Dismissed 2024-12-05T18:24:43+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_002 Dismissed 2024-12-05T18:14:15+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_001 Dismissed 2024-12-05T18:12:34+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
SSE GENERATION
48X000000000077M
Other_0000000000000009704_003 Dismissed 2024-12-05T18:22:37+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start Q22027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_003 Inactive 2024-11-28T18:02:32+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_002 Dismissed 2024-11-11T14:48:52+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_001 Dismissed 2024-10-31T09:34:29+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in November 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_006 Dismissed 2024-04-03T10:47:47+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from late April 24 with an increase towards 300MW in May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_005 Dismissed 2024-03-07T14:58:39+00:00 2022-07-14T17:23:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation until late April 24 with an increase towards 300MW in early May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_010 Inactive 2024-07-01T13:02:32+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_009 Dismissed 2024-05-21T12:12:29+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_007 Dismissed 2024-04-14T22:58:55+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW late May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_008 Dismissed 2024-05-16T17:24:21+00:00 2022-07-14T17:23:00+00:00 2024-07-01T12:00:00+00:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+00:00 2024-04-26T00:00:00+00:00 2024-06-06T00:00:00+00:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Other_0000000000000010561_001 Dismissed 2025-10-01T10:59:39+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. A may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000010561_003 Inactive 2025-10-02T22:02:32+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. It may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000010561_002 Dismissed 2025-10-01T11:00:01+00:00 2025-10-01T10:56:33+00:00 2025-10-02T21:00:44+00:00
Keadby 1 enters a period a hot commissioning following a planned outage. It may run outwith market conditions for periods to facilitate the completion of this task.
Other_0000000000000010556_001 Dismissed 2025-09-30T14:56:12+00:00 2025-10-06T08:30:00+00:00 2025-10-08T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 6th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000010556_003 Inactive 2025-10-10T17:32:32+00:00 2025-10-08T08:30:00+00:00 2025-10-10T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 8th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000010556_002 Dismissed 2025-10-06T08:48:13+00:00 2025-10-08T08:30:00+00:00 2025-10-10T16:30:00+00:00
Keadby 2 will be completing statutory pressure parts onload testing over 3 days starting 8th Oct. They'll be periods of inflexibility and slightly reduced load.
Other_0000000000000009955_002 Inactive 2025-04-02T20:02:32+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000009955_001 Dismissed 2025-03-06T17:04:05+00:00 2025-03-06T17:02:01+00:00 2025-04-02T19:00:00+00:00
Keadby 2 will be operating with an hour’s restriction of circa 40% load factor, up to next planned outage 2nd April 2025.
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Other_0000000000000010152_002 Inactive 2025-05-23T00:02:32+00:00 2025-05-20T10:00:25+00:00 2025-05-22T23:00:37+00:00
Medway will be carrying out a full speed no load run on 20/05/2025. On completion NDZ value will increase to 720minutes until the start of our planned outage, 23:00 22/05/2025
Other_0000000000000010152_001 Dismissed 2025-05-15T15:58:37+00:00 2025-05-20T10:00:25+00:00 2025-05-22T23:00:37+00:00
Medway will be carrying out a full speed no load run on 20/05/2025. On completion NDZ value will increase to 720minutes until the start of our planned outage, 23:00 22/05/2025
Other_0000000000000010625_002 Dismissed 2025-10-20T08:54:50+00:00 2025-10-20T00:00:00+00:00 2025-10-20T23:59:59+00:00
On 20th Oct Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010625_001 Dismissed 2025-10-19T09:37:54+00:00 2025-10-20T00:00:00+00:00 2025-10-20T23:59:59+00:00
On 20th Oct Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_005 Inactive 2025-10-29T01:02:32+00:00 2025-10-27T23:00:00+00:00 2025-10-28T23:59:00+00:00
On 27th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_004 Dismissed 2025-10-27T14:44:07+00:00 2025-10-27T23:00:00+00:00 2025-10-28T23:59:00+00:00
On 27th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_001 Dismissed 2025-10-22T11:59:24+00:00 2025-10-27T23:00:19+00:00 2025-10-28T23:59:48+00:00
On 27th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_003 Dismissed 2025-10-27T14:40:46+00:00 2025-10-27T23:00:00+00:00 2025-10-28T23:59:00+00:00
On 28th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_003 Inactive 2025-10-30T01:02:32+00:00 2025-10-28T23:00:19+00:00 2025-10-29T23:59:48+00:00
On 28th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_002 Dismissed 2025-10-27T09:08:52+00:00 2025-10-28T23:00:19+00:00 2025-10-29T23:59:48+00:00
On 28th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010636_002 Dismissed 2025-10-27T09:08:58+00:00 2025-10-28T23:00:19+00:00 2025-10-29T23:59:48+00:00
On 28th October Keadby 1 Power Station will run a reduced MZT and increased SEL to facilitate post outage recommissioning testing.
Other_0000000000000010648_002 Inactive 2025-10-30T19:02:32+00:00 2025-10-30T08:00:00+00:00 2025-10-30T18:00:00+00:00
On Thursday 30th October from 08:00 to 18:00, Keadby 1 is planning to trevi test safety valves on Boiler 1. This will require Keadby 1 to be running somewhere near MEL during this time.
Other_0000000000000010648_001 Dismissed 2025-10-28T13:37:15+00:00 2025-10-30T08:00:00+00:00 2025-10-30T18:00:00+00:00
On Thursday 30th October from 08:00 to 18:00, Keadby 1 is planning to trevi test safety valves on Boiler 1. This will require Keadby 1 to be running somewhere near MEL during this time.
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+00:00 2023-09-19T10:00:00+00:00 2023-09-19T19:00:00+00:00
Operating at circa 300MW for statutory testing.
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+00:00 2023-09-19T10:00:00+00:00 2023-09-19T19:00:00+00:00
Operating at circa 300MW for statutory testing.
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+00:00 2023-09-20T08:00:00+00:00 2023-09-20T19:00:00+00:00
Operating at circa 550MW for statutory testing.
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+00:00 2023-09-20T08:00:00+00:00 2023-09-20T19:00:00+00:00
Operating at circa 550MW for statutory testing.
Other_0000000000000010169_003 Inactive 2025-05-28T18:02:32+00:00 2025-05-28T13:15:00+00:00 2025-05-28T17:00:00+00:00
Other Market Information message withdrawn – site commissioning complete.
Yellow River
Yellow River
Other_0000000000000010169_002 Dismissed 2025-05-28T13:10:30+00:00 2025-05-28T13:15:00+00:00 2025-05-28T17:00:00+00:00
Other Market Information message withdrawn – site commissioning complete.