Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 2 3 4 5 6 >
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_008 Dismissed 2022-09-15T16:20:45+01:00 2022-01-12T00:00:00+00:00 2022-11-14T23:59:00+00:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_007 Dismissed 2022-05-16T15:35:06+01:00 2022-01-12T00:00:00+00:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2021-09-07T16:27:51+01:00 2022-04-19T00:00:00+01:00 2022-07-31T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000027_003 Dismissed 2021-06-10T12:31:45+01:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000027_002 Dismissed 2021-03-01T15:11:31+00:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Dismissed 2021-11-29T13:21:53+00:00 2022-05-23T00:00:00+01:00 2022-09-03T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_006 Dismissed 2022-05-16T15:33:37+01:00 2022-05-23T00:00:00+01:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2021-08-05T16:06:16+01:00 2022-02-28T00:00:00+00:00 2022-07-21T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_010 Dismissed 2022-09-21T16:51:34+01:00 2022-01-12T00:00:00+00:00 2023-01-10T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_009 Dismissed 2022-09-20T11:17:25+01:00 2022-01-12T00:00:00+00:00 2022-12-19T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_001 Dismissed 2022-12-19T16:02:46+00:00 2022-01-12T00:00:00+00:00 2023-02-11T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2023-02-06T08:49:47+00:00 2022-01-12T00:00:00+00:00 2023-03-12T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_011 Dismissed 2022-11-22T12:07:38+00:00 2022-01-12T00:00:00+00:00 2023-02-14T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2023-03-10T15:59:26+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2023-03-10T15:58:32+00:00 2022-01-12T00:00:00+00:00 2023-03-10T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_003 Dismissed 2024-06-21T14:22:29+01:00 2023-11-10T12:44:00+00:00 2025-03-31T00:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_001 Dismissed 2023-11-10T15:42:44+00:00 2023-11-10T12:44:00+00:00 2024-12-31T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000009473_001 Active 2024-09-27T09:23:00+01:00 2024-09-27T09:18:00+01:00 2025-07-31T10:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_007 Dismissed 2024-09-27T09:23:17+01:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_006 Dismissed 2024-09-27T09:04:57+01:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_005 Dismissed 2024-09-27T09:04:33+01:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_004 Dismissed 2024-09-27T08:55:31+01:00 2023-11-10T12:44:00+00:00 2025-06-30T11:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_002 Dismissed 2024-03-22T16:27:38+00:00 2023-11-10T12:44:00+00:00 2025-01-30T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available, As relevant details of the commissioning plans become firmer REMIT will be updated.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_006 Dismissed 2024-04-03T10:47:47+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from late April 24 with an increase towards 300MW in May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_005 Dismissed 2024-03-07T14:58:39+00:00 2022-07-14T17:23:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation until late April 24 with an increase towards 300MW in early May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_010 Inactive 2024-07-01T13:02:32+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_009 Dismissed 2024-05-21T12:12:29+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From June 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from June 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_007 Dismissed 2024-04-14T22:58:55+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW late May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_008 Dismissed 2024-05-16T17:24:21+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From May 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from May 24 with an increase towards 300MW mid June 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_003 Dismissed 2024-01-25T10:06:41+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_002 Dismissed 2024-01-23T14:55:33+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_001 Dismissed 2024-01-23T08:48:33+00:00 2024-01-22T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_002 Inactive 2023-11-22T01:02:36+00:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_001 Dismissed 2023-06-07T16:31:26+01:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
MEDWAY POWER LTD
48X000000000076O
Other_0000000000000009354_001 Dismissed 2024-08-23T14:04:31+01:00 2024-09-10T00:01:00+01:00 2024-09-12T23:59:00+01:00
Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 10th,11th and 12th of September 2024.
MEDWAY POWER LTD
48X000000000076O
Other_0000000000000009354_003 Inactive 2024-09-13T01:02:32+01:00 2024-09-10T00:01:00+01:00 2024-09-12T23:59:00+01:00
Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 11th and 12th of September 2024.
MEDWAY POWER LTD
48X000000000076O
Other_0000000000000009354_002 Dismissed 2024-09-09T09:01:48+01:00 2024-09-10T00:01:00+01:00 2024-09-12T23:59:00+01:00
Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 11th and 12th of September 2024.
Peterhead
T_PEHE-1
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_039 Dismissed 2023-10-07T21:51:29+01:00 2023-07-18T13:30:00+01:00 2023-10-08T19:00:00+01:00
Other market information message withdrawn with first generation achieved 07/10/23 All REMIT submitted by BMU on SSE Remit portal.