This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-10-03T15:00:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_031 Dismissed 2023-10-02T08:51:38+01:00 2023-07-18T13:30:00+01:00 2023-10-03T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_035 Dismissed 2023-10-05T16:49:11+01:00 2023-07-18T13:30:00+01:00 2023-10-06T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_034 Dismissed 2023-10-03T16:16:32+01:00 2023-07-18T13:30:00+01:00 2023-10-06T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_036 Dismissed 2023-10-06T15:08:54+01:00 2023-07-18T13:30:00+01:00 2023-10-06T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_038 Dismissed 2023-10-06T16:23:25+01:00 2023-07-18T13:30:00+01:00 2023-10-08T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_037 Dismissed 2023-10-06T15:46:32+01:00 2023-07-18T13:30:00+01:00 2023-10-08T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_014 Dismissed 2023-09-05T17:41:03+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:48:41+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:05+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:14+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_017 Dismissed 2023-09-12T08:50:34+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:45:43+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_018 Dismissed 2023-09-14T21:28:32+01:00 2023-07-18T13:30:00+01:00 2023-09-18T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_019 Dismissed 2023-09-17T18:18:20+01:00 2023-07-18T13:30:00+01:00 2023-09-19T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_020 Dismissed 2023-09-18T17:45:34+01:00 2023-07-18T13:30:00+01:00 2023-09-20T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_022 Dismissed 2023-09-22T17:41:06+01:00 2023-07-18T13:30:00+01:00 2023-09-23T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_021 Dismissed 2023-09-19T18:32:22+01:00 2023-07-18T13:30:00+01:00 2023-09-23T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_023 Dismissed 2023-09-23T12:53:08+01:00 2023-07-18T13:30:00+01:00 2023-09-26T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_025 Dismissed 2023-09-26T15:41:57+01:00 2023-07-18T13:30:00+01:00 2023-09-27T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_024 Dismissed 2023-09-25T17:45:52+01:00 2023-07-18T13:30:00+01:00 2023-09-27T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_026 Dismissed 2023-09-27T15:26:24+01:00 2023-07-18T13:30:00+01:00 2023-09-28T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 28th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_027 Dismissed 2023-09-28T14:32:16+01:00 2023-07-18T13:30:00+01:00 2023-09-29T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 29th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_028 Dismissed 2023-09-29T16:49:18+01:00 2023-07-18T13:30:00+01:00 2023-09-30T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 30th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_006 Dismissed 2023-08-04T15:49:36+01:00 2023-07-18T13:30:00+01:00 2023-08-11T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_007 Dismissed 2023-08-09T17:31:28+01:00 2023-07-18T13:30:00+01:00 2023-08-15T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_008 Dismissed 2023-08-14T14:39:29+01:00 2023-07-18T13:30:00+01:00 2023-08-20T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_009 Dismissed 2023-08-18T09:18:00+01:00 2023-07-18T13:30:00+01:00 2023-08-23T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_010 Dismissed 2023-08-22T11:18:09+01:00 2023-07-18T13:30:00+01:00 2023-08-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_001 Dismissed 2023-07-18T13:28:20+01:00 2023-07-18T13:30:00+01:00 2023-07-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_002 Dismissed 2023-07-24T13:53:38+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_012 Dismissed 2023-08-25T21:32:06+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_011 Dismissed 2023-08-25T10:13:08+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_013 Dismissed 2023-08-30T16:05:41+01:00 2023-07-18T13:30:00+01:00 2023-09-06T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_005 Dismissed 2023-08-01T14:41:23+01:00 2023-07-18T13:30:00+01:00 2023-08-07T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_004 Dismissed 2023-07-28T16:16:25+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_003 Dismissed 2023-07-28T16:14:41+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_004 Dismissed 2021-11-30T10:14:00+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_003 Dismissed 2021-08-16T12:27:40+01:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_006 Dismissed 2022-01-13T17:07:41+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_005 Dismissed 2021-12-07T13:46:29+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_007 Dismissed 2022-02-07T11:55:37+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_008 Dismissed 2022-02-07T16:15:11+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_009 Dismissed 2022-03-07T10:12:53+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_004 Dismissed 2024-02-13T16:06:55+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. From April 2024 Viking will generate at the required MW levels to commission the windfarm to provide the power required to support commissioning of the SSEN HVDC link to the mainland. The commissioning profile of Viking will be subject to a number of factors, including the progress on the HVDC link as well as any associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_003 Dismissed 2023-02-10T11:57:40+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking
48X000000000314Y
Other_0000000000000000039_002 Dismissed 2022-09-20T12:28:17+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_001 Dismissed 2021-04-13T14:42:27+01:00 2022-01-06T00:00:00+00:00 2022-05-30T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2021-06-10T12:30:47+01:00 2022-02-09T00:00:00+00:00 2022-07-02T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000027_001 Dismissed 2020-11-24T11:35:27+00:00 2021-12-09T23:59:00+00:00 2022-05-02T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.