Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_004 Dismissed 2024-02-13T16:06:55+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. From April 2024 Viking will generate at the required MW levels to commission the windfarm to provide the power required to support commissioning of the SSEN HVDC link to the mainland. The commissioning profile of Viking will be subject to a number of factors, including the progress on the HVDC link as well as any associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_003 Dismissed 2023-02-10T11:57:40+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking
48X000000000314Y
Other_0000000000000000039_002 Dismissed 2022-09-20T12:28:17+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_009 Dismissed 2023-05-18T13:59:17+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_008 Dismissed 2023-05-16T09:17:28+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_007 Dismissed 2023-05-16T09:02:22+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_006 Dismissed 2023-05-12T16:59:23+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_005 Dismissed 2023-02-10T11:54:13+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Dogger Bank A
48X0000000003113
Other_0000000000000000038_004 Dismissed 2022-09-20T12:19:09+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Dogger Bank A
48X0000000003113
Other_0000000000000000038_003 Dismissed 2021-11-18T10:21:30+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Dogger Bank A
Other_0000000000000000038_002 Dismissed 2021-11-02T14:08:36+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Dogger Bank A
Other_0000000000000000038_001 Dismissed 2021-11-02T11:32:15+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000000037_002 Inactive 2021-05-22T00:01:53+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000037_001 Dismissed 2021-05-13T13:23:19+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000036_002 Inactive 2021-05-19T09:01:54+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000036_001 Dismissed 2021-05-13T13:22:03+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000035_002 Inactive 2021-05-17T09:01:53+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000035_001 Dismissed 2021-05-13T13:20:34+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000034_002 Inactive 2021-05-15T00:01:53+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000034_001 Dismissed 2021-05-12T13:04:36+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000033_002 Inactive 2021-05-14T00:01:52+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000033_001 Dismissed 2021-05-11T11:39:02+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000032_002 Inactive 2021-05-13T00:01:51+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M
Other_0000000000000000032_001 Dismissed 2021-05-10T12:49:52+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M
Other_0000000000000000031_006 Dismissed 2021-05-31T17:01:14+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_005 Dismissed 2021-05-10T13:01:06+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_004 Dismissed 2021-05-05T20:53:41+01:00 2021-05-12T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 12 May 2021. End date of 20 August 2021 remains unchanged. Original: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_003 Dismissed 2021-05-04T10:57:17+01:00 2021-05-11T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 11 May 2021. End date of 20 August 2021 remains unchanged. Original Remarks: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_002 Dismissed 2021-04-20T11:44:37+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
SSE GENERATION
48X000000000077M
Other_0000000000000000031_001 Dismissed 2021-04-20T11:32:25+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_011 Dismissed 2022-11-22T12:07:38+00:00 2022-01-12T00:00:00+00:00 2023-02-14T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_010 Dismissed 2022-09-21T16:51:34+01:00 2022-01-12T00:00:00+00:00 2023-01-10T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_009 Dismissed 2022-09-20T11:17:25+01:00 2022-01-12T00:00:00+00:00 2022-12-19T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_008 Dismissed 2022-09-15T16:20:45+01:00 2022-01-12T00:00:00+00:00 2022-11-14T23:59:00+00:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_007 Dismissed 2022-05-16T15:35:06+01:00 2022-01-12T00:00:00+00:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_006 Dismissed 2022-05-16T15:33:37+01:00 2022-05-23T00:00:00+01:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Dismissed 2021-11-29T13:21:53+00:00 2022-05-23T00:00:00+01:00 2022-09-03T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2021-09-07T16:27:51+01:00 2022-04-19T00:00:00+01:00 2022-07-31T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2023-03-10T15:59:26+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2021-08-05T16:06:16+01:00 2022-02-28T00:00:00+00:00 2022-07-21T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2023-03-10T15:58:32+00:00 2022-01-12T00:00:00+00:00 2023-03-10T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2021-06-10T12:30:47+01:00 2022-02-09T00:00:00+00:00 2022-07-02T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2023-02-06T08:49:47+00:00 2022-01-12T00:00:00+00:00 2023-03-12T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_001 Dismissed 2022-12-19T16:02:46+00:00 2022-01-12T00:00:00+00:00 2023-02-11T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_001 Dismissed 2021-04-13T14:42:27+01:00 2022-01-06T00:00:00+00:00 2022-05-30T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_018 Dismissed 2023-07-19T13:23:52+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_017 Dismissed 2022-11-04T12:50:38+00:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_016 Dismissed 2022-09-20T14:16:02+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal.