Last update at: 2023-09-26T16:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
1 2 3 4 > | |||||||
Other_0000000000000008437_006 | Dismissed | 2023-09-22T15:13:14+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Other_0000000000000008437_005 | Dismissed | 2023-09-21T17:33:37+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Other_0000000000000008437_004 | Dismissed | 2023-09-21T17:03:58+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon |
||
Other_0000000000000008437_003 | Dismissed | 2023-09-21T16:48:56+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing |
||
Other_0000000000000008437_002 | Dismissed | 2023-09-21T14:26:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 550MW for statutory testing |
||
Other_0000000000000008437_001 | Dismissed | 2023-09-20T08:32:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | Running at Circa 550MW for statutory testing |
||
Other_0000000000000008436_003 | Dismissed | 2023-09-21T14:38:30+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Other_0000000000000008436_002 | Dismissed | 2023-09-21T14:27:09+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Other_0000000000000008436_001 | Dismissed | 2023-09-20T08:29:55+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | Running at Circa 300MW for statutory testing |
||
Other_0000000000000008421_002 | Dismissed | 2023-09-18T12:19:17+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |
||
Other_0000000000000008421_001 | Dismissed | 2023-09-15T15:02:40+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |
||
Other_0000000000000008420_002 | Dismissed | 2023-09-18T12:19:36+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Other_0000000000000008420_001 | Dismissed | 2023-09-15T15:01:11+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_002 | Dismissed | 2023-09-07T17:00:31+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_001 | Dismissed | 2023-09-06T16:25:23+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_004 | Dismissed | 2023-08-09T14:21:16+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_003 | Dismissed | 2023-08-09T14:15:15+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_002 | Dismissed | 2023-08-09T14:14:24+01:00 | 2023-08-09T14:09:00+01:00 | 2023-08-10T14:14:00+01:00 | This is a test message |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_001 | Dismissed | 2023-08-09T14:11:02+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_025 | Active | 2023-09-26T15:41:57+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_024 | Dismissed | 2023-09-25T17:45:52+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_023 | Dismissed | 2023-09-23T12:53:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-26T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_022 | Dismissed | 2023-09-22T17:41:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_021 | Dismissed | 2023-09-19T18:32:22+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_020 | Dismissed | 2023-09-18T17:45:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-20T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_019 | Dismissed | 2023-09-17T18:18:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-19T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_018 | Dismissed | 2023-09-14T21:28:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-18T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_017 | Dismissed | 2023-09-12T08:50:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:45:43+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:48:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:14+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_014 | Dismissed | 2023-09-05T17:41:03+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_013 | Dismissed | 2023-08-30T16:05:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-06T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_012 | Dismissed | 2023-08-25T21:32:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_011 | Dismissed | 2023-08-25T10:13:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_010 | Dismissed | 2023-08-22T11:18:09+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_009 | Dismissed | 2023-08-18T09:18:00+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-23T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_008 | Dismissed | 2023-08-14T14:39:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-20T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_007 | Dismissed | 2023-08-09T17:31:28+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-15T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_006 | Dismissed | 2023-08-04T15:49:36+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-11T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_005 | Dismissed | 2023-08-01T14:41:23+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-07T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_004 | Dismissed | 2023-07-28T16:16:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_003 | Dismissed | 2023-07-28T16:14:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_002 | Dismissed | 2023-07-24T13:53:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_001 | Dismissed | 2023-07-18T13:28:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-07-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Other_0000000000000008203_003 | Active | 2023-07-27T12:34:51+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Other_0000000000000008203_002 | Dismissed | 2023-06-19T10:34:59+01:00 | 2023-06-19T10:07:00+01:00 | 2023-07-28T10:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Other_0000000000000008203_001 | Dismissed | 2023-06-19T10:13:07+01:00 | 2023-06-19T10:07:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
|||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000008178_001 | Active | 2023-06-07T16:31:26+01:00 | 2023-11-14T00:00:00+00:00 | 2023-11-21T23:59:00+00:00 | Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed. |