Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007759_001 Dismissed 2022-12-05T14:29:36+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:01+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007759_001 Dismissed 2022-12-05T14:35:29+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007759_001 Dismissed 2022-12-05T14:36:09+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007759_001 Dismissed 2022-12-05T14:36:52+00:00 2026-12-02T14:22:00+00:00 2026-12-02T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007759_001 Dismissed 2022-12-05T14:56:55+00:00 2026-12-02T14:22:00+00:00 2026-12-02T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007760_001 Dismissed 2022-12-05T14:58:16+00:00 2026-12-06T00:00:00+00:00 2026-12-06T00:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007760_001 Dismissed 2022-12-05T14:44:18+00:00 2026-12-05T00:00:00+00:00 2026-12-05T00:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007760_001 Dismissed 2022-12-05T14:51:07+00:00 2026-12-06T00:00:00+00:00 2026-12-06T00:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007785_001 Dismissed 2022-12-19T13:59:31+00:00 2025-03-01T13:53:00+00:00 2025-03-01T13:55:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Keadby
T_KEAD-1
Other_0000000000000007785_001 Dismissed 2022-12-21T11:51:47+00:00 2025-03-01T13:53:00+00:00 2025-03-01T13:55:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007786_001 Dismissed 2022-12-21T11:51:24+00:00 2024-03-01T14:02:00+00:00 2024-03-01T14:03:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000007786_001 Dismissed 2022-12-19T14:04:00+00:00 2024-03-01T14:02:00+00:00 2024-03-01T14:03:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
Medway
T_MEDP-1
Other_0000000000000007814_001 Dismissed 2022-12-22T17:45:01+00:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Great Island
Great Island
Other_0000000000000008020_001 Dismissed 2023-03-15T11:40:21+00:00 2027-03-15T11:45:00+00:00 2027-03-15T11:46:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008020_002 Inactive 2023-03-15T12:11:38+00:00 2027-03-15T11:45:00+00:00 2027-03-15T11:46:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_001 Dismissed 2023-03-15T13:49:55+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_002 Inactive 2023-03-15T13:51:41+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_001 Dismissed 2023-03-16T09:34:37+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_002 Inactive 2023-03-16T09:36:20+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_001 Dismissed 2023-03-16T09:38:18+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_002 Inactive 2023-03-16T09:39:01+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tawnaghmore
TAWN1
Other_0000000000000008024_001 Dismissed 2023-03-16T09:40:16+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tawnaghmore
TAWN1
Other_0000000000000008024_002 Inactive 2023-03-16T09:40:56+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008119_001 Active 2023-05-10T08:46:36+01:00 2023-05-10T08:43:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008120_001 Active 2023-05-10T08:47:39+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_001 Dismissed 2023-05-10T08:49:10+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_002 Dismissed 2023-08-04T17:37:40+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_003 Active 2023-08-04T18:05:35+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_001 Dismissed 2023-05-10T08:50:25+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_002 Active 2023-08-04T17:30:10+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
Dogger Bank A
48X0000000003113
Other_0000000000000008140_001 Dismissed 2023-05-18T14:01:15+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
Dogger Bank A
48X0000000003113
Other_0000000000000008140_002 Dismissed 2023-07-19T13:26:01+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_001 Dismissed 2023-06-07T16:31:26+01:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_002 Inactive 2023-11-22T01:02:36+00:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
Great Island
Great Island
Other_0000000000000008203_001 Dismissed 2023-06-19T10:13:07+01:00 2023-06-19T10:07:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_002 Dismissed 2023-06-19T10:34:59+01:00 2023-06-19T10:07:00+01:00 2023-07-28T10:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_003 Dismissed 2023-07-27T12:34:51+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_004 Dismissed 2023-10-02T17:07:15+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_001 Dismissed 2023-07-18T13:28:20+01:00 2023-07-18T13:30:00+01:00 2023-07-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_002 Dismissed 2023-07-24T13:53:38+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_003 Dismissed 2023-07-28T16:14:41+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_004 Dismissed 2023-07-28T16:16:25+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_005 Dismissed 2023-08-01T14:41:23+01:00 2023-07-18T13:30:00+01:00 2023-08-07T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_006 Dismissed 2023-08-04T15:49:36+01:00 2023-07-18T13:30:00+01:00 2023-08-11T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_007 Dismissed 2023-08-09T17:31:28+01:00 2023-07-18T13:30:00+01:00 2023-08-15T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_008 Dismissed 2023-08-14T14:39:29+01:00 2023-07-18T13:30:00+01:00 2023-08-20T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_009 Dismissed 2023-08-18T09:18:00+01:00 2023-07-18T13:30:00+01:00 2023-08-23T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_010 Dismissed 2023-08-22T11:18:09+01:00 2023-07-18T13:30:00+01:00 2023-08-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_011 Dismissed 2023-08-25T10:13:08+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.