Last update at: 2024-04-27T01:30:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | |||||||||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_002 | Dismissed | 2023-08-09T14:14:24+01:00 | 2023-08-09T14:09:00+01:00 | 2023-08-10T14:14:00+01:00 | This is a test message |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_001 | Dismissed | 2023-08-09T14:11:02+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_003 | Active | 2023-08-04T18:05:35+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_002 | Dismissed | 2023-08-04T17:37:40+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_001 | Dismissed | 2023-05-10T08:49:10+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_002 | Active | 2023-08-04T17:30:10+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_001 | Dismissed | 2023-05-10T08:50:25+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008120_001 | Active | 2023-05-10T08:47:39+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008119_001 | Active | 2023-05-10T08:46:36+01:00 | 2023-05-10T08:43:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:33:28+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:36:04+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_003 | Inactive | 2022-10-17T16:02:33+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_002 | Dismissed | 2022-10-17T14:46:02+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_001 | Dismissed | 2022-10-14T15:47:02+01:00 | 2022-10-14T15:35:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
|||
Other_0000000000000009044_005 | Inactive | 2024-04-27T01:02:32+01:00 | 2024-04-26T00:00:00+01:00 | 2024-04-26T23:59:59+01:00 | Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented. |
||||
Keadby |
T_KEAD-1 |
Other_0000000000000009044_004 | Dismissed | 2024-04-25T10:49:47+01:00 | 2024-04-26T00:00:00+01:00 | 2024-04-26T23:59:59+01:00 | Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009044_003 | Dismissed | 2024-04-25T10:23:07+01:00 | 2024-04-26T00:00:00+01:00 | 2024-04-26T23:59:59+01:00 | Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009044_002 | Dismissed | 2024-04-25T09:44:41+01:00 | 2024-04-26T00:00:00+01:00 | 2024-06-06T00:00:00+01:00 | KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009044_001 | Dismissed | 2024-04-24T19:54:16+01:00 | 2024-04-25T00:00:00+01:00 | 2024-06-06T00:00:00+01:00 | Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009046_001 | Active | 2024-04-25T12:04:26+01:00 | 2024-04-27T23:00:00+01:00 | 2024-05-21T23:00:00+01:00 | T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam. |
||
Viking Wind Farm |
Other_0000000000000000039_001 | Dismissed | 2022-07-14T17:25:58+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
||||
Other_0000000000000008908_004 | Inactive | 2024-03-18T01:02:32+00:00 | 2024-03-04T00:00:00+00:00 | 2024-03-18T00:00:00+00:00 | SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work). |
||||
Keadby |
T_KEAD-2 |
Other_0000000000000008908_003 | Dismissed | 2024-03-08T11:26:43+00:00 | 2024-03-04T00:00:00+00:00 | 2024-03-18T00:00:00+00:00 | SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work). |
||
Keadby |
T_KEAD-2 |
Other_0000000000000008908_002 | Dismissed | 2024-03-05T14:03:34+00:00 | 2024-03-04T00:00:00+00:00 | 2024-03-18T00:00:00+00:00 | SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work). |
||
Keadby |
T_KEAD-2 |
Other_0000000000000008908_001 | Dismissed | 2024-03-04T13:13:31+00:00 | 2024-03-04T00:00:00+00:00 | 2024-03-18T00:00:00+00:00 | SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified. |
||
Other_0000000000000008899_004 | Inactive | 2024-03-08T01:02:31+00:00 | 2024-03-04T06:00:00+00:00 | 2024-03-07T23:59:00+00:00 | Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads. |
||||
Medway |
T_MEDP-1 |
Other_0000000000000008899_003 | Dismissed | 2024-03-05T14:59:17+00:00 | 2024-03-04T06:00:00+00:00 | 2024-03-07T23:59:00+00:00 | Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads. |
||
Medway |
T_MEDP-1 |
Other_0000000000000008899_002 | Dismissed | 2024-02-29T14:00:58+00:00 | 2024-03-04T06:00:00+00:00 | 2024-03-07T23:59:00+00:00 | Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads. |
||
Medway |
T_MEDP-1 |
Other_0000000000000008899_001 | Dismissed | 2024-02-29T13:41:02+00:00 | 2024-03-04T06:00:00+00:00 | 2024-04-04T23:59:00+01:00 | Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads. |
||
Great Island |
Great Island |
Other_0000000000000008845_002 | Inactive | 2024-02-13T14:47:42+00:00 | 2030-02-13T14:40:00+00:00 | 2030-02-13T14:41:00+00:00 | This is a test of SSE REMIT application functionality only. No action should be taken. |
||
Great Island |
Great Island |
Other_0000000000000008845_001 | Dismissed | 2024-02-13T14:42:10+00:00 | 2030-02-13T14:40:00+00:00 | 2030-02-13T14:41:00+00:00 | This is a test of SSE REMIT application functionality only. No action should be taken. |
||
Great Island |
Great Island |
Other_0000000000000008475_002 | Active | 2023-10-02T17:20:09+01:00 | 2023-10-02T17:05:00+01:00 | 2024-05-17T22:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
Great Island |
Great Island |
Other_0000000000000008475_001 | Dismissed | 2023-10-02T17:06:20+01:00 | 2023-10-02T17:05:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
|||
Great Island |
Great Island |
Other_0000000000000008203_004 | Dismissed | 2023-10-02T17:07:15+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Great Island |
Great Island |
Other_0000000000000008203_003 | Dismissed | 2023-07-27T12:34:51+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Great Island |
Great Island |
Other_0000000000000008203_002 | Dismissed | 2023-06-19T10:34:59+01:00 | 2023-06-19T10:07:00+01:00 | 2023-07-28T10:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Great Island |
Great Island |
Other_0000000000000008203_001 | Dismissed | 2023-06-19T10:13:07+01:00 | 2023-06-19T10:07:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
|||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_006 | Dismissed | 2023-09-22T15:13:14+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_005 | Dismissed | 2023-09-21T17:33:37+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_004 | Dismissed | 2023-09-21T17:03:58+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_003 | Dismissed | 2023-09-21T16:48:56+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:01:00+01:00 | T_PEHE-1 Running at Circa 780MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_002 | Dismissed | 2023-09-21T14:26:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | T_PEHE-1 Running at Circa 550MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008437_001 | Dismissed | 2023-09-20T08:32:32+01:00 | 2023-09-22T08:00:00+01:00 | 2023-09-22T19:00:00+01:00 | Running at Circa 550MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_003 | Dismissed | 2023-09-21T14:38:30+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_002 | Dismissed | 2023-09-21T14:27:09+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | T_PEHE-1 Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008436_001 | Dismissed | 2023-09-20T08:29:55+01:00 | 2023-09-21T12:00:00+01:00 | 2023-09-21T19:00:00+01:00 | Running at Circa 300MW for statutory testing |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008420_002 | Dismissed | 2023-09-18T12:19:36+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008420_001 | Dismissed | 2023-09-15T15:01:11+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008421_002 | Dismissed | 2023-09-18T12:19:17+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000008421_001 | Dismissed | 2023-09-15T15:02:40+01:00 | 2023-09-20T08:00:00+01:00 | 2023-09-20T19:00:00+01:00 | Operating at circa 550MW for statutory testing. |