This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-04-27T01:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_002 Dismissed 2023-08-09T14:14:24+01:00 2023-08-09T14:09:00+01:00 2023-08-10T14:14:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_001 Dismissed 2023-08-09T14:11:02+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_003 Active 2023-08-04T18:05:35+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_002 Dismissed 2023-08-04T17:37:40+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_001 Dismissed 2023-05-10T08:49:10+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_002 Active 2023-08-04T17:30:10+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_001 Dismissed 2023-05-10T08:50:25+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008120_001 Active 2023-05-10T08:47:39+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008119_001 Active 2023-05-10T08:46:36+01:00 2023-05-10T08:43:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000007750_001 Dismissed 2022-12-01T11:33:28+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000007750_001 Dismissed 2022-12-01T11:36:04+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_003 Inactive 2022-10-17T16:02:33+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_002 Dismissed 2022-10-17T14:46:02+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_001 Dismissed 2022-10-14T15:47:02+01:00 2022-10-14T15:35:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
Other_0000000000000009044_005 Inactive 2024-04-27T01:02:32+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_004 Dismissed 2024-04-25T10:49:47+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_003 Dismissed 2024-04-25T10:23:07+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Keadby
T_KEAD-1
Other_0000000000000009044_001 Dismissed 2024-04-24T19:54:16+01:00 2024-04-25T00:00:00+01:00 2024-06-06T00:00:00+01:00
Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Peterhead
T_PEHE-1
Other_0000000000000009046_001 Active 2024-04-25T12:04:26+01:00 2024-04-27T23:00:00+01:00 2024-05-21T23:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Other_0000000000000008908_004 Inactive 2024-03-18T01:02:32+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_003 Dismissed 2024-03-08T11:26:43+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_002 Dismissed 2024-03-05T14:03:34+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_001 Dismissed 2024-03-04T13:13:31+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Great Island
Great Island
Other_0000000000000008845_002 Inactive 2024-02-13T14:47:42+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008845_001 Dismissed 2024-02-13T14:42:10+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008475_002 Active 2023-10-02T17:20:09+01:00 2023-10-02T17:05:00+01:00 2024-05-17T22:00:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008475_001 Dismissed 2023-10-02T17:06:20+01:00 2023-10-02T17:05:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008203_004 Dismissed 2023-10-02T17:07:15+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_003 Dismissed 2023-07-27T12:34:51+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_002 Dismissed 2023-06-19T10:34:59+01:00 2023-06-19T10:07:00+01:00 2023-07-28T10:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_001 Dismissed 2023-06-19T10:13:07+01:00 2023-06-19T10:07:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Peterhead
T_PEHE-1
Other_0000000000000008437_006 Dismissed 2023-09-22T15:13:14+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_005 Dismissed 2023-09-21T17:33:37+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_004 Dismissed 2023-09-21T17:03:58+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon
Peterhead
T_PEHE-1
Other_0000000000000008437_003 Dismissed 2023-09-21T16:48:56+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_002 Dismissed 2023-09-21T14:26:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_001 Dismissed 2023-09-20T08:32:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_003 Dismissed 2023-09-21T14:38:30+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_002 Dismissed 2023-09-21T14:27:09+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_001 Dismissed 2023-09-20T08:29:55+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.