Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
1 2 3 4 > | |||||||
Viking Energy Wind Farm LLP |
48X000000000314Y | Other_0000000000000000039_003 | Active | 2023-02-10T11:57:40+00:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|
Viking |
48X000000000314Y | Other_0000000000000000039_002 | Dismissed | 2022-09-20T12:28:17+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_025 | Active | 2023-09-26T15:41:57+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_024 | Dismissed | 2023-09-25T17:45:52+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_023 | Dismissed | 2023-09-23T12:53:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-26T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_022 | Dismissed | 2023-09-22T17:41:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_021 | Dismissed | 2023-09-19T18:32:22+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_020 | Dismissed | 2023-09-18T17:45:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-20T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_019 | Dismissed | 2023-09-17T18:18:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-19T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_018 | Dismissed | 2023-09-14T21:28:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-18T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_017 | Dismissed | 2023-09-12T08:50:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:45:43+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:48:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:14+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_014 | Dismissed | 2023-09-05T17:41:03+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_013 | Dismissed | 2023-08-30T16:05:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-06T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_012 | Dismissed | 2023-08-25T21:32:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_011 | Dismissed | 2023-08-25T10:13:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_010 | Dismissed | 2023-08-22T11:18:09+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_009 | Dismissed | 2023-08-18T09:18:00+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-23T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_008 | Dismissed | 2023-08-14T14:39:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-20T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_007 | Dismissed | 2023-08-09T17:31:28+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-15T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_006 | Dismissed | 2023-08-04T15:49:36+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-11T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_005 | Dismissed | 2023-08-01T14:41:23+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-07T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_004 | Dismissed | 2023-07-28T16:16:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_003 | Dismissed | 2023-07-28T16:14:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_002 | Dismissed | 2023-07-24T13:53:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_001 | Dismissed | 2023-07-18T13:28:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-07-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_002 | Dismissed | 2023-07-19T13:26:01+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_001 | Dismissed | 2023-05-18T14:01:15+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_009 | Dismissed | 2023-05-18T13:59:17+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_008 | Dismissed | 2023-05-16T09:17:28+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_004 | Dismissed | 2022-09-20T12:19:09+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_003 | Dismissed | 2021-11-18T10:21:30+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_002 | Dismissed | 2023-09-07T17:00:31+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_001 | Dismissed | 2023-09-06T16:25:23+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_018 | Dismissed | 2023-07-19T13:23:52+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_017 | Dismissed | 2022-11-04T12:50:38+00:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_016 | Dismissed | 2022-09-20T14:16:02+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_015 | Dismissed | 2022-09-20T12:16:29+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_014 | Dismissed | 2022-08-05T16:52:37+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_013 | Dismissed | 2022-07-21T17:11:40+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_012 | Dismissed | 2022-06-17T11:53:11+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_011 | Dismissed | 2022-04-27T13:19:42+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_010 | Dismissed | 2022-03-29T16:49:45+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_009 | Dismissed | 2022-03-07T10:12:53+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023. |