Last update at: 2024-10-31T10:00:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 2 3 4 5 6 > | |||||||||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_010 | Dismissed | 2022-03-29T16:49:45+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_009 | Dismissed | 2022-03-07T10:12:53+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_008 | Dismissed | 2022-02-07T16:15:11+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_007 | Dismissed | 2022-02-07T11:55:37+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_006 | Dismissed | 2022-01-13T17:07:41+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_005 | Dismissed | 2021-12-07T13:46:29+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_004 | Dismissed | 2021-11-30T10:14:00+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
|||
SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | Other_0000000000000009038_002 | Inactive | 2024-04-23T01:02:47+01:00 | 2024-04-22T00:01:00+01:00 | 2024-04-22T23:59:00+01:00 | Peterhead 12 hour on load run requested of GT 11 and 12 for preservation of plant during Monday 22nd of April 2024. |
||
SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | Other_0000000000000009038_001 | Dismissed | 2024-04-19T14:29:07+01:00 | 2024-04-22T00:01:00+01:00 | 2024-04-22T23:59:00+01:00 | Peterhead 12 hour on load run requested of GT 11 and 12 for preservation of plant during Monday 22nd of April 2024. |
||
SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | Other_0000000000000008909_002 | Dismissed | 2024-03-05T15:33:12+00:00 | 2024-03-04T16:37:00+00:00 | Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead |
|||
SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | Other_0000000000000008909_001 | Dismissed | 2024-03-04T16:40:26+00:00 | 2024-03-04T16:37:00+00:00 | Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000009175_003 | Active | 2024-09-27T08:57:17+01:00 | 2024-06-21T14:00:00+01:00 | 2025-06-30T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.300MW of installed capacity as at 26 September 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
48X0000000003113 | Other_0000000000000009175_002 | Dismissed | 2024-06-21T14:23:06+01:00 | 2024-06-21T14:00:00+01:00 | 2025-03-31T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.200MW of installed capacity as at 1 June 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
48X0000000003113 | Other_0000000000000009175_001 | Dismissed | 2024-06-21T14:21:28+01:00 | 2024-06-21T14:00:00+01:00 | 2025-03-31T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.200MW of installed capacity as at 1 June 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_039 | Dismissed | 2023-10-07T21:51:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | Other market information message withdrawn with first generation achieved 07/10/23 All REMIT submitted by BMU on SSE Remit portal. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_038 | Dismissed | 2023-10-06T16:23:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_037 | Dismissed | 2023-10-06T15:46:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-08T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 08th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_036 | Dismissed | 2023-10-06T15:08:54+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_035 | Dismissed | 2023-10-05T16:49:11+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_034 | Dismissed | 2023-10-03T16:16:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-06T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_033 | Dismissed | 2023-10-03T11:39:12+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T20:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_032 | Dismissed | 2023-10-03T07:08:50+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T12:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_031 | Dismissed | 2023-10-02T08:51:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_030 | Dismissed | 2023-10-01T17:10:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-03T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_029 | Dismissed | 2023-09-30T16:22:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-10-02T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 02nd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_028 | Dismissed | 2023-09-29T16:49:18+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-30T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 30th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_027 | Dismissed | 2023-09-28T14:32:16+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-29T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 29th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_026 | Dismissed | 2023-09-27T15:26:24+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-28T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 28th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_025 | Dismissed | 2023-09-26T15:41:57+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_024 | Dismissed | 2023-09-25T17:45:52+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_023 | Dismissed | 2023-09-23T12:53:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-26T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_022 | Dismissed | 2023-09-22T17:41:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_021 | Dismissed | 2023-09-19T18:32:22+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_020 | Dismissed | 2023-09-18T17:45:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-20T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_019 | Dismissed | 2023-09-17T18:18:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-19T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_018 | Dismissed | 2023-09-14T21:28:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-18T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_017 | Dismissed | 2023-09-12T08:50:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:45:43+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:48:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:14+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_014 | Dismissed | 2023-09-05T17:41:03+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_013 | Dismissed | 2023-08-30T16:05:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-06T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_012 | Dismissed | 2023-08-25T21:32:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_011 | Dismissed | 2023-08-25T10:13:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_010 | Dismissed | 2023-08-22T11:18:09+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_009 | Dismissed | 2023-08-18T09:18:00+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-23T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_008 | Dismissed | 2023-08-14T14:39:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-20T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_007 | Dismissed | 2023-08-09T17:31:28+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-15T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_006 | Dismissed | 2023-08-04T15:49:36+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-11T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |