This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2023-09-26T16:00:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 >
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008121_002 Dismissed 2023-08-04T17:37:40+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008121_001 Dismissed 2023-05-10T08:49:10+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008122_002 Active 2023-08-04T17:30:10+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008122_001 Dismissed 2023-05-10T08:50:25+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008120_001 Active 2023-05-10T08:47:39+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000008119_001 Active 2023-05-10T08:46:36+01:00 2023-05-10T08:43:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000041_003 Active 2023-02-28T10:01:18+00:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000041_002 Dismissed 2022-09-02T09:34:18+01:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000041_001 Dismissed 2022-09-01T16:31:20+01:00 2024-01-01T00:00:00+00:00 2030-01-01T00:00:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000007750_001 Dismissed 2022-12-01T11:33:28+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000007750_001 Dismissed 2022-12-01T11:36:04+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_003 Inactive 2022-10-17T16:02:33+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_002 Dismissed 2022-10-17T14:46:02+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000042_001 Dismissed 2022-10-14T15:47:02+01:00 2022-10-14T15:35:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_003 Inactive 2020-10-28T01:01:54+00:00 2020-10-26T07:45:00+00:00 2020-10-27T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_002 Dismissed 2020-10-26T09:06:10+00:00 2020-10-26T07:45:00+00:00 2020-10-27T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
SSE Generation Ireland Ltd
47X0000000000592 Other_0000000000000000026_001 Dismissed 2020-10-23T08:25:15+01:00 2020-10-25T07:45:00+00:00 2020-10-26T23:59:00+00:00
Great Island CCGT Unit on post outage testing.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000008178_001 Active 2023-06-07T16:31:26+01:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_011 Dismissed 2022-11-22T12:07:38+00:00 2022-01-12T00:00:00+00:00 2023-02-14T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_010 Dismissed 2022-09-21T16:51:34+01:00 2022-01-12T00:00:00+00:00 2023-01-10T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_009 Dismissed 2022-09-20T11:17:25+01:00 2022-01-12T00:00:00+00:00 2022-12-19T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_008 Dismissed 2022-09-15T16:20:45+01:00 2022-01-12T00:00:00+00:00 2022-11-14T23:59:00+00:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_007 Dismissed 2022-05-16T15:35:06+01:00 2022-01-12T00:00:00+00:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_006 Dismissed 2022-05-16T15:33:37+01:00 2022-05-23T00:00:00+01:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_005 Dismissed 2021-11-29T13:21:53+00:00 2022-05-23T00:00:00+01:00 2022-09-03T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_004 Dismissed 2021-09-07T16:27:51+01:00 2022-04-19T00:00:00+01:00 2022-07-31T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_004 Dismissed 2023-03-10T15:59:26+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_003 Dismissed 2023-03-10T15:58:32+00:00 2022-01-12T00:00:00+00:00 2023-03-10T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_003 Dismissed 2021-08-05T16:06:16+01:00 2022-02-28T00:00:00+00:00 2022-07-21T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_002 Dismissed 2021-06-10T12:30:47+01:00 2022-02-09T00:00:00+00:00 2022-07-02T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_002 Dismissed 2023-02-06T08:49:47+00:00 2022-01-12T00:00:00+00:00 2023-03-12T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_001 Dismissed 2022-12-19T16:02:46+00:00 2022-01-12T00:00:00+00:00 2023-02-11T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000030_001 Dismissed 2021-04-13T14:42:27+01:00 2022-01-06T00:00:00+00:00 2022-05-30T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007786_001 Dismissed 2022-12-21T11:51:24+00:00 2024-03-01T14:02:00+00:00 2024-03-01T14:03:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007786_001 Dismissed 2022-12-19T14:04:00+00:00 2024-03-01T14:02:00+00:00 2024-03-01T14:03:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007759_001 Dismissed 2022-12-05T14:29:36+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:01+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007759_001 Dismissed 2022-12-05T14:35:29+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007759_001 Dismissed 2022-12-05T14:36:09+00:00 2026-12-01T14:22:00+00:00 2026-12-01T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007759_001 Dismissed 2022-12-05T14:36:52+00:00 2026-12-02T14:22:00+00:00 2026-12-02T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007759_001 Dismissed 2022-12-05T14:56:55+00:00 2026-12-02T14:22:00+00:00 2026-12-02T14:22:02+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007752_001 Dismissed 2022-12-01T11:46:45+00:00 2022-12-01T12:15:00+00:00 2022-12-01T12:16:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000007752_001 Dismissed 2022-12-01T12:12:07+00:00 2022-12-01T12:15:00+00:00 2022-12-01T12:16:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_003 Dismissed 2021-06-10T12:31:45+01:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_002 Dismissed 2021-03-01T15:11:31+00:00 2021-12-20T00:00:00+00:00 2022-05-13T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000027_001 Dismissed 2020-11-24T11:35:27+00:00 2021-12-09T23:59:00+00:00 2022-05-02T00:01:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_003 Inactive 2021-01-11T01:02:32+00:00 2020-09-02T00:01:00+01:00 2021-01-10T23:59:00+00:00
Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_002 Dismissed 2020-09-01T13:43:16+01:00 2020-09-02T00:01:00+01:00 2021-01-10T23:59:00+00:00
Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000025_001 Dismissed 2020-08-20T08:26:48+01:00 2020-10-09T23:59:00+01:00 2021-03-08T14:00:00+00:00
A phased array test on Keadby GT1 R1 compressor blade root has identified a subsurface anomaly which needs to be monitored with further phase array tests in August and September. We will begin preparations for rectification of this issue from October 2020 onwards inline with the published outage program. Should the ongoing tests provide further information then we will adjust the outage program accordingly.
KEADBY GEN. LTD
48X000000000073U Other_0000000000000000024_001 Active 2019-06-13T12:30:13+01:00 2019-06-13T12:30:00+01:00
Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020.