Last update at: 2024-10-31T10:00:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
1 2 3 4 5 > | |||||||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009457_004 | Dismissed | 2024-10-01T16:28:19+01:00 | 2024-10-07T09:00:00+01:00 | 2024-10-13T18:00:00+01:00 | T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 1 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009457_003 | Dismissed | 2024-09-25T09:07:21+01:00 | 2024-10-07T09:00:00+01:00 | 2024-10-13T18:00:00+01:00 | T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 1 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009457_002 | Dismissed | 2024-09-23T16:12:25+01:00 | 2024-09-30T09:00:00+01:00 | 2024-10-13T18:00:00+01:00 | T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 2 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009457_001 | Dismissed | 2024-09-23T15:52:48+01:00 | 2024-09-30T09:00:00+01:00 | 2024-10-06T18:00:00+01:00 | T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 2 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009350_002 | Dismissed | 2024-08-22T14:45:18+01:00 | 2024-09-22T00:00:00+01:00 | 2024-09-22T00:00:01+01:00 | This is a test publication following the automation of SSE REMIT admin app. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009350_001 | Dismissed | 2024-08-22T14:41:23+01:00 | 2024-09-22T00:00:00+01:00 | 2024-09-22T00:00:01+01:00 | This is a test publication following the automation of SSE REMIT admin app. |
||
Other_0000000000000009256_008 | Inactive | 2024-08-01T04:02:32+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T03:00:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||||
Great Island |
Great Island |
Other_0000000000000009256_007 | Dismissed | 2024-07-31T21:10:48+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T03:00:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_006 | Dismissed | 2024-07-31T21:07:31+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T00:03:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_005 | Dismissed | 2024-07-30T15:59:06+01:00 | 2024-07-31T00:00:00+01:00 | 2024-07-31T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_004 | Dismissed | 2024-07-29T14:03:08+01:00 | 2024-08-01T00:00:00+01:00 | 2024-08-01T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_003 | Dismissed | 2024-07-28T16:25:13+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_002 | Dismissed | 2024-07-27T20:37:44+01:00 | 2024-07-29T00:00:00+01:00 | 2024-07-30T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_001 | Dismissed | 2024-07-18T16:02:07+01:00 | 2024-07-28T00:00:00+01:00 | 2024-07-29T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009284_001 | Active | 2024-07-29T14:17:35+01:00 | 2024-08-02T00:00:00+01:00 | 2025-04-30T00:00:00+01:00 | Great Island is unavailable to run on oil due to plant fault. |
||
Other_0000000000000009232_003 | Inactive | 2024-07-08T22:02:32+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-08T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009232_002 | Dismissed | 2024-07-05T16:16:03+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-08T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009232_001 | Dismissed | 2024-07-05T14:44:07+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_003 | Dismissed | 2024-07-08T21:43:03+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 370MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_002 | Dismissed | 2024-07-08T09:37:04+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 370MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_001 | Dismissed | 2024-07-05T16:18:45+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
Other_0000000000000009202_002 | Inactive | 2024-07-03T19:02:32+01:00 | 2024-07-03T13:00:00+01:00 | 2024-07-03T18:00:00+01:00 | T_PEHE-1 running for post outage commissioning at circa 600MW. |
||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009202_001 | Dismissed | 2024-07-02T09:06:48+01:00 | 2024-07-03T13:00:00+01:00 | 2024-07-03T18:00:00+01:00 | T_PEHE-1 running for post outage commissioning at circa 600MW. |
||
Viking Wind Farm |
Other_0000000000000000039_001 | Dismissed | 2022-07-14T17:25:58+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009046_003 | Dismissed | 2024-06-25T15:31:25+01:00 | 2024-04-27T23:00:00+01:00 | 2024-06-28T00:00:00+01:00 | T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009046_002 | Dismissed | 2024-05-17T08:50:18+01:00 | 2024-04-27T23:00:00+01:00 | 2024-06-28T00:00:00+01:00 | T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009046_001 | Dismissed | 2024-04-25T12:04:26+01:00 | 2024-04-27T23:00:00+01:00 | 2024-05-21T23:00:00+01:00 | T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam. |
||
Other_0000000000000009139_003 | Inactive | 2024-06-07T13:02:32+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-07T12:00:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||||
Keadby |
T_KEAD-1 |
Other_0000000000000009139_002 | Dismissed | 2024-06-06T17:30:33+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-07T12:00:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009139_001 | Dismissed | 2024-06-04T15:45:42+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-06T23:59:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||
Other_0000000000000009127_004 | Inactive | 2024-06-04T01:02:31+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins. |
||||
Medway |
T_MEDP-1 |
Other_0000000000000009127_003 | Dismissed | 2024-06-03T16:49:21+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins. |
||
Other_0000000000000009127_003 | Inactive | 2024-06-04T01:02:31+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||||
Medway |
T_MEDP-1 |
Other_0000000000000009127_002 | Dismissed | 2024-06-03T08:32:07+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||
Medway |
T_MEDP-1 |
Other_0000000000000009127_002 | Dismissed | 2024-06-03T08:32:16+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||
Medway |
T_MEDP-1 |
Other_0000000000000009127_001 | Dismissed | 2024-05-31T09:03:01+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity station on load run. Once out of merit run is complete our dynamic data NDZ value will become 360 mins. |
||
Great Island |
Great Island |
Other_0000000000000009107_002 | Inactive | 2024-05-24T16:22:43+01:00 | 2029-12-24T16:19:00+00:00 | **** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Unit Level. |
|||
Great Island |
Great Island |
Other_0000000000000009107_001 | Dismissed | 2024-05-24T16:18:52+01:00 | 2029-12-24T16:19:00+00:00 | **** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Unit Level. |
|||
Other_0000000000000009072_002 | Inactive | 2024-05-17T23:02:32+01:00 | 2024-05-17T07:00:00+01:00 | 2024-05-17T22:00:00+01:00 | For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours. |
||||
Great Island |
Great Island |
Other_0000000000000009072_001 | Dismissed | 2024-05-08T10:08:54+01:00 | 2024-05-17T07:00:00+01:00 | 2024-05-17T22:00:00+01:00 | For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours. |
||
Other_0000000000000008475_003 | Inactive | 2024-05-17T23:02:32+01:00 | 2023-10-02T17:05:00+01:00 | 2024-05-17T22:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||||
Great Island |
Great Island |
Other_0000000000000008475_002 | Dismissed | 2023-10-02T17:20:09+01:00 | 2023-10-02T17:05:00+01:00 | 2024-05-17T22:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
Great Island |
Great Island |
Other_0000000000000008475_001 | Dismissed | 2023-10-02T17:06:20+01:00 | 2023-10-02T17:05:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
|||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_005 | Dismissed | 2024-05-16T18:41:49+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_005 | Dismissed | 2024-05-16T18:41:53+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_004 | Dismissed | 2024-05-16T18:36:19+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_003 | Dismissed | 2024-05-14T08:51:35+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_002 | Dismissed | 2024-05-13T17:15:57+01:00 | 2024-05-15T08:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_001 | Dismissed | 2024-05-13T11:11:57+01:00 | 2024-05-15T08:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running at circa 600MW for post outage commissioning works. |
||
Other_0000000000000009044_005 | Inactive | 2024-04-27T01:02:32+01:00 | 2024-04-26T00:00:00+01:00 | 2024-04-26T23:59:59+01:00 | Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented. |