This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-04-27T01:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
Other_0000000000000009044_005 Inactive 2024-04-27T01:02:32+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_004 Dismissed 2024-04-25T10:49:47+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_003 Dismissed 2024-04-25T10:23:07+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Keadby
T_KEAD-1
Other_0000000000000009044_001 Dismissed 2024-04-24T19:54:16+01:00 2024-04-25T00:00:00+01:00 2024-06-06T00:00:00+01:00
Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Peterhead
T_PEHE-1
Other_0000000000000009046_001 Active 2024-04-25T12:04:26+01:00 2024-04-27T23:00:00+01:00 2024-05-21T23:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Other_0000000000000008908_004 Inactive 2024-03-18T01:02:32+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_003 Dismissed 2024-03-08T11:26:43+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_002 Dismissed 2024-03-05T14:03:34+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_001 Dismissed 2024-03-04T13:13:31+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Great Island
Great Island
Other_0000000000000008845_002 Inactive 2024-02-13T14:47:42+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008845_001 Dismissed 2024-02-13T14:42:10+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008475_002 Active 2023-10-02T17:20:09+01:00 2023-10-02T17:05:00+01:00 2024-05-17T22:00:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008475_001 Dismissed 2023-10-02T17:06:20+01:00 2023-10-02T17:05:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008203_004 Dismissed 2023-10-02T17:07:15+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_003 Dismissed 2023-07-27T12:34:51+01:00 2023-06-19T10:07:00+01:00 2024-05-17T22:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_002 Dismissed 2023-06-19T10:34:59+01:00 2023-06-19T10:07:00+01:00 2023-07-28T10:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Great Island
Great Island
Other_0000000000000008203_001 Dismissed 2023-06-19T10:13:07+01:00 2023-06-19T10:07:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Peterhead
T_PEHE-1
Other_0000000000000008437_006 Dismissed 2023-09-22T15:13:14+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_005 Dismissed 2023-09-21T17:33:37+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_004 Dismissed 2023-09-21T17:03:58+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon
Peterhead
T_PEHE-1
Other_0000000000000008437_003 Dismissed 2023-09-21T16:48:56+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_002 Dismissed 2023-09-21T14:26:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_001 Dismissed 2023-09-20T08:32:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_003 Dismissed 2023-09-21T14:38:30+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_002 Dismissed 2023-09-21T14:27:09+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_001 Dismissed 2023-09-20T08:29:55+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Seagreen Wind Energy Ltd
Other_0000000000000000029_003 Dismissed 2021-08-16T12:27:40+01:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Medway
T_MEDP-1
Other_0000000000000007814_001 Dismissed 2022-12-22T17:45:01+00:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Dogger Bank A
Other_0000000000000000038_002 Dismissed 2021-11-02T14:08:36+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Dogger Bank A
Other_0000000000000000038_001 Dismissed 2021-11-02T11:32:15+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Tawnaghmore
TAWN1
Other_0000000000000008024_002 Inactive 2023-03-16T09:40:56+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tawnaghmore
TAWN1
Other_0000000000000008024_001 Dismissed 2023-03-16T09:40:16+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_002 Inactive 2023-03-16T09:39:01+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_001 Dismissed 2023-03-16T09:38:18+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_002 Inactive 2023-03-16T09:36:20+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_001 Dismissed 2023-03-16T09:34:37+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_002 Inactive 2023-03-15T13:51:41+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level