Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
1 2 > | |||||||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_003 | Dismissed | 2021-08-16T12:27:40+01:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_002 | Dismissed | 2021-03-09T13:55:35+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Seagreen wind energy Ltd |
Other_0000000000000000029_001 | Dismissed | 2021-03-09T13:41:20+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Viking Wind Farm |
Other_0000000000000000039_001 | Dismissed | 2022-07-14T17:25:58+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
||
Dogger Bank A |
Other_0000000000000000038_002 | Dismissed | 2021-11-02T14:08:36+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
Other_0000000000000000038_001 | Dismissed | 2021-11-02T11:32:15+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:33:28+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000007750_001 | Dismissed | 2022-12-01T11:36:04+00:00 | 2022-12-01T12:00:00+00:00 | 2022-12-01T12:01:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_003 | Inactive | 2022-10-17T16:02:33+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_002 | Dismissed | 2022-10-17T14:46:02+01:00 | 2022-10-14T15:35:00+01:00 | 2022-10-17T14:48:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_001 | Dismissed | 2022-10-14T15:47:02+01:00 | 2022-10-14T15:35:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000041_002 | Active | 2022-09-02T09:34:18+01:00 | 2022-09-01T00:00:00+01:00 | 2023-12-31T23:59:00+00:00 | Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000041_001 | Dismissed | 2022-09-01T16:31:20+01:00 | 2024-01-01T00:00:00+00:00 | 2030-01-01T00:00:00+00:00 | Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_003 | Inactive | 2020-10-28T01:01:54+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_002 | Dismissed | 2020-10-26T09:06:10+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_001 | Dismissed | 2020-10-23T08:25:15+01:00 | 2020-10-25T07:45:00+00:00 | 2020-10-26T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-21T11:51:24+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007786_001 | Dismissed | 2022-12-19T14:04:00+00:00 | 2024-03-01T14:02:00+00:00 | 2024-03-01T14:03:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_011 | Dismissed | 2022-11-22T12:07:38+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-14T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_010 | Dismissed | 2022-09-21T16:51:34+01:00 | 2022-01-12T00:00:00+00:00 | 2023-01-10T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_009 | Dismissed | 2022-09-20T11:17:25+01:00 | 2022-01-12T00:00:00+00:00 | 2022-12-19T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_008 | Dismissed | 2022-09-15T16:20:45+01:00 | 2022-01-12T00:00:00+00:00 | 2022-11-14T23:59:00+00:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_007 | Dismissed | 2022-05-16T15:35:06+01:00 | 2022-01-12T00:00:00+00:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_006 | Dismissed | 2022-05-16T15:33:37+01:00 | 2022-05-23T00:00:00+01:00 | 2022-09-30T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_005 | Dismissed | 2021-11-29T13:21:53+00:00 | 2022-05-23T00:00:00+01:00 | 2022-09-03T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_004 | Dismissed | 2021-09-07T16:27:51+01:00 | 2022-04-19T00:00:00+01:00 | 2022-07-31T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_003 | Dismissed | 2021-08-05T16:06:16+01:00 | 2022-02-28T00:00:00+00:00 | 2022-07-21T00:00:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_002 | Dismissed | 2021-06-10T12:30:47+01:00 | 2022-02-09T00:00:00+00:00 | 2022-07-02T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Dismissed | 2021-04-13T14:42:27+01:00 | 2022-01-06T00:00:00+00:00 | 2022-05-30T23:59:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 06/01/2022 & finish on 30/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000030_001 | Active | 2022-12-19T16:02:46+00:00 | 2022-01-12T00:00:00+00:00 | 2023-02-11T23:59:00+00:00 | It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:29:36+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:01+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:35:29+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:36:09+00:00 | 2026-12-01T14:22:00+00:00 | 2026-12-01T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:36:52+00:00 | 2026-12-02T14:22:00+00:00 | 2026-12-02T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007759_001 | Dismissed | 2022-12-05T14:56:55+00:00 | 2026-12-02T14:22:00+00:00 | 2026-12-02T14:22:02+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T11:46:45+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T12:12:07+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_003 | Dismissed | 2021-06-10T12:31:45+01:00 | 2021-12-20T00:00:00+00:00 | 2022-05-13T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_002 | Dismissed | 2021-03-01T15:11:31+00:00 | 2021-12-20T00:00:00+00:00 | 2022-05-13T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 20/12/2021 & finish on 13/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in August 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000027_001 | Dismissed | 2020-11-24T11:35:27+00:00 | 2021-12-09T23:59:00+00:00 | 2022-05-02T00:01:00+01:00 | It is currently anticipated Keadby 2 performance validation period will start on 09/12/2021 & finish on 02/05/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in July 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_003 | Inactive | 2021-01-11T01:02:32+00:00 | 2020-09-02T00:01:00+01:00 | 2021-01-10T23:59:00+00:00 | Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_002 | Dismissed | 2020-09-01T13:43:16+01:00 | 2020-09-02T00:01:00+01:00 | 2021-01-10T23:59:00+00:00 | Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_001 | Dismissed | 2020-08-20T08:26:48+01:00 | 2020-10-09T23:59:00+01:00 | 2021-03-08T14:00:00+00:00 | A phased array test on Keadby GT1 R1 compressor blade root has identified a subsurface anomaly which needs to be monitored with further phase array tests in August and September. We will begin preparations for rectification of this issue from October 2020 onwards inline with the published outage program. Should the ongoing tests provide further information then we will adjust the outage program accordingly. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000024_001 | Active | 2019-06-13T12:30:13+01:00 | 2019-06-13T12:30:00+01:00 | Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020. |
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000015_001 | Active | 2019-03-19T14:46:49+00:00 | 2019-03-19T12:55:00+00:00 | T_FIDL-1 - With immediate effect, unit 1 will be withdrawn from service. |
|
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_002 | Inactive | 2020-12-01T20:01:53+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_001 | Dismissed | 2020-12-01T09:29:14+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
SSE GENERATION |
48X000000000077M | Other_0000000000000000040_002 | Inactive | 2022-08-26T09:01:54+01:00 | 2022-08-26T00:00:00+01:00 | 2022-08-26T08:00:00+01:00 | Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage. |
SSE GENERATION |
48X000000000077M | Other_0000000000000000040_001 | Dismissed | 2022-08-17T16:13:32+01:00 | 2022-08-26T00:00:00+01:00 | 2022-08-26T08:00:00+01:00 | Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage. |
SSE GENERATION |
48X000000000077M | Other_0000000000000000031_006 | Dismissed | 2021-05-31T17:01:14+01:00 | 2021-05-12T17:00:00+01:00 | 2021-08-20T23:00:00+01:00 | Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC |