This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-07-26T13:00:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
Great Island
Great Island
Other_0000000000000009256_001 Active 2024-07-18T16:02:07+01:00 2024-07-28T00:00:00+01:00 2024-07-29T23:59:00+01:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009232_003 Inactive 2024-07-08T22:02:32+01:00 2024-07-08T08:00:00+01:00 2024-07-08T21:00:00+01:00
T_PEHE-1 commissioning run at circa 1000MW.
Peterhead
T_PEHE-1
Other_0000000000000009232_002 Dismissed 2024-07-05T16:16:03+01:00 2024-07-08T08:00:00+01:00 2024-07-08T21:00:00+01:00
T_PEHE-1 commissioning run at circa 1000MW.
Peterhead
T_PEHE-1
Other_0000000000000009232_001 Dismissed 2024-07-05T14:44:07+01:00 2024-07-08T08:00:00+01:00 2024-07-09T21:00:00+01:00
T_PEHE-1 commissioning run at circa 1000MW.
Peterhead
T_PEHE-1
Other_0000000000000009233_003 Dismissed 2024-07-08T21:43:03+01:00 2024-07-09T08:00:00+01:00 2024-07-09T21:00:00+01:00
T_PEHE-1 commissioning run at circa 370MW.
Peterhead
T_PEHE-1
Other_0000000000000009233_002 Dismissed 2024-07-08T09:37:04+01:00 2024-07-09T08:00:00+01:00 2024-07-09T21:00:00+01:00
T_PEHE-1 commissioning run at circa 370MW.
Peterhead
T_PEHE-1
Other_0000000000000009233_001 Dismissed 2024-07-05T16:18:45+01:00 2024-07-09T08:00:00+01:00 2024-07-09T21:00:00+01:00
T_PEHE-1 commissioning run at circa 1000MW.
Other_0000000000000009202_002 Inactive 2024-07-03T19:02:32+01:00 2024-07-03T13:00:00+01:00 2024-07-03T18:00:00+01:00
T_PEHE-1 running for post outage commissioning at circa 600MW.
Peterhead
T_PEHE-1
Other_0000000000000009202_001 Dismissed 2024-07-02T09:06:48+01:00 2024-07-03T13:00:00+01:00 2024-07-03T18:00:00+01:00
T_PEHE-1 running for post outage commissioning at circa 600MW.
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Peterhead
T_PEHE-1
Other_0000000000000009046_003 Dismissed 2024-06-25T15:31:25+01:00 2024-04-27T23:00:00+01:00 2024-06-28T00:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Peterhead
T_PEHE-1
Other_0000000000000009046_002 Dismissed 2024-05-17T08:50:18+01:00 2024-04-27T23:00:00+01:00 2024-06-28T00:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Peterhead
T_PEHE-1
Other_0000000000000009046_001 Dismissed 2024-04-25T12:04:26+01:00 2024-04-27T23:00:00+01:00 2024-05-21T23:00:00+01:00
T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam.
Other_0000000000000009139_003 Inactive 2024-06-07T13:02:32+01:00 2024-06-06T00:00:00+01:00 2024-06-07T12:00:00+01:00
T_KEAD-1 2+1 run required for post outage commissioning works.
Keadby
T_KEAD-1
Other_0000000000000009139_002 Dismissed 2024-06-06T17:30:33+01:00 2024-06-06T00:00:00+01:00 2024-06-07T12:00:00+01:00
T_KEAD-1 2+1 run required for post outage commissioning works.
Keadby
T_KEAD-1
Other_0000000000000009139_001 Dismissed 2024-06-04T15:45:42+01:00 2024-06-06T00:00:00+01:00 2024-06-06T23:59:00+01:00
T_KEAD-1 2+1 run required for post outage commissioning works.
Other_0000000000000009127_004 Inactive 2024-06-04T01:02:31+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins.
Medway
T_MEDP-1
Other_0000000000000009127_003 Dismissed 2024-06-03T16:49:21+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins.
Other_0000000000000009127_003 Inactive 2024-06-04T01:02:31+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins.
Medway
T_MEDP-1
Other_0000000000000009127_002 Dismissed 2024-06-03T08:32:07+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins.
Medway
T_MEDP-1
Other_0000000000000009127_002 Dismissed 2024-06-03T08:32:16+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins.
Medway
T_MEDP-1
Other_0000000000000009127_001 Dismissed 2024-05-31T09:03:01+01:00 2024-06-03T00:00:00+01:00 2024-06-03T23:59:00+01:00
Asset integrity station on load run. Once out of merit run is complete our dynamic data NDZ value will become 360 mins.
Great Island
Great Island
Other_0000000000000009107_002 Inactive 2024-05-24T16:22:43+01:00 2029-12-24T16:19:00+00:00
**** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Unit Level.
Great Island
Great Island
Other_0000000000000009107_001 Dismissed 2024-05-24T16:18:52+01:00 2029-12-24T16:19:00+00:00
**** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Unit Level.
Other_0000000000000009072_002 Inactive 2024-05-17T23:02:32+01:00 2024-05-17T07:00:00+01:00 2024-05-17T22:00:00+01:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Great Island
Great Island
Other_0000000000000009072_001 Dismissed 2024-05-08T10:08:54+01:00 2024-05-17T07:00:00+01:00 2024-05-17T22:00:00+01:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000008475_003 Inactive 2024-05-17T23:02:32+01:00 2023-10-02T17:05:00+01:00 2024-05-17T22:00:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008475_002 Dismissed 2023-10-02T17:20:09+01:00 2023-10-02T17:05:00+01:00 2024-05-17T22:00:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Great Island
Great Island
Other_0000000000000008475_001 Dismissed 2023-10-02T17:06:20+01:00 2023-10-02T17:05:00+01:00
Great Island is available for running on secondary fuel in the event of a gas system emergency
Peterhead
T_PEHE-1
Other_0000000000000009081_005 Dismissed 2024-05-16T18:41:49+01:00 2024-05-14T23:00:00+01:00 2024-05-16T18:37:00+01:00
T_PEHE-1 block running for post outage commissioning works.
Peterhead
T_PEHE-1
Other_0000000000000009081_005 Dismissed 2024-05-16T18:41:53+01:00 2024-05-14T23:00:00+01:00 2024-05-16T18:37:00+01:00
T_PEHE-1 block running for post outage commissioning works.
Peterhead
T_PEHE-1
Other_0000000000000009081_004 Dismissed 2024-05-16T18:36:19+01:00 2024-05-14T23:00:00+01:00 2024-05-16T18:37:00+01:00
T_PEHE-1 block running for post outage commissioning works.
Peterhead
T_PEHE-1
Other_0000000000000009081_003 Dismissed 2024-05-14T08:51:35+01:00 2024-05-14T23:00:00+01:00 2024-05-17T21:00:00+01:00
T_PEHE-1 block running for post outage commissioning works.
Peterhead
T_PEHE-1
Other_0000000000000009081_002 Dismissed 2024-05-13T17:15:57+01:00 2024-05-15T08:00:00+01:00 2024-05-17T21:00:00+01:00
T_PEHE-1 block running for post outage commissioning works.
Peterhead
T_PEHE-1
Other_0000000000000009081_001 Dismissed 2024-05-13T11:11:57+01:00 2024-05-15T08:00:00+01:00 2024-05-17T21:00:00+01:00
T_PEHE-1 block running at circa 600MW for post outage commissioning works.
Other_0000000000000009044_005 Inactive 2024-04-27T01:02:32+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_004 Dismissed 2024-04-25T10:49:47+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 26th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_003 Dismissed 2024-04-25T10:23:07+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Keadby
T_KEAD-1
Other_0000000000000009044_001 Dismissed 2024-04-24T19:54:16+01:00 2024-04-25T00:00:00+01:00 2024-06-06T00:00:00+01:00
Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Other_0000000000000008908_004 Inactive 2024-03-18T01:02:32+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_003 Dismissed 2024-03-08T11:26:43+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_002 Dismissed 2024-03-05T14:03:34+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_001 Dismissed 2024-03-04T13:13:31+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified.
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Great Island
Great Island
Other_0000000000000008845_002 Inactive 2024-02-13T14:47:42+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
Great Island
Great Island
Other_0000000000000008845_001 Dismissed 2024-02-13T14:42:10+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.