Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
SSE GENERATION
48X000000000077M
Other_0000000000000000032_001 Dismissed 2021-05-10T12:49:52+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M
Other_0000000000000000018_002 Dismissed 2019-04-19T12:04:54+01:00 2019-04-19T09:08:00+01:00
SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications.
SSE GENERATION
48X000000000077M
Other_0000000000000000018_001 Dismissed 2019-04-19T09:10:02+01:00 2019-04-19T09:08:00+01:00
SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications.
SSE GENERATION
48X000000000077M
Other_0000000000000000019_001 Active 2019-04-19T12:04:36+01:00 2019-04-19T12:03:00+01:00
The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations
SSE GENERATION
48X000000000077M
Other_0000000000000000017_002 Dismissed 2019-04-19T09:08:42+01:00 2019-04-18T19:00:00+01:00
The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations
SSE GENERATION
48X000000000077M
Other_0000000000000000017_001 Dismissed 2019-04-18T19:00:28+01:00 2019-04-18T19:00:00+01:00
The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations
SSE GENERATION
48X000000000077M
Other_0000000000000000006_003 Active 2017-12-19T12:08:01+00:00 2018-04-01T00:00:00+01:00
Peterhead TEC has been increased to 1180MW on an enduring basis from 1st April 2018 and will continue operations at 1180MW going forward.
SSE GENERATION
48X000000000077M
Other_0000000000000000006_002 Dismissed 2017-11-07T13:55:07+00:00 2018-04-01T00:00:00+01:00
Subject to CMP268 not being legally challenged, we intend to increase TEC at Peterhead to 1180MW on an enduring basis commencing 1st April 2018 and continue operations at 1180MW going forward.
SSE GENERATION
48X000000000077M
Other_0000000000000000006_001 Dismissed 2017-03-23T14:04:44+00:00 2018-04-01T00:00:00+01:00
From the 1st April 2018 we will be reducing the TEC at Peterhead to zero. The cancellation of our TEC at this time is a risk mitigation measure to avoid a substantial cancellation charge if we were to cancel later in the year, once we have completed our review of the stations future, which we announced on 6 February 2017. We will reapply for TEC and subject to receiving a satisfactory offer from NGET, reinstate TEC should our review conclude that the station has an enduring future.
SSE Energy Supply Limited
A0001004V.UK
Other_0000000000000008476_002 Inactive 2023-10-24T23:47:32+01:00 2023-10-24T22:36:00+01:00 2023-10-24T22:40:00+01:00
end of outage
SSE Energy Supply Limited
A0001004V.UK
Other_0000000000000008476_001 Dismissed 2023-10-24T22:39:53+01:00 2023-10-24T22:36:00+01:00 2023-10-24T22:40:00+01:00
end of outage
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_002 Dismissed 2023-09-07T17:00:31+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_001 Dismissed 2023-09-06T16:25:23+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_018 Dismissed 2023-07-19T13:23:52+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_017 Dismissed 2022-11-04T12:50:38+00:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_016 Dismissed 2022-09-20T14:16:02+01:00 2021-03-09T13:33:00+00:00
Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_015 Dismissed 2022-09-20T12:16:29+01:00 2021-03-09T13:33:00+00:00
Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_014 Dismissed 2022-08-05T16:52:37+01:00 2021-03-09T13:33:00+00:00
Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_013 Dismissed 2022-07-21T17:11:40+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_012 Dismissed 2022-06-17T11:53:11+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_011 Dismissed 2022-04-27T13:19:42+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_010 Dismissed 2022-03-29T16:49:45+01:00 2021-03-09T13:33:00+00:00
Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_009 Dismissed 2022-03-07T10:12:53+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_008 Dismissed 2022-02-07T16:15:11+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_007 Dismissed 2022-02-07T11:55:37+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_006 Dismissed 2022-01-13T17:07:41+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_005 Dismissed 2021-12-07T13:46:29+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000000029_004 Dismissed 2021-11-30T10:14:00+00:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_003 Dismissed 2021-08-16T12:27:40+01:00 2021-03-09T13:33:00+00:00
It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated
Seagreen Wind Energy Ltd
Other_0000000000000000029_002 Dismissed 2021-03-09T13:55:35+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen wind energy Ltd
Other_0000000000000000029_001 Dismissed 2021-03-09T13:41:20+00:00 2021-03-09T13:33:00+00:00
It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_003 Dismissed 2024-01-25T10:06:41+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_002 Dismissed 2024-01-23T14:55:33+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_001 Dismissed 2024-01-23T08:48:33+00:00 2024-01-22T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_002 Inactive 2023-11-22T01:02:36+00:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_001 Dismissed 2023-06-07T16:31:26+01:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_011 Dismissed 2022-11-22T12:07:38+00:00 2022-01-12T00:00:00+00:00 2023-02-14T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_010 Dismissed 2022-09-21T16:51:34+01:00 2022-01-12T00:00:00+00:00 2023-01-10T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_009 Dismissed 2022-09-20T11:17:25+01:00 2022-01-12T00:00:00+00:00 2022-12-19T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_008 Dismissed 2022-09-15T16:20:45+01:00 2022-01-12T00:00:00+00:00 2022-11-14T23:59:00+00:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 14/11/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_007 Dismissed 2022-05-16T15:35:06+01:00 2022-01-12T00:00:00+00:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 12/01/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_006 Dismissed 2022-05-16T15:33:37+01:00 2022-05-23T00:00:00+01:00 2022-09-30T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 30/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Dismissed 2021-11-29T13:21:53+00:00 2022-05-23T00:00:00+01:00 2022-09-03T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 23/05/2022 & finish on 03/09/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase started in October 2021 & will run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2021-09-07T16:27:51+01:00 2022-04-19T00:00:00+01:00 2022-07-31T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 19/04/2022 & finish on 31/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2023-03-10T15:59:26+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2021-08-05T16:06:16+01:00 2022-02-28T00:00:00+00:00 2022-07-21T00:00:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 28/02/2022 & finish on 21/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in October 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2023-03-10T15:58:32+00:00 2022-01-12T00:00:00+00:00 2023-03-10T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2021-06-10T12:30:47+01:00 2022-02-09T00:00:00+00:00 2022-07-02T23:59:00+01:00
It is currently anticipated Keadby 2 performance validation period will start on 09/02/2022 & finish on 02/07/2022. Prior to this there will be a commissioning phase, during which there will be periods of intermittent generation. The commissioning phase is scheduled to start in September 2021 & run until the start of the validation period. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2023-02-06T08:49:47+00:00 2022-01-12T00:00:00+00:00 2023-03-12T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.