This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-03-22T16:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_005 Active 2024-03-07T14:58:39+00:00 2022-07-14T17:23:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation until late April 24 with an increase towards 300MW in early May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_004 Dismissed 2024-02-13T16:06:55+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. From April 2024 Viking will generate at the required MW levels to commission the windfarm to provide the power required to support commissioning of the SSEN HVDC link to the mainland. The commissioning profile of Viking will be subject to a number of factors, including the progress on the HVDC link as well as any associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_003 Dismissed 2023-02-10T11:57:40+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking
48X000000000314Y
Other_0000000000000000039_002 Dismissed 2022-09-20T12:28:17+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000008909_002 Dismissed 2024-03-05T15:33:12+00:00 2024-03-04T16:37:00+00:00
Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000008909_001 Dismissed 2024-03-04T16:40:26+00:00 2024-03-04T16:37:00+00:00
Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_004 Inactive 2024-01-01T01:02:32+00:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_003 Dismissed 2023-02-28T10:01:18+00:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_002 Dismissed 2022-09-02T09:34:18+01:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_001 Dismissed 2022-09-01T16:31:20+01:00 2024-01-01T00:00:00+00:00 2030-01-01T00:00:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_004 Dismissed 2023-08-09T14:21:16+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_003 Dismissed 2023-08-09T14:15:15+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_002 Dismissed 2023-08-09T14:14:24+01:00 2023-08-09T14:09:00+01:00 2023-08-10T14:14:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_001 Dismissed 2023-08-09T14:11:02+01:00 2023-08-09T14:09:00+01:00
This is a test message
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_003 Active 2023-08-04T18:05:35+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_002 Dismissed 2023-08-04T17:37:40+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008121_001 Dismissed 2023-05-10T08:49:10+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_002 Active 2023-08-04T17:30:10+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008122_001 Dismissed 2023-05-10T08:50:25+01:00 2023-05-10T08:49:00+01:00
As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008120_001 Active 2023-05-10T08:47:39+01:00 2023-05-10T08:47:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008119_001 Active 2023-05-10T08:46:36+01:00 2023-05-10T08:43:00+01:00
As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000007750_001 Dismissed 2022-12-01T11:33:28+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000007750_001 Dismissed 2022-12-01T11:36:04+00:00 2022-12-01T12:00:00+00:00 2022-12-01T12:01:00+00:00
**Please ignore this Message** This is a test of auto transfer from SSE REMIT to Nordpool following SSE REMIT File Mover update.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_003 Inactive 2022-10-17T16:02:33+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_002 Dismissed 2022-10-17T14:46:02+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_001 Dismissed 2022-10-14T15:47:02+01:00 2022-10-14T15:35:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE GENERATION
48X000000000077M
Other_0000000000000000040_002 Inactive 2022-08-26T09:01:54+01:00 2022-08-26T00:00:00+01:00 2022-08-26T08:00:00+01:00
Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage.
SSE GENERATION
48X000000000077M
Other_0000000000000000040_001 Dismissed 2022-08-17T16:13:32+01:00 2022-08-26T00:00:00+01:00 2022-08-26T08:00:00+01:00
Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage.
SSE GENERATION
48X000000000077M
Other_0000000000000000031_006 Dismissed 2021-05-31T17:01:14+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_005 Dismissed 2021-05-10T13:01:06+01:00 2021-05-12T17:00:00+01:00 2021-08-20T23:00:00+01:00
Update: Start date of non-firm TEC period changed to 17:00 on 12 May 2021. End date of 20 August 2021 remains unchanged. Original:We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_004 Dismissed 2021-05-05T20:53:41+01:00 2021-05-12T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 12 May 2021. End date of 20 August 2021 remains unchanged. Original: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_003 Dismissed 2021-05-04T10:57:17+01:00 2021-05-11T00:01:00+01:00 2021-08-20T23:59:00+01:00
Update: Start date of non-firm TEC period changed to 11 May 2021. End date of 20 August 2021 remains unchanged. Original Remarks: We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC
SSE GENERATION
48X000000000077M
Other_0000000000000000031_002 Dismissed 2021-04-20T11:44:37+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
SSE GENERATION
48X000000000077M
Other_0000000000000000031_001 Dismissed 2021-04-20T11:32:25+01:00 2021-05-07T00:01:00+01:00 2021-08-20T23:59:00+01:00
We have been notified by National Grid ESO that, pending completion of network reinforcement works being conducted by SHETL in the nearby area, TEC in excess of 400MW at Peterhead Power Station will be non-firm in the period between 7 May 2021 and 20 August 2021. From time to time in this period, Peterhead’s output may be constrained by the limited availability of TEC.
SSE GENERATION
48X000000000077M
Other_0000000000000000037_002 Inactive 2021-05-22T00:01:53+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000037_001 Dismissed 2021-05-13T13:23:19+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000036_002 Inactive 2021-05-19T09:01:54+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000036_001 Dismissed 2021-05-13T13:22:03+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000035_002 Inactive 2021-05-17T09:01:53+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000035_001 Dismissed 2021-05-13T13:20:34+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000034_002 Inactive 2021-05-15T00:01:53+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000034_001 Dismissed 2021-05-12T13:04:36+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000033_002 Inactive 2021-05-14T00:01:52+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000033_001 Dismissed 2021-05-11T11:39:02+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000032_002 Inactive 2021-05-13T00:01:51+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M
Other_0000000000000000032_001 Dismissed 2021-05-10T12:49:52+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
SSE GENERATION
48X000000000077M
Other_0000000000000000018_002 Dismissed 2019-04-19T12:04:54+01:00 2019-04-19T09:08:00+01:00
SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications.
SSE GENERATION
48X000000000077M
Other_0000000000000000018_001 Dismissed 2019-04-19T09:10:02+01:00 2019-04-19T09:08:00+01:00
SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications.
SSE GENERATION
48X000000000077M
Other_0000000000000000019_001 Active 2019-04-19T12:04:36+01:00 2019-04-19T12:03:00+01:00
The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations