Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_036 Dismissed 2023-10-06T15:08:54+01:00 2023-07-18T13:30:00+01:00 2023-10-06T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_035 Dismissed 2023-10-05T16:49:11+01:00 2023-07-18T13:30:00+01:00 2023-10-06T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_034 Dismissed 2023-10-03T16:16:32+01:00 2023-07-18T13:30:00+01:00 2023-10-06T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 06th Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_033 Dismissed 2023-10-03T11:39:12+01:00 2023-07-18T13:30:00+01:00 2023-10-03T20:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_032 Dismissed 2023-10-03T07:08:50+01:00 2023-07-18T13:30:00+01:00 2023-10-03T12:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 03rd Oct 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.250MW by the end of Q4 2023, c.525MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_031 Dismissed 2023-10-02T08:51:38+01:00 2023-07-18T13:30:00+01:00 2023-10-03T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.325MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_030 Dismissed 2023-10-01T17:10:08+01:00 2023-07-18T13:30:00+01:00 2023-10-03T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 03rd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_029 Dismissed 2023-09-30T16:22:05+01:00 2023-07-18T13:30:00+01:00 2023-10-02T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 02nd OCT 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_028 Dismissed 2023-09-29T16:49:18+01:00 2023-07-18T13:30:00+01:00 2023-09-30T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 30th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_027 Dismissed 2023-09-28T14:32:16+01:00 2023-07-18T13:30:00+01:00 2023-09-29T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 29th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_026 Dismissed 2023-09-27T15:26:24+01:00 2023-07-18T13:30:00+01:00 2023-09-28T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 28th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_025 Dismissed 2023-09-26T15:41:57+01:00 2023-07-18T13:30:00+01:00 2023-09-27T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_024 Dismissed 2023-09-25T17:45:52+01:00 2023-07-18T13:30:00+01:00 2023-09-27T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_023 Dismissed 2023-09-23T12:53:08+01:00 2023-07-18T13:30:00+01:00 2023-09-26T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_022 Dismissed 2023-09-22T17:41:06+01:00 2023-07-18T13:30:00+01:00 2023-09-23T19:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_021 Dismissed 2023-09-19T18:32:22+01:00 2023-07-18T13:30:00+01:00 2023-09-23T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_020 Dismissed 2023-09-18T17:45:34+01:00 2023-07-18T13:30:00+01:00 2023-09-20T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_019 Dismissed 2023-09-17T18:18:20+01:00 2023-07-18T13:30:00+01:00 2023-09-19T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_018 Dismissed 2023-09-14T21:28:32+01:00 2023-07-18T13:30:00+01:00 2023-09-18T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_017 Dismissed 2023-09-12T08:50:34+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:45:43+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:48:41+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:05+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:14+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_014 Dismissed 2023-09-05T17:41:03+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_013 Dismissed 2023-08-30T16:05:41+01:00 2023-07-18T13:30:00+01:00 2023-09-06T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_012 Dismissed 2023-08-25T21:32:06+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_011 Dismissed 2023-08-25T10:13:08+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_010 Dismissed 2023-08-22T11:18:09+01:00 2023-07-18T13:30:00+01:00 2023-08-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_009 Dismissed 2023-08-18T09:18:00+01:00 2023-07-18T13:30:00+01:00 2023-08-23T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_008 Dismissed 2023-08-14T14:39:29+01:00 2023-07-18T13:30:00+01:00 2023-08-20T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_007 Dismissed 2023-08-09T17:31:28+01:00 2023-07-18T13:30:00+01:00 2023-08-15T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_006 Dismissed 2023-08-04T15:49:36+01:00 2023-07-18T13:30:00+01:00 2023-08-11T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_005 Dismissed 2023-08-01T14:41:23+01:00 2023-07-18T13:30:00+01:00 2023-08-07T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_004 Dismissed 2023-07-28T16:16:25+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_003 Dismissed 2023-07-28T16:14:41+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_002 Dismissed 2023-07-24T13:53:38+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_001 Dismissed 2023-07-18T13:28:20+01:00 2023-07-18T13:30:00+01:00 2023-07-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_009 Dismissed 2023-05-18T13:59:17+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_008 Dismissed 2023-05-16T09:17:28+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_007 Dismissed 2023-05-16T09:02:22+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_006 Dismissed 2023-05-12T16:59:23+01:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000000038_005 Dismissed 2023-02-10T11:54:13+00:00 2021-02-11T11:31:00+00:00
It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_003 Active 2024-06-21T14:22:29+01:00 2023-11-10T12:44:00+00:00 2025-03-31T00:00:00+01:00
It is expected that Dogger Bank B commissioning will start in H1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_002 Dismissed 2024-03-22T16:27:38+00:00 2023-11-10T12:44:00+00:00 2025-01-30T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in Q1 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available, As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_001 Dismissed 2023-11-10T15:42:44+00:00 2023-11-10T12:44:00+00:00 2024-12-31T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_003 Dismissed 2024-01-25T10:06:41+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_002 Dismissed 2024-01-23T14:55:33+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_001 Dismissed 2024-01-23T08:48:33+00:00 2024-01-22T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_002 Inactive 2023-11-22T01:02:36+00:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.