Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 1 2 3 4 5 >
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_009 Dismissed 2022-09-20T11:17:25+01:00 2022-01-12T00:00:00+00:00 2022-12-19T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_010 Dismissed 2022-09-21T16:51:34+01:00 2022-01-12T00:00:00+00:00 2023-01-10T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 10/01/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_001 Dismissed 2022-12-19T16:02:46+00:00 2022-01-12T00:00:00+00:00 2023-02-11T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 11/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_011 Dismissed 2022-11-22T12:07:38+00:00 2022-01-12T00:00:00+00:00 2023-02-14T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 14/02/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_003 Dismissed 2023-03-10T15:58:32+00:00 2022-01-12T00:00:00+00:00 2023-03-10T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_002 Dismissed 2023-02-06T08:49:47+00:00 2022-01-12T00:00:00+00:00 2023-03-12T23:59:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 12/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_004 Dismissed 2023-03-10T15:59:26+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Medway
T_MEDP-1
Other_0000000000000007814_001 Dismissed 2022-12-22T17:45:01+00:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Dogger Bank A
48X0000000003113
Other_0000000000000008140_002 Dismissed 2023-07-19T13:26:01+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
Dogger Bank A
48X0000000003113
Other_0000000000000008140_001 Dismissed 2023-05-18T14:01:15+01:00 2023-05-18T14:01:00+01:00 2023-07-23T00:00:00+01:00
It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_001 Dismissed 2023-07-18T13:28:20+01:00 2023-07-18T13:30:00+01:00 2023-07-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Great Island
Great Island
Other_0000000000000008203_002 Dismissed 2023-06-19T10:34:59+01:00 2023-06-19T10:07:00+01:00 2023-07-28T10:00:00+01:00
Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_004 Dismissed 2023-07-28T16:16:25+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_003 Dismissed 2023-07-28T16:14:41+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_002 Dismissed 2023-07-24T13:53:38+01:00 2023-07-18T13:30:00+01:00 2023-08-02T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_005 Dismissed 2023-08-01T14:41:23+01:00 2023-07-18T13:30:00+01:00 2023-08-07T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000008299_002 Dismissed 2023-08-09T14:14:24+01:00 2023-08-09T14:09:00+01:00 2023-08-10T14:14:00+01:00
This is a test message
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_006 Dismissed 2023-08-04T15:49:36+01:00 2023-07-18T13:30:00+01:00 2023-08-11T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_007 Dismissed 2023-08-09T17:31:28+01:00 2023-07-18T13:30:00+01:00 2023-08-15T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_008 Dismissed 2023-08-14T14:39:29+01:00 2023-07-18T13:30:00+01:00 2023-08-20T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_009 Dismissed 2023-08-18T09:18:00+01:00 2023-07-18T13:30:00+01:00 2023-08-23T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_010 Dismissed 2023-08-22T11:18:09+01:00 2023-07-18T13:30:00+01:00 2023-08-28T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_012 Dismissed 2023-08-25T21:32:06+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_011 Dismissed 2023-08-25T10:13:08+01:00 2023-07-18T13:30:00+01:00 2023-08-31T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_013 Dismissed 2023-08-30T16:05:41+01:00 2023-07-18T13:30:00+01:00 2023-09-06T07:00:00+01:00
It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_002 Dismissed 2023-09-07T17:00:31+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
Seagreen Wind Energy Ltd
48X000000000263P
Other_0000000000000008388_001 Dismissed 2023-09-06T16:25:23+01:00 2023-09-07T14:00:00+01:00 2023-09-07T17:00:00+01:00
SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:48:41+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:05+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_015 Dismissed 2023-09-06T11:35:14+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_014 Dismissed 2023-09-05T17:41:03+01:00 2023-07-18T13:30:00+01:00 2023-09-13T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_017 Dismissed 2023-09-12T08:50:34+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_016 Dismissed 2023-09-12T08:45:43+01:00 2023-07-18T13:30:00+01:00 2023-09-15T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_018 Dismissed 2023-09-14T21:28:32+01:00 2023-07-18T13:30:00+01:00 2023-09-18T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_019 Dismissed 2023-09-17T18:18:20+01:00 2023-07-18T13:30:00+01:00 2023-09-19T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Peterhead
T_PEHE-1
Other_0000000000000008420_002 Dismissed 2023-09-18T12:19:36+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008420_001 Dismissed 2023-09-15T15:01:11+01:00 2023-09-19T10:00:00+01:00 2023-09-19T19:00:00+01:00
Operating at circa 300MW for statutory testing.
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113
Other_0000000000000008251_020 Dismissed 2023-09-18T17:45:34+01:00 2023-07-18T13:30:00+01:00 2023-09-20T07:00:00+01:00
It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated.
Peterhead
T_PEHE-1
Other_0000000000000008421_002 Dismissed 2023-09-18T12:19:17+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008421_001 Dismissed 2023-09-15T15:02:40+01:00 2023-09-20T08:00:00+01:00 2023-09-20T19:00:00+01:00
Operating at circa 550MW for statutory testing.
Peterhead
T_PEHE-1
Other_0000000000000008436_003 Dismissed 2023-09-21T14:38:30+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_002 Dismissed 2023-09-21T14:27:09+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
T_PEHE-1 Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008436_001 Dismissed 2023-09-20T08:29:55+01:00 2023-09-21T12:00:00+01:00 2023-09-21T19:00:00+01:00
Running at Circa 300MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_006 Dismissed 2023-09-22T15:13:14+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_005 Dismissed 2023-09-21T17:33:37+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times referenced in the comments section in Elexon as requested
Peterhead
T_PEHE-1
Other_0000000000000008437_002 Dismissed 2023-09-21T14:26:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
T_PEHE-1 Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_001 Dismissed 2023-09-20T08:32:32+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:00:00+01:00
Running at Circa 550MW for statutory testing
Peterhead
T_PEHE-1
Other_0000000000000008437_004 Dismissed 2023-09-21T17:03:58+01:00 2023-09-22T08:00:00+01:00 2023-09-22T19:01:00+01:00
T_PEHE-1 Running at Circa 780MW for statutory testing. Resubmitted with GMT times in Elexon