Last update at: 2023-05-18T14:30:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
1 2 3 > | |||||||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_009 | Dismissed | 2023-05-18T13:59:17+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_008 | Dismissed | 2023-05-16T09:17:28+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_004 | Dismissed | 2022-09-20T12:19:09+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_003 | Dismissed | 2021-11-18T10:21:30+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Dogger Bank A |
Other_0000000000000000038_002 | Dismissed | 2021-11-02T14:08:36+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
Other_0000000000000000038_001 | Dismissed | 2021-11-02T11:32:15+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_001 | Active | 2023-05-10T08:50:25+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_001 | Active | 2023-05-10T08:49:10+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008120_001 | Active | 2023-05-10T08:47:39+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008119_001 | Active | 2023-05-10T08:46:36+01:00 | 2023-05-10T08:43:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
Viking Energy Wind Farm LLP |
48X000000000314Y | Other_0000000000000000039_003 | Active | 2023-02-10T11:57:40+00:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|
Viking |
48X000000000314Y | Other_0000000000000000039_002 | Dismissed | 2022-09-20T12:28:17+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
|
Viking Wind Farm |
Other_0000000000000000039_001 | Dismissed | 2022-07-14T17:25:58+01:00 | 2022-07-14T17:23:00+01:00 | It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works |
||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_017 | Active | 2022-11-04T12:50:38+00:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Jul 23. As generation becomes available, this will be reported via the portal. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_016 | Dismissed | 2022-09-20T14:16:02+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen first export achieved 22 Aug with full availability expected by Apr 23. As generation becomes available, this will be reported via the portal. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_015 | Dismissed | 2022-09-20T12:16:29+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_014 | Dismissed | 2022-08-05T16:52:37+01:00 | 2021-03-09T13:33:00+00:00 | Commissioning & energisation is ongoing,first export forecast Mid-Aug & full availability by Apr23.BMU6 first export as updated via the portal.BMU5 expected to energise full allocation 80MW early Oct.BMU4 expected to energise with 20MW end Oct with full allocation mid Apr23.BMU3 expected to energise with 60MW end of Sept with full availability Apr23.BMU2 expected to energise with 20MW early Nov, with full availability Mar23.BMU1 expected to energise with 40MW Nov & reach full availability Apr23 |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_013 | Dismissed | 2022-07-21T17:11:40+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning is ongoing, with circuit 1 forecast complete and commissioned by End-July 2022. Full commercial operation is expected to commence End-April 2023. It is expected that First Generation will be Early-Aug, with 100MW by End-Aug, 500MW Oct, 720MW December 2022 and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_012 | Dismissed | 2022-06-17T11:53:11+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning has commenced and is ongoing, with circuit 1 forecast complete and commissioned by Late-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW October, 720MW December and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_011 | Dismissed | 2022-04-27T13:19:42+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with circuit 1 forecast complete and commissioned by mid-July 2022. Full commercial operation is expected to commence Mid-April 2023. It is expected that over 2022 there will be 500MW September, 720MW December and the total capacity of 1075MW available by April 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_010 | Dismissed | 2022-03-29T16:49:45+01:00 | 2021-03-09T13:33:00+00:00 | Seagreen commissioning period started late March 2022, with the Offshore Substation being installed early March 2022 and circuit 1 complete and commissioned by mid-July 2022. Full commercial operation is expected to commence March 2023. It is expected that over 2022 there will be 270MW available August 2022, 600MW by late Q3 and the total capacity of 1075MW available by late Q1 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_009 | Dismissed | 2022-03-07T10:12:53+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_008 | Dismissed | 2022-02-07T16:15:11+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_007 | Dismissed | 2022-02-07T11:55:37+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_006 | Dismissed | 2022-01-13T17:07:41+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_005 | Dismissed | 2021-12-07T13:46:29+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_004 | Dismissed | 2021-11-30T10:14:00+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
|
Seagreen Wind Energy Ltd |
Other_0000000000000000029_003 | Dismissed | 2021-08-16T12:27:40+01:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_002 | Dismissed | 2021-03-09T13:55:35+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Seagreen wind energy Ltd |
Other_0000000000000000029_001 | Dismissed | 2021-03-09T13:41:20+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000042_001 | Dismissed | 2022-10-14T15:47:02+01:00 | 2022-10-14T15:35:00+01:00 | GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made. |
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000024_001 | Active | 2019-06-13T12:30:13+01:00 | 2019-06-13T12:30:00+01:00 | Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_002 | Dismissed | 2019-04-19T12:04:54+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_001 | Dismissed | 2019-04-19T09:10:02+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000019_001 | Active | 2019-04-19T12:04:36+01:00 | 2019-04-19T12:03:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_002 | Dismissed | 2019-04-19T09:08:42+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_001 | Dismissed | 2019-04-18T19:00:28+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000015_001 | Active | 2019-03-19T14:46:49+00:00 | 2019-03-19T12:55:00+00:00 | T_FIDL-1 - With immediate effect, unit 1 will be withdrawn from service. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_003 | Active | 2017-12-19T12:08:01+00:00 | 2018-04-01T00:00:00+01:00 | Peterhead TEC has been increased to 1180MW on an enduring basis from 1st April 2018 and will continue operations at 1180MW going forward. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_002 | Dismissed | 2017-11-07T13:55:07+00:00 | 2018-04-01T00:00:00+01:00 | Subject to CMP268 not being legally challenged, we intend to increase TEC at Peterhead to 1180MW on an enduring basis commencing 1st April 2018 and continue operations at 1180MW going forward. |
|
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_001 | Dismissed | 2017-03-23T14:04:44+00:00 | 2018-04-01T00:00:00+01:00 | From the 1st April 2018 we will be reducing the TEC at Peterhead to zero. The cancellation of our TEC at this time is a risk mitigation measure to avoid a substantial cancellation charge if we were to cancel later in the year, once we have completed our review of the stations future, which we announced on 6 February 2017. We will reapply for TEC and subject to receiving a satisfactory offer from NGET, reinstate TEC should our review conclude that the station has an enduring future. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_001 | Dismissed | 2020-10-23T08:25:15+01:00 | 2020-10-25T07:45:00+00:00 | 2020-10-26T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_003 | Inactive | 2020-10-28T01:01:54+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000000026_002 | Dismissed | 2020-10-26T09:06:10+00:00 | 2020-10-26T07:45:00+00:00 | 2020-10-27T23:59:00+00:00 | Great Island CCGT Unit on post outage testing. |
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_002 | Inactive | 2020-12-01T20:01:53+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000000028_001 | Dismissed | 2020-12-01T09:29:14+00:00 | 2020-12-01T09:30:00+00:00 | 2020-12-01T19:00:00+00:00 | Following PN to allow GT Tuning. some variation from PN expected. |
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000025_003 | Inactive | 2021-01-11T01:02:32+00:00 | 2020-09-02T00:01:00+01:00 | 2021-01-10T23:59:00+00:00 | Following the phased array test on GT1 during 28-30 August, the outage programme has been adjusted for rectification of this issue from September onwards. Should the ongoing work provide further information then we will adjust the outage programme accordingly. |