This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-04-25T12:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
1 2 3 4 5 >
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000009038_002 Inactive 2024-04-23T01:02:47+01:00 2024-04-22T00:01:00+01:00 2024-04-22T23:59:00+01:00
Peterhead 12 hour on load run requested of GT 11 and 12 for preservation of plant during Monday 22nd of April 2024.
Dogger Bank A
48X0000000003113
Other_0000000000000009040_002 Inactive 2024-04-22T10:37:32+01:00 2024-04-19T09:00:00+01:00 2025-01-06T00:00:00+00:00
Dogger Bank A is in the commissioning phase and it is expected that there will be a steady increase in installed capacity with c. 400MW available by the end of Q2 2024, c.800MW by the end of Q3 2024, c.1050MW by the end of Q4 2024 and the total capacity of 1.2GW available during Q1 2025.
Other_0000000000000008908_004 Inactive 2024-03-18T01:02:32+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Other_0000000000000008899_004 Inactive 2024-03-08T01:02:31+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Great Island
Great Island
Other_0000000000000008845_002 Inactive 2024-02-13T14:47:42+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_004 Inactive 2024-01-01T01:02:32+00:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008178_002 Inactive 2023-11-22T01:02:36+00:00 2023-11-14T00:00:00+00:00 2023-11-21T23:59:00+00:00
Keadby 2 will be subject to approximately one week of hot commissioning following Gas Turbine and generator outage works. REMIT will be updated when commissioning profiles are confirmed.
SSE Energy Supply Limited
A0001004V.UK
Other_0000000000000008476_002 Inactive 2023-10-24T23:47:32+01:00 2023-10-24T22:36:00+01:00 2023-10-24T22:40:00+01:00
end of outage
Other_0000000000000007814_002 Inactive 2023-07-06T01:02:32+01:00 2022-12-22T17:39:00+00:00 2023-07-06T00:00:00+01:00
Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023
Tawnaghmore
TAWN1
Other_0000000000000008024_002 Inactive 2023-03-16T09:40:56+00:00 2027-03-16T09:39:00+00:00 2027-03-16T09:40:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Rhode
RHODE1
Other_0000000000000008023_002 Inactive 2023-03-16T09:39:01+00:00 2027-03-16T09:37:00+00:00 2027-03-16T09:38:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Tarbert
TB3
Other_0000000000000008022_002 Inactive 2023-03-16T09:36:20+00:00 2027-03-16T09:33:00+00:00 2027-03-16T09:34:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008021_002 Inactive 2023-03-15T13:51:41+00:00 2027-03-15T13:47:00+00:00 2027-03-15T13:48:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
Great Island
Great Island
Other_0000000000000008020_002 Inactive 2023-03-15T12:11:38+00:00 2027-03-15T11:45:00+00:00 2027-03-15T11:46:00+00:00
***TEST ONLY*** Testing publishing Other Market Information at Unit level
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000000030_005 Inactive 2023-03-15T10:02:32+00:00 2022-01-12T00:00:00+00:00 2023-03-15T09:00:00+00:00
It is currently anticipated that Keadby 2 performance validation period which started on 12/01/2022 will finish on 15/03/2023. There will be periods of intermittent generation. As relevant details of the validation plans become firmer REMIT will be updated.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000042_003 Inactive 2022-10-17T16:02:33+01:00 2022-10-14T15:35:00+01:00 2022-10-17T14:48:00+01:00
GI4 Great Island CCGT. Generator code 47W0000000001024. Emergent plant fault on auxiliary systems has resulted in an unreliable start-up. If unit is dispatched off, it may not be able to be restarted. If unit fails to restart a REMIT declaration will be made.
SSE GENERATION
48X000000000077M
Other_0000000000000000040_002 Inactive 2022-08-26T09:01:54+01:00 2022-08-26T00:00:00+01:00 2022-08-26T08:00:00+01:00
Foyers Power station dam is undergoing testing during the forthcoming station outage. In advance of the outage the water level will be raised to Top water level and this has the potential to incur pumping activity in the hours leading up to the outage.
SSE GENERATION
48X000000000077M
Other_0000000000000000037_002 Inactive 2021-05-22T00:01:53+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 0MW non-firm TEC from 08:00 on 19/05/2021 to 23:00 on 21/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000036_002 Inactive 2021-05-19T09:01:54+01:00 2021-05-17T08:00:00+01:00 2021-05-19T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 500MW non-firm TEC from 08:00 on 17/05/2021 to 08:00 on 19/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000035_002 Inactive 2021-05-17T09:01:53+01:00 2021-05-14T23:00:00+01:00 2021-05-17T08:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 14/05/2021 to 08:00 on 17/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000034_002 Inactive 2021-05-15T00:01:53+01:00 2021-05-13T23:00:00+01:00 2021-05-14T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 13/05/2021 to 23:00 on 14/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000033_002 Inactive 2021-05-14T00:01:52+01:00 2021-05-12T23:00:00+01:00 2021-05-13T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 23:00 on 12/05/2021 to 23:00 on 13/05/2021 (BST).
SSE GENERATION
48X000000000077M
Other_0000000000000000032_002 Inactive 2021-05-13T00:01:51+01:00 2021-05-12T17:00:00+01:00 2021-05-12T23:00:00+01:00
D-2 non-firm TEC Guidance issued: 780MW non-firm TEC from 17:00 on 12/05/2021 to 23:00 on 12/05/2021.
Keadby
T_KEAD-1
Other_0000000000000009044_003 Dismissed 2024-04-25T10:23:07+01:00 2024-04-26T00:00:00+01:00 2024-04-26T23:59:59+01:00
Asset Integrity. Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
Keadby
T_KEAD-1
Other_0000000000000009044_002 Dismissed 2024-04-25T09:44:41+01:00 2024-04-26T00:00:00+01:00 2024-06-06T00:00:00+01:00
KEAD_1 10 hour on load run requested for preservation of plant during Friday 26th April 2024.
Keadby
T_KEAD-1
Other_0000000000000009044_001 Dismissed 2024-04-24T19:54:16+01:00 2024-04-25T00:00:00+01:00 2024-06-06T00:00:00+01:00
Following the KEAD_1 out-of-merit run commencing 25th April ’24, a dynamic data change to 720min NDZ will be implemented.
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000009038_001 Dismissed 2024-04-19T14:29:07+01:00 2024-04-22T00:01:00+01:00 2024-04-22T23:59:00+01:00
Peterhead 12 hour on load run requested of GT 11 and 12 for preservation of plant during Monday 22nd of April 2024.
Dogger Bank A
48X0000000003113
Other_0000000000000009040_001 Dismissed 2024-04-22T09:04:24+01:00 2024-04-19T09:00:00+01:00 2025-01-06T00:00:00+00:00
Dogger Bank A is in the commissioning phase and it is expected that there will be a steady increase in installed capacity with c. 400MW available by the end of Q2 2024, c.800MW by the end of Q3 2024, c.1050MW by the end of Q4 2024 and the total capacity of 1.2GW available during Q1 2025.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_006 Dismissed 2024-04-03T10:47:47+01:00 2022-07-14T17:23:00+01:00 2024-07-01T12:00:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation from late April 24 with an increase towards 300MW in May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_005 Dismissed 2024-03-07T14:58:39+00:00 2022-07-14T17:23:00+01:00
Its anticipated Viking Windfarm will be fully commissioned July 24, with over 400MW being exported to the Grid. From April 24 Viking will generate at the required level to commission the windfarm, to provide the power required to support commissioning of SSEN HVDC link. The commissioning profile will have low levels of generation until late April 24 with an increase towards 300MW in early May 24 and will be subject to various factors including the progress on the HVDC link and associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_004 Dismissed 2024-02-13T16:06:55+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. From April 2024 Viking will generate at the required MW levels to commission the windfarm to provide the power required to support commissioning of the SSEN HVDC link to the mainland. The commissioning profile of Viking will be subject to a number of factors, including the progress on the HVDC link as well as any associated works.
Viking Energy Wind Farm LLP
48X000000000314Y
Other_0000000000000000039_003 Dismissed 2023-02-10T11:57:40+00:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking
48X000000000314Y
Other_0000000000000000039_002 Dismissed 2022-09-20T12:28:17+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Viking Wind Farm
Other_0000000000000000039_001 Dismissed 2022-07-14T17:25:58+01:00 2022-07-14T17:23:00+01:00
It is anticipated that Viking Windfarm on Shetland will be fully commissioned by July 2024, with over 400MW being exported to the National Grid. It is likely that up to approximately 100MW will be available from April 2024. This is subject to a number of factors including weather conditions and the progress on the separate 600MW HVDC link project to Shetland, as well as any associated works
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000008538_001 Dismissed 2023-11-10T15:42:44+00:00 2023-11-10T12:44:00+00:00 2024-12-31T00:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Keadby
T_KEAD-2
Other_0000000000000008908_003 Dismissed 2024-03-08T11:26:43+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 4-5 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_002 Dismissed 2024-03-05T14:03:34+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified (anticipated to be 2-3 days work).
Keadby
T_KEAD-2
Other_0000000000000008908_001 Dismissed 2024-03-04T13:13:31+00:00 2024-03-04T00:00:00+00:00 2024-03-18T00:00:00+00:00
SSE Keadby 2 Power Station is currently restricted in it's range of operation due to a technical issue. Additionally, once offload, the plant will be unable to restart until the issue is rectified.
Medway
T_MEDP-1
Other_0000000000000008899_003 Dismissed 2024-03-05T14:59:17+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emissions testing of both gas turbines. This will require periods of running at MEL and other varying loads.
Medway
T_MEDP-1
Other_0000000000000008899_002 Dismissed 2024-02-29T14:00:58+00:00 2024-03-04T06:00:00+00:00 2024-03-07T23:59:00+00:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
Medway
T_MEDP-1
Other_0000000000000008899_001 Dismissed 2024-02-29T13:41:02+00:00 2024-03-04T06:00:00+00:00 2024-04-04T23:59:00+01:00
Medway is carrying out emission testing of both gas turbines along with RSO testing of all 3 generators. This will require periods of running at MEL and other various loads.
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000008909_002 Dismissed 2024-03-05T15:33:12+00:00 2024-03-04T16:37:00+00:00
Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead
SSE Thermal Generation (Scotland) Ltd
48X0000000003024
Other_0000000000000008909_001 Dismissed 2024-03-04T16:40:26+00:00 2024-03-04T16:37:00+00:00
Subject to contract, discussions are ongoing with regards a multi-week 0MW contract at Peterhead. During the contract period there would be no output from Peterhead
Great Island
Great Island
Other_0000000000000008845_001 Dismissed 2024-02-13T14:42:10+00:00 2030-02-13T14:40:00+00:00 2030-02-13T14:41:00+00:00
This is a test of SSE REMIT application functionality only. No action should be taken.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_003 Dismissed 2024-01-25T10:06:41+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_002 Dismissed 2024-01-23T14:55:33+00:00 2024-01-16T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
KEADBY GEN. LTD
48X000000000073U
Other_0000000000000008783_001 Dismissed 2024-01-23T08:48:33+00:00 2024-01-22T00:00:00+00:00 2024-06-29T00:00:00+01:00
Kead-2 is subject to an ongoing restriction meaning that following 5 starts the unit will require a period of unavailability. The date and duration of the unavailability will be reflected in a separate REMIT notification when known. While onload after the 5th start the unit will remain available therefore the start time of the period of unavailability will be determined when the unit is brought below SEL.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_003 Dismissed 2023-02-28T10:01:18+00:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the EPA, Tarbert is subject to a limitation on operating hours. Should these hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly. For the avoidance of doubt, all units at the station are required to close by 31st December 2023 at the latest under Condition 5.17 referenced above.
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_002 Dismissed 2022-09-02T09:34:18+01:00 2022-09-01T00:00:00+01:00 2023-12-31T23:59:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly
SSE Generation Ireland Ltd
47X0000000000592
Other_0000000000000000041_001 Dismissed 2022-09-01T16:31:20+01:00 2024-01-01T00:00:00+00:00 2030-01-01T00:00:00+00:00
Under Condition 5.17 of the Industrial Emissions Licence granted to Tarbert Generating Station (“Tarbert”) by the Environmental Protection Agency, Tarbert is subject to a limitation on operating hours. Tarbert currently has approximately 3000 running hours remaining for Units 3 and 4 combined. Should these running hours be exhausted before 31st December 2023, Units 3 and 4 will no longer be available to run and any REMIT notifications will be updated accordingly