Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 | |||||||||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_009 | Dismissed | 2022-03-07T10:12:53+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by mid-June 2022. Full commercial operation is expected to commence February 2023. It is expected that over 2022 there will be 270MW available July 2022, 600MW by late Q3 and the total capacity of 1075MW available by Q1 2023. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_008 | Dismissed | 2022-02-07T16:15:11+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start March 2022 subject to the Offshore Substation being installed March 2022 and circuit 1 complete and commissioned by end of May 2022. Full commercial operation is expected to commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 and the total capacity of 1075MW available by the end of 2022. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_007 | Dismissed | 2022-02-07T11:55:37+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 21/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_006 | Dismissed | 2022-01-13T17:07:41+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 01/05/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_005 | Dismissed | 2021-12-07T13:46:29+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 07/03/22 subject to the Offshore Substation being installed February 2022 and circuit 1 complete and commissioned by 18/04/22. Full commercial operation will commence January 2023. It is expected that over 2022 there will be 270MW available Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000000029_004 | Dismissed | 2021-11-30T10:14:00+00:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
|||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_003 | Dismissed | 2021-08-16T12:27:40+01:00 | 2021-03-09T13:33:00+00:00 | It is anticipated that Seagreen commissioning period will start 06/03/22 subject to the Offshore Substation being installed January 2022 and circuit 1 complete and commissioned by 06/03/22. Full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be 270MW available by the early Q2, 600MW by early Q3 2022 and the total capacity of 1075MW available by the end of 2022. As relevant details of the commissioning plans become firmer REMIT will be updated |
||||
Seagreen Wind Energy Ltd |
Other_0000000000000000029_002 | Dismissed | 2021-03-09T13:55:35+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Seagreen wind energy Ltd |
Other_0000000000000000029_001 | Dismissed | 2021-03-09T13:41:20+00:00 | 2021-03-09T13:33:00+00:00 | It is currently anticipated that Seagreen commissioning period will start on 01/12/2021 & full commercial operation will commence by the end of 2022. It is expected that over 2022 there will be a steady increase in installed capacity with approximately 270MW available by the end of Q1 2022, 600MW by the end of Q2 2022 and the total capacity of 1075MW available by the end of 2022.As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_009 | Dismissed | 2023-05-18T13:59:17+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_008 | Dismissed | 2023-05-16T09:17:28+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_007 | Dismissed | 2023-05-16T09:02:22+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q2 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_006 | Dismissed | 2023-05-12T16:59:23+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q2 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000000038_005 | Dismissed | 2023-02-10T11:54:13+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_004 | Dismissed | 2022-09-20T12:19:09+01:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
48X0000000003113 | Other_0000000000000000038_003 | Dismissed | 2021-11-18T10:21:30+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
|||
Dogger Bank A |
Other_0000000000000000038_002 | Dismissed | 2021-11-02T14:08:36+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
Dogger Bank A |
Other_0000000000000000038_001 | Dismissed | 2021-11-02T11:32:15+00:00 | 2021-02-11T11:31:00+00:00 | It is anticipated that Dogger Bank A commissioning period will start on 23/07/2023 with 300MW to be installed by this date and full commercial operation will commence by end of Q1 of 2024. It is expected that there will be a steady increase in installed capacity with approximately 790MW available by the end of Q3 2023, 1050MW by the end of Q4 2023 and the total capacity of 1.2GW available by the end of Q1 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000024_001 | Active | 2019-06-13T12:30:13+01:00 | 2019-06-13T12:30:00+01:00 | Fiddler’s Ferry Units 2, 3 and 4 (BMU IDs: T_FIDL-2, T_FIDL-3, T_FIDL-4) are expected to close with effect from 31 March 2020. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000019_001 | Active | 2019-04-19T12:04:36+01:00 | 2019-04-19T12:03:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_002 | Dismissed | 2019-04-19T12:04:54+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000018_001 | Dismissed | 2019-04-19T09:10:02+01:00 | 2019-04-19T09:08:00+01:00 | SSE is currently experiencing a communication fault with National Grid, and are therefore unable to submit Physical Notifications. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_002 | Dismissed | 2019-04-19T09:08:42+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000017_001 | Dismissed | 2019-04-18T19:00:28+01:00 | 2019-04-18T19:00:00+01:00 | The communication fault between SSE & National Grid has now been resolved and we have returned to normal business operations |
|||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000000015_001 | Active | 2019-03-19T14:46:49+00:00 | 2019-03-19T12:55:00+00:00 | T_FIDL-1 - With immediate effect, unit 1 will be withdrawn from service. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_003 | Active | 2017-12-19T12:08:01+00:00 | 2018-04-01T00:00:00+01:00 | Peterhead TEC has been increased to 1180MW on an enduring basis from 1st April 2018 and will continue operations at 1180MW going forward. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_002 | Dismissed | 2017-11-07T13:55:07+00:00 | 2018-04-01T00:00:00+01:00 | Subject to CMP268 not being legally challenged, we intend to increase TEC at Peterhead to 1180MW on an enduring basis commencing 1st April 2018 and continue operations at 1180MW going forward. |
|||
SSE GENERATION |
48X000000000077M | Other_0000000000000000006_001 | Dismissed | 2017-03-23T14:04:44+00:00 | 2018-04-01T00:00:00+01:00 | From the 1st April 2018 we will be reducing the TEC at Peterhead to zero. The cancellation of our TEC at this time is a risk mitigation measure to avoid a substantial cancellation charge if we were to cancel later in the year, once we have completed our review of the stations future, which we announced on 6 February 2017. We will reapply for TEC and subject to receiving a satisfactory offer from NGET, reinstate TEC should our review conclude that the station has an enduring future. |