Last update at: 2024-10-03T15:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Unit Location | Unit Name | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|---|---|
< 2 3 4 5 6 > | |||||||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009046_001 | Dismissed | 2024-04-25T12:04:26+01:00 | 2024-04-27T23:00:00+01:00 | 2024-05-21T23:00:00+01:00 | T_PEHE-1. Auxiliary boiler taken out of service to allow statutory inspection to be completed. While auxiliary boiler is out of service, block in inflexible following shutdown as a period of 37 hours is required to allow sufficient cooling of steam turbine to allow re-start without auxiliary steam. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_005 | Dismissed | 2024-05-16T18:41:49+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_005 | Dismissed | 2024-05-16T18:41:53+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_004 | Dismissed | 2024-05-16T18:36:19+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-16T18:37:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_003 | Dismissed | 2024-05-14T08:51:35+01:00 | 2024-05-14T23:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_002 | Dismissed | 2024-05-13T17:15:57+01:00 | 2024-05-15T08:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running for post outage commissioning works. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009081_001 | Dismissed | 2024-05-13T11:11:57+01:00 | 2024-05-15T08:00:00+01:00 | 2024-05-17T21:00:00+01:00 | T_PEHE-1 block running at circa 600MW for post outage commissioning works. |
||
Other_0000000000000009072_002 | Inactive | 2024-05-17T23:02:32+01:00 | 2024-05-17T07:00:00+01:00 | 2024-05-17T22:00:00+01:00 | For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours. |
||||
Great Island |
Great Island |
Other_0000000000000009072_001 | Dismissed | 2024-05-08T10:08:54+01:00 | 2024-05-17T07:00:00+01:00 | 2024-05-17T22:00:00+01:00 | For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 17/05/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009108_002 | Inactive | 2024-05-24T16:25:24+01:00 | 2024-05-24T00:00:00+01:00 | **** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Market Participant Level |
|||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009108_001 | Dismissed | 2024-05-24T16:24:36+01:00 | 2024-05-24T00:00:00+01:00 | **** PLEASE IGNORE ***** Test publication to check SSE REMIT app functioning correctly after update. Market Participant Level |
|||
Other_0000000000000009127_004 | Inactive | 2024-06-04T01:02:31+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins. |
||||
Medway |
T_MEDP-1 |
Other_0000000000000009127_003 | Dismissed | 2024-06-03T16:49:21+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 720 mins. |
||
Other_0000000000000009127_003 | Inactive | 2024-06-04T01:02:31+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||||
Medway |
T_MEDP-1 |
Other_0000000000000009127_002 | Dismissed | 2024-06-03T08:32:07+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||
Medway |
T_MEDP-1 |
Other_0000000000000009127_002 | Dismissed | 2024-06-03T08:32:16+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity 2 + 1 SEL run. Dynamic data NDZ value will become 360 mins. |
||
Medway |
T_MEDP-1 |
Other_0000000000000009127_001 | Dismissed | 2024-05-31T09:03:01+01:00 | 2024-06-03T00:00:00+01:00 | 2024-06-03T23:59:00+01:00 | Asset integrity station on load run. Once out of merit run is complete our dynamic data NDZ value will become 360 mins. |
||
Other_0000000000000009139_003 | Inactive | 2024-06-07T13:02:32+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-07T12:00:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||||
Keadby |
T_KEAD-1 |
Other_0000000000000009139_002 | Dismissed | 2024-06-06T17:30:33+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-07T12:00:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009139_001 | Dismissed | 2024-06-04T15:45:42+01:00 | 2024-06-06T00:00:00+01:00 | 2024-06-06T23:59:00+01:00 | T_KEAD-1 2+1 run required for post outage commissioning works. |
||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000009175_003 | Active | 2024-09-27T08:57:17+01:00 | 2024-06-21T14:00:00+01:00 | 2025-06-30T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.300MW of installed capacity as at 26 September 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H2 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
48X0000000003113 | Other_0000000000000009175_002 | Dismissed | 2024-06-21T14:23:06+01:00 | 2024-06-21T14:00:00+01:00 | 2025-03-31T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.200MW of installed capacity as at 1 June 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Dogger Bank A |
48X0000000003113 | Other_0000000000000009175_001 | Dismissed | 2024-06-21T14:21:28+01:00 | 2024-06-21T14:00:00+01:00 | 2025-03-31T14:00:00+01:00 | Dogger Bank A is currently in the commissioning phase, with c.200MW of installed capacity as at 1 June 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available during H1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated. |
||
Other_0000000000000009202_002 | Inactive | 2024-07-03T19:02:32+01:00 | 2024-07-03T13:00:00+01:00 | 2024-07-03T18:00:00+01:00 | T_PEHE-1 running for post outage commissioning at circa 600MW. |
||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009202_001 | Dismissed | 2024-07-02T09:06:48+01:00 | 2024-07-03T13:00:00+01:00 | 2024-07-03T18:00:00+01:00 | T_PEHE-1 running for post outage commissioning at circa 600MW. |
||
Other_0000000000000009232_003 | Inactive | 2024-07-08T22:02:32+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-08T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||||
Peterhead |
T_PEHE-1 |
Other_0000000000000009232_002 | Dismissed | 2024-07-05T16:16:03+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-08T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009232_001 | Dismissed | 2024-07-05T14:44:07+01:00 | 2024-07-08T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_003 | Dismissed | 2024-07-08T21:43:03+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 370MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_002 | Dismissed | 2024-07-08T09:37:04+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 370MW. |
||
Peterhead |
T_PEHE-1 |
Other_0000000000000009233_001 | Dismissed | 2024-07-05T16:18:45+01:00 | 2024-07-09T08:00:00+01:00 | 2024-07-09T21:00:00+01:00 | T_PEHE-1 commissioning run at circa 1000MW. |
||
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000009241_002 | Inactive | 2024-07-15T19:02:32+01:00 | 2024-07-15T02:01:00+01:00 | 2024-07-15T18:00:00+01:00 | Post outage out of merit commission/testing run. |
||
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000009241_001 | Dismissed | 2024-07-12T10:10:34+01:00 | 2024-07-15T02:01:00+01:00 | 2024-07-15T18:00:00+01:00 | Post outage out of merit commission/testing run. |
||
Great Island |
Great Island |
Other_0000000000000009256_001 | Dismissed | 2024-07-18T16:02:07+01:00 | 2024-07-28T00:00:00+01:00 | 2024-07-29T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_002 | Dismissed | 2024-07-27T20:37:44+01:00 | 2024-07-29T00:00:00+01:00 | 2024-07-30T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009279_002 | Dismissed | 2024-07-29T14:20:34+01:00 | 2024-07-30T00:00:00+01:00 | 2026-05-01T00:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009279_001 | Dismissed | 2024-07-26T12:31:36+01:00 | 2024-07-30T00:00:00+01:00 | 2026-05-01T00:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009280_002 | Dismissed | 2024-07-29T14:19:57+01:00 | 2024-07-30T00:00:00+01:00 | 2026-05-01T00:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000009280_001 | Dismissed | 2024-07-26T12:31:39+01:00 | 2024-07-30T00:00:00+01:00 | 2026-05-01T00:00:00+01:00 | Great Island is available for running on secondary fuel in the event of a gas system emergency |
||
Other_0000000000000009256_008 | Inactive | 2024-08-01T04:02:32+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T03:00:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||||
Great Island |
Great Island |
Other_0000000000000009256_007 | Dismissed | 2024-07-31T21:10:48+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T03:00:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_006 | Dismissed | 2024-07-31T21:07:31+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T00:03:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_005 | Dismissed | 2024-07-30T15:59:06+01:00 | 2024-07-31T00:00:00+01:00 | 2024-07-31T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_003 | Dismissed | 2024-07-28T16:25:13+01:00 | 2024-07-31T00:00:00+01:00 | 2024-08-01T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009256_004 | Dismissed | 2024-07-29T14:03:08+01:00 | 2024-08-01T00:00:00+01:00 | 2024-08-01T23:59:00+01:00 | Unit will be completing testing within the range of 0-464MW following completion of centreline outage. |
||
Great Island |
Great Island |
Other_0000000000000009284_001 | Active | 2024-07-29T14:17:35+01:00 | 2024-08-02T00:00:00+01:00 | 2025-04-30T00:00:00+01:00 | Great Island is unavailable to run on oil due to plant fault. |
||
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000009354_003 | Inactive | 2024-09-13T01:02:32+01:00 | 2024-09-10T00:01:00+01:00 | 2024-09-12T23:59:00+01:00 | Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 11th and 12th of September 2024. |
||
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000009354_002 | Dismissed | 2024-09-09T09:01:48+01:00 | 2024-09-10T00:01:00+01:00 | 2024-09-12T23:59:00+01:00 | Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 11th and 12th of September 2024. |
||
MEDWAY POWER LTD |
48X000000000076O | Other_0000000000000009354_001 | Dismissed | 2024-08-23T14:04:31+01:00 | 2024-09-10T00:01:00+01:00 | 2024-09-12T23:59:00+01:00 | Medway will be required to run 2+1 to allow national gas to undertake pipeline inspections. This testing will take place between 09:00-18:00 on the 10th,11th and 12th of September 2024. |
||
Keadby |
T_KEAD-1 |
Other_0000000000000009350_002 | Dismissed | 2024-08-22T14:45:18+01:00 | 2024-09-22T00:00:00+01:00 | 2024-09-22T00:00:01+01:00 | This is a test publication following the automation of SSE REMIT admin app. |