This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

SSE Thermal Generation and Gas Storage REMIT information is no longer being updated on this page.
For SSE Thermal Generation and Gas Storage REMIT Information (Unavailability of Facilities and Other Market Information), please visit SSE Thermal REMIT.

Last update at: 2026-01-12T15:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status
Market Participant Market Participant Code Unit Location Unit Name Message ID Event Status Publication Date Event Start Event Stop Remarks
< 3 4 5 6 7 >
Other_0000000000000009256_008 Inactive 2024-08-01T04:02:32+00:00 2024-07-31T00:00:00+00:00 2024-08-01T03:00:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009256_007 Dismissed 2024-07-31T21:10:48+00:00 2024-07-31T00:00:00+00:00 2024-08-01T03:00:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009256_006 Dismissed 2024-07-31T21:07:31+00:00 2024-07-31T00:00:00+00:00 2024-08-01T00:03:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009256_005 Dismissed 2024-07-30T15:59:06+00:00 2024-07-31T00:00:00+00:00 2024-07-31T23:59:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009256_003 Dismissed 2024-07-28T16:25:13+00:00 2024-07-31T00:00:00+00:00 2024-08-01T23:59:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009256_004 Dismissed 2024-07-29T14:03:08+00:00 2024-08-01T00:00:00+00:00 2024-08-01T23:59:00+00:00
Unit will be completing testing within the range of 0-464MW following completion of centreline outage.
Other_0000000000000009284_007 Inactive 2025-06-10T04:02:32+00:00 2024-08-02T00:00:00+00:00 2025-06-10T03:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_006 Dismissed 2025-06-09T04:07:03+00:00 2024-08-02T00:00:00+00:00 2025-06-10T03:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_005 Dismissed 2025-06-09T01:48:55+00:00 2024-08-02T00:00:00+00:00 2025-06-10T09:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_004 Dismissed 2025-06-09T00:24:09+00:00 2024-08-02T00:00:00+00:00 2025-06-10T01:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_003 Dismissed 2025-05-31T12:59:58+00:00 2024-08-02T00:00:00+00:00 2025-06-09T23:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_002 Dismissed 2024-11-11T14:44:45+00:00 2024-08-02T00:00:00+00:00 2025-06-06T23:59:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009284_001 Dismissed 2024-07-29T14:17:35+00:00 2024-08-02T00:00:00+00:00 2025-04-30T00:00:00+00:00
Great Island is unavailable to run on oil due to plant fault.
Other_0000000000000009350_002 Dismissed 2024-08-22T14:45:18+00:00 2024-09-22T00:00:00+00:00 2024-09-22T00:00:01+00:00
This is a test publication following the automation of SSE REMIT admin app.
Other_0000000000000009350_001 Dismissed 2024-08-22T14:41:23+00:00 2024-09-22T00:00:00+00:00 2024-09-22T00:00:01+00:00
This is a test publication following the automation of SSE REMIT admin app.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000009473_002 Inactive 2025-07-31T11:02:32+00:00 2024-09-27T09:18:00+00:00 2025-07-31T10:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
Doggerbank Offshore Wind Farm Project 2 Projco Limited
48X0000000003121
Other_0000000000000009473_001 Dismissed 2024-09-27T09:23:00+00:00 2024-09-27T09:18:00+00:00 2025-07-31T10:00:00+00:00
It is expected that Dogger Bank B commissioning will start in H2 2025. It is expected that there will be a steady increase in installed capacity through to the total capacity of 1.2 GW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
Other_0000000000000009457_002 Dismissed 2024-09-23T16:12:25+00:00 2024-09-30T09:00:00+00:00 2024-10-13T18:00:00+00:00
T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 2 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours.
Other_0000000000000009457_001 Dismissed 2024-09-23T15:52:48+00:00 2024-09-30T09:00:00+00:00 2024-10-06T18:00:00+00:00
T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 2 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours.
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000009501_002 Dismissed 2024-10-03T14:43:04+00:00 2024-10-03T15:00:00+00:00 2024-10-03T15:03:00+00:00
This is a test submission to check connection to Elexon Insights
SSE Ferrybridge Battery Limited
48X000000000382H
Other_0000000000000009501_001 Dismissed 2024-10-03T14:42:19+00:00 2024-10-03T15:00:00+00:00 2024-10-03T15:03:00+00:00
This is a test submission to check connection to Elexon Insights
Other_0000000000000009457_004 Dismissed 2024-10-01T16:28:19+00:00 2024-10-07T09:00:00+00:00 2024-10-13T18:00:00+00:00
T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 1 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours.
Other_0000000000000009457_003 Dismissed 2024-09-25T09:07:21+00:00 2024-10-07T09:00:00+00:00 2024-10-13T18:00:00+00:00
T_PEHE-1, Upcoming pipeline pigging operations. Planned 4 runs over 1 week period with each run requiring 3+1 operation (circa 920 MW) for approximately 6 hours.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_003 Inactive 2024-11-28T18:02:32+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_002 Dismissed 2024-11-11T14:48:52+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in December 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009584_001 Dismissed 2024-10-31T09:34:29+00:00 2024-10-31T10:00:00+00:00 2024-11-28T17:00:00+00:00
It is expected that Yellow River commissioning will start in November 2024. It is expected that there will be a steady increase in installed capacity through to the total capacity of 101MW being available during Q1 2025. As relevant details of the commissioning plans become firmer REMIT will be updated.
Other_0000000000000009597_002 Dismissed 2024-11-27T11:23:57+00:00 2024-11-11T08:00:00+00:00 2024-12-06T17:00:00+00:00
Pipeline pigging opperations planned at T_PEHE-1 over period from 11/11/24 to 06/12/24. Anticipated 4 runs at circa 885MW for a duration of 6 hours per run.
Other_0000000000000009597_001 Dismissed 2024-11-04T11:15:46+00:00 2024-11-11T08:00:00+00:00 2024-12-06T17:00:00+00:00
Pipeline pigging opperations planned at T_PEHE-1 over period from 11/11/24 to 06/12/24. Anticipated 4 runs at circa 885MW for a duration of 6 hours per run.
Other_0000000000000009626_002 Inactive 2024-12-03T23:02:32+00:00 2024-12-03T07:00:00+00:00 2024-12-03T22:00:00+00:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 03/12/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
Other_0000000000000009626_001 Dismissed 2024-11-15T15:58:41+00:00 2024-12-03T07:00:00+00:00 2024-12-03T22:00:00+00:00
For the last shutdown that is within 15 hours prior to the start of the planned outage with a commencement time of 22:00hrs on 03/12/2024, a maintenance shutdown is required. This shutdown should commence from a turbine output of 205MW, have a reduced ramp rate and the expected duration until off load is approximately 3 hours.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_006 Inactive 2024-12-10T10:02:32+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_005 Dismissed 2024-12-05T18:24:43+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027
SSE GENERATION
48X000000000077M
Other_0000000000000009704_004 Dismissed 2024-12-05T18:23:19+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
TEST
SSE GENERATION
48X000000000077M
Other_0000000000000009704_003 Dismissed 2024-12-05T18:22:37+00:00 2024-12-05T18:15:00+00:00 2024-12-10T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start Q22027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_002 Dismissed 2024-12-05T18:14:15+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.
SSE GENERATION
48X000000000077M
Other_0000000000000009704_001 Dismissed 2024-12-05T18:12:34+00:00 2024-12-05T18:15:00+00:00 2025-06-05T09:00:00+00:00
It is expected that Strathy South Windfarm commissioning will start in Q2 2027. It is expected that there will be a steady increase in installed capacity through to the total capacity of 208MW being available. As relevant details of the commissioning plans become firmer REMIT will be updated.”
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009709_002 Inactive 2024-12-13T01:02:32+00:00 2024-12-06T12:55:00+00:00 2024-12-13T00:00:00+00:00
Yellow River Wind Farm is energised and will start generation upto 15MW from December 10th 2024.
SSE Airtricity Limited
23X--140207ALT-9
Other_0000000000000009709_001 Dismissed 2024-12-06T12:56:23+00:00 2024-12-06T12:55:00+00:00 2024-12-13T00:00:00+00:00
Yellow River Wind Farm is energised and will start generation upto 15MW from December 10th 2024.
Other_0000000000000009640_003 Inactive 2024-12-10T01:02:32+00:00 2024-12-09T04:00:00+00:00 2024-12-10T00:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009640_002 Dismissed 2024-12-09T09:43:13+00:00 2024-12-09T04:00:00+00:00 2024-12-10T00:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009640_001 Dismissed 2024-11-21T17:10:54+00:00 2024-12-09T04:00:00+00:00 2024-12-09T23:00:00+00:00
Unit will be completing testing within the range of 165-464 following completion of STMO.
Other_0000000000000009790_002 Dismissed 2025-01-09T08:28:08+00:00 2025-01-09T00:00:00+00:00 2025-01-09T23:59:59+00:00
For commissioning and gas turbine tuning purposes Keadby 2 will be operating at reduced loads for periods of time. These periods will be visible via MEL & REMIT declarations.
Other_0000000000000009790_001 Dismissed 2025-01-07T19:29:36+00:00 2025-01-09T00:00:00+00:00 2025-01-09T23:59:59+00:00
For commissioning and gas turbine tuning purposes Keadby 2 will be operating at reduced loads for periods of time. These periods will be visible via MEL & REMIT declarations.
Other_0000000000000009755_002 Dismissed 2025-01-07T09:06:15+00:00 2025-01-10T00:00:06+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 10th, 11th & 12th Jan '25.
Other_0000000000000009755_001 Dismissed 2024-12-23T10:32:20+00:00 2025-01-10T00:00:06+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate at MEL in 1+1 configuration for a minimum of 2hrs commencing 4pm on the 10th, 11th & 12th Jan '25.
Other_0000000000000009755_004 Dismissed 2025-01-10T13:31:15+00:00 2025-01-11T00:00:00+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 11th & 12th Jan '25.
Other_0000000000000009755_003 Dismissed 2025-01-08T13:00:54+00:00 2025-01-11T00:00:00+00:00 2025-01-12T23:59:25+00:00
To facilitate National Gas Transmission statutory gas pipeline inspection works, KEAD_1 is forced to operate without commercial consideration for periods of time on the 11th & 12th Jan '25.
Other_0000000000000009850_013 Inactive 2025-03-31T17:02:32+00:00 2025-01-27T09:25:54+00:00 2025-03-31T16:00:00+00:00
#Commissioning# Current capacity 86MW. Commissioning is scheduled to conclude early Q2 2025.
Yellow River
Yellow River
Other_0000000000000009850_012 Dismissed 2025-03-18T12:05:48+00:00 2025-01-27T09:25:54+00:00 2025-03-31T16:00:00+00:00
#Commissioning# Current capacity 86MW. Commissioning is scheduled to conclude early Q2 2025.
Yellow River
Yellow River
Other_0000000000000009850_011 Dismissed 2025-03-18T12:03:28+00:00 2025-01-27T09:25:54+00:00 2025-03-31T16:00:00+00:00
#Commissioning# Current capacity 86MW. Commissioning is scheduled to conclude late Q2 2025.