Last update at: 2023-09-26T16:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Market Participant | Market Participant Code | Message ID | Event Status | Publication Date | Event Start | Event Stop | Remarks |
---|---|---|---|---|---|---|---|
< 1 2 3 4 > | |||||||
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T11:46:45+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
KEADBY GEN. LTD |
48X000000000073U | Other_0000000000000007752_001 | Dismissed | 2022-12-01T12:12:07+00:00 | 2022-12-01T12:15:00+00:00 | 2022-12-01T12:16:00+00:00 | **Please ignore this Message** This is a test of auto transfer from SSE REMIT to NG / Elexon following SSE REMIT File Mover update.
|
Other_0000000000000007814_002 | Inactive | 2023-07-06T01:02:32+01:00 | 2022-12-22T17:39:00+00:00 | 2023-07-06T00:00:00+01:00 | Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023 |
||
Other_0000000000000007814_001 | Dismissed | 2022-12-22T17:45:01+00:00 | 2022-12-22T17:39:00+00:00 | 2023-07-06T00:00:00+01:00 | Due to a failed Auxiliary transformer at Medway the capability for onload transition from 1 GT and 1 Steam Turbine (1+1) to 2 GT’s and 1 Steam turbine is no longer possible. It is expected this situation will be resolved during the summer outage in 2023 |
||
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008119_001 | Active | 2023-05-10T08:46:36+01:00 | 2023-05-10T08:43:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_003 | Active | 2023-08-04T18:05:35+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update of Feb 23, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation. SSE has agreed a PWA for this project with expected delivery Sept 24. GE is the instructed contractor for the works at site. Further contracts to facilitate the project continue to be negotiated. As of Apr 23, the TSO has confirmed that this unit will operate outside the wholesale market |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_002 | Dismissed | 2023-08-04T17:37:40+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE has agreed a preliminary works contract for this project with expected delivery Sept 24 GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008121_001 | Dismissed | 2023-05-10T08:49:10+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008120_001 | Active | 2023-05-10T08:47:39+01:00 | 2023-05-10T08:47:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023, Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply. SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_002 | Active | 2023-08-04T17:30:10+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE has agreed a preliminary works contract for this project with expected delivery September, 24. GE as the instructed contractor will complete works at site. Further contracts needed to facilitate this project continue to be negotiated. |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008122_001 | Dismissed | 2023-05-10T08:50:25+01:00 | 2023-05-10T08:49:00+01:00 | As outlined in the CRU Security of Supply update published in February 2023 Tarbert is a designated site for the installation of up to 160MW of temporary emergency generation to support security of supply SSE have now agreed a preliminary works contract for this project to allow it to progress to targeted delivery GE as the instructed contractor will complete works at site Further contracts needed to facilitate this project continue to be negotiated |
|
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_002 | Dismissed | 2023-07-19T13:26:01+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
Dogger Bank A |
48X0000000003113 | Other_0000000000000008140_001 | Dismissed | 2023-05-18T14:01:15+01:00 | 2023-05-18T14:01:00+01:00 | 2023-07-23T00:00:00+01:00 | It is anticipated that Dogger Bank A commissioning period will start on 23rd July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c200MW available by the end of Q3 2023, c500MW by the end of Q4 2023, c700MW by the end of Q1 2024, 950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated |
Other_0000000000000008203_003 | Active | 2023-07-27T12:34:51+01:00 | 2023-06-19T10:07:00+01:00 | 2024-05-17T22:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Other_0000000000000008203_002 | Dismissed | 2023-06-19T10:34:59+01:00 | 2023-06-19T10:07:00+01:00 | 2023-07-28T10:00:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
||
Other_0000000000000008203_001 | Dismissed | 2023-06-19T10:13:07+01:00 | 2023-06-19T10:07:00+01:00 | Due to plant fault, unit is not available to run on distillate oil. Gas running is not affected |
|||
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_025 | Active | 2023-09-26T15:41:57+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_024 | Dismissed | 2023-09-25T17:45:52+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-27T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 27th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_023 | Dismissed | 2023-09-23T12:53:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-26T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 26th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_022 | Dismissed | 2023-09-22T17:41:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T19:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_021 | Dismissed | 2023-09-19T18:32:22+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-23T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 23rd Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_020 | Dismissed | 2023-09-18T17:45:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-20T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 20th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.25MW available by the end of Q3 2023, c.300MW by the end of Q4 2023, c.575MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_019 | Dismissed | 2023-09-17T18:18:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-19T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 19th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_018 | Dismissed | 2023-09-14T21:28:32+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-18T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 18th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_017 | Dismissed | 2023-09-12T08:50:34+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:45:43+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-15T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 15th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_016 | Dismissed | 2023-09-12T08:48:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:05+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_015 | Dismissed | 2023-09-06T11:35:14+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.75MW available by the end of Q3 2023, c.350MW by the end of Q4 2023, c.625MW by the end of Q1 2024, c.975MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_014 | Dismissed | 2023-09-05T17:41:03+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-13T07:00:00+01:00 | It is anticipated that Dogger Bank A commissioning will start on 13th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_013 | Dismissed | 2023-08-30T16:05:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-09-06T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 6th Sept 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_012 | Dismissed | 2023-08-25T21:32:06+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.125MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_011 | Dismissed | 2023-08-25T10:13:08+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-31T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 31st Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_010 | Dismissed | 2023-08-22T11:18:09+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_009 | Dismissed | 2023-08-18T09:18:00+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-23T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 23rd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_008 | Dismissed | 2023-08-14T14:39:29+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-20T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 20th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_007 | Dismissed | 2023-08-09T17:31:28+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-15T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 15th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_006 | Dismissed | 2023-08-04T15:49:36+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-11T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 11th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.900MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_005 | Dismissed | 2023-08-01T14:41:23+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-07T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_004 | Dismissed | 2023-07-28T16:16:25+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.150MW available by the end of Q3 2023, c.400MW by the end of Q4 2023, c.600MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_003 | Dismissed | 2023-07-28T16:14:41+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 7th Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_002 | Dismissed | 2023-07-24T13:53:38+01:00 | 2023-07-18T13:30:00+01:00 | 2023-08-02T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 2nd Aug 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | Other_0000000000000008251_001 | Dismissed | 2023-07-18T13:28:20+01:00 | 2023-07-18T13:30:00+01:00 | 2023-07-28T07:00:00+01:00 | It is anticipated that DoggerBank A commissioning will start on 28th July 2023 and full commercial operation will commence during Q3 of 2024. It is expected that there will be a steady increase in installed capacity with c.200MW available by the end of Q3 2023, c.450MW by the end of Q4 2023, c.650MW by the end of Q1 2024, c.950MW by the end of Q2 2024 and the total capacity of 1.2GW available during Q3 2024. As relevant details of the commissioning plans become firmer REMIT will be updated. |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_004 | Dismissed | 2023-08-09T14:21:16+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_003 | Dismissed | 2023-08-09T14:15:15+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_002 | Dismissed | 2023-08-09T14:14:24+01:00 | 2023-08-09T14:09:00+01:00 | 2023-08-10T14:14:00+01:00 | This is a test message |
SSE Generation Ireland Ltd |
47X0000000000592 | Other_0000000000000008299_001 | Dismissed | 2023-08-09T14:11:02+01:00 | 2023-08-09T14:09:00+01:00 | This is a test message |
|
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_002 | Dismissed | 2023-09-07T17:00:31+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
Seagreen Wind Energy Ltd |
48X000000000263P | Other_0000000000000008388_001 | Dismissed | 2023-09-06T16:25:23+01:00 | 2023-09-07T14:00:00+01:00 | 2023-09-07T17:00:00+01:00 | SWEL will be carrying out SCADA commissioning / testing on the 07 September 2023 between 1400hrs and 1700hrs. The MW output of the BMU3, 4, 5 and 6 will vary between 0MW and maximum available during this period. |
Other_0000000000000008420_002 | Dismissed | 2023-09-18T12:19:36+01:00 | 2023-09-19T10:00:00+01:00 | 2023-09-19T19:00:00+01:00 | Operating at circa 300MW for statutory testing. |