Last update at: 2023-01-30T09:00:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | ||||||||||||||||||
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007720_002 | Dismissed | Planned | Production unavailability | 2022-11-11T17:16:00+00:00 | 2022-11-14T12:00:00+00:00 | 2023-05-10T11:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007720_001 | Dismissed | Planned | Production unavailability | 2022-11-09T17:10:34+00:00 | 2022-11-14T18:00:00+00:00 | 2023-05-10T11:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007737_001 | Dismissed | Unplanned | Production unavailability | 2022-11-19T17:01:17+00:00 | 2022-11-19T16:55:00+00:00 | 2022-11-19T20:00:00+00:00 | MW | 0 | 464 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007734_002 | Dismissed | Planned | Production unavailability | 2022-11-16T16:58:09+00:00 | 2027-11-16T16:45:00+00:00 | 2027-11-16T16:46:00+00:00 | MW | 0 | 1180 | 1180 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000007734_001 | Dismissed | Planned | Production unavailability | 2022-11-16T16:45:34+00:00 | 2027-11-16T16:45:00+00:00 | 2027-11-16T16:46:00+00:00 | MW | 0 | 1180 | 1180 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007652_001 | Dismissed | Planned | Production unavailability | 2022-10-18T12:20:27+01:00 | 2023-01-09T06:00:00+00:00 | 2023-01-13T12:00:00+00:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000007723_001 | Dismissed | Planned | Production unavailability | 2022-11-10T14:01:26+00:00 | 2022-11-10T14:15:00+00:00 | 2022-11-10T14:45:00+00:00 | MW | 0 | 129 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007708_002 | Inactive | Unplanned | Production unavailability | 2022-11-04T17:47:33+00:00 | 2022-11-04T15:59:00+00:00 | 2022-11-04T16:45:00+00:00 | MW | 0 | 241 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007708_001 | Dismissed | Unplanned | Production unavailability | 2022-11-04T15:59:39+00:00 | 2022-11-04T15:59:00+00:00 | 2022-11-04T16:45:00+00:00 | MW | 0 | 241 | 241 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_003 | Inactive | Planned | Consumption unavailability | 2022-10-16T18:47:33+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_003 | Inactive | Planned | Consumption unavailability | 2022-10-16T18:47:33+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_002 | Dismissed | Planned | Consumption unavailability | 2022-10-16T17:32:13+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_002 | Dismissed | Planned | Consumption unavailability | 2022-10-16T17:31:46+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T17:35:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007650_001 | Dismissed | Planned | Consumption unavailability | 2022-10-16T11:14:23+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T20:30:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007651_001 | Dismissed | Planned | Consumption unavailability | 2022-10-16T11:16:38+01:00 | 2022-10-16T12:00:00+01:00 | 2022-10-16T20:30:00+01:00 | MW | 0 | 150 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007613_002 | Inactive | Planned | Production unavailability | 2022-10-15T13:02:35+01:00 | 2022-10-14T06:00:00+01:00 | 2022-10-15T12:00:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007613_001 | Dismissed | Planned | Production unavailability | 2022-09-20T14:35:12+01:00 | 2022-10-14T06:00:00+01:00 | 2022-10-15T12:00:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
Cloosh | 47W0000000003918 | CLOOSH VALLEY WIND FARM DESIGNATED ACTIVITY COMPANY |
47X0000000002099 | 0000000000000000000007649_001 | Dismissed | Unplanned | Production unavailability | 2022-10-15T10:32:45+01:00 | 2022-10-15T09:47:00+01:00 | 2022-10-15T11:47:00+01:00 | MW | 0 | 105 | 105 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007625_002 | Inactive | Planned | Production unavailability | 2022-09-29T08:52:35+01:00 | 2022-09-29T08:00:00+01:00 | 2022-09-29T08:10:00+01:00 | MW | 0 | 102 | 102 | Shutdown | Grid |
Wind Onshore | 10YGB----------A |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007625_001 | Dismissed | Planned | Production unavailability | 2022-09-29T08:51:32+01:00 | 2022-09-29T08:00:00+01:00 | 2022-09-29T10:00:00+01:00 | MW | 0 | 102 | 102 | Shutdown | Grid |
Wind Onshore | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007542_003 | Inactive | Planned | Production unavailability | 2022-08-29T00:01:53+01:00 | 2022-08-28T08:00:00+01:00 | 2022-08-28T23:00:00+01:00 | MW | 0 | 464 | 464 | Foreseen Maintenance | Testing |
Fossil Oil | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007542_002 | Dismissed | Planned | Production unavailability | 2022-08-28T17:45:08+01:00 | 2022-08-28T08:00:00+01:00 | 2022-08-28T23:00:00+01:00 | MW | 0 | 464 | 464 | Foreseen Maintenance | Testing |
Fossil Oil | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007542_001 | Dismissed | Planned | Production unavailability | 2022-08-27T10:13:12+01:00 | 2022-08-28T08:00:00+01:00 | 2022-08-28T21:30:00+01:00 | MW | 0 | 464 | 464 | Foreseen Maintenance | Testing |
Fossil Oil | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005534_001 | Dismissed | Planned | Production unavailability | 2021-02-12T14:55:00+00:00 | 2025-11-01T00:00:00+00:00 | 2025-11-29T00:00:00+00:00 | MW | 0 | 464 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007477_002 | Dismissed | Planned | Production unavailability | 2022-08-04T16:15:09+01:00 | 2026-08-04T15:30:00+01:00 | 2026-08-04T15:31:00+01:00 | MW | 0 | 358 | 358 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000007477_001 | Dismissed | Planned | Production unavailability | 2022-08-04T15:31:31+01:00 | 2026-08-04T15:30:00+01:00 | 2026-08-04T15:31:00+01:00 | MW | 0 | 358 | 358 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007471_002 | Dismissed | Planned | Production unavailability | 2022-08-02T16:48:44+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007471_001 | Dismissed | Planned | Production unavailability | 2022-07-29T09:24:23+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-2 | 48W00000GRIFW-2Y | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007472_002 | Dismissed | Planned | Production unavailability | 2022-08-02T16:47:57+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-2 | 48W00000GRIFW-2Y | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007472_001 | Dismissed | Planned | Production unavailability | 2022-07-29T09:26:13+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-2 | 48W00000GRIFW-2Y | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007467_002 | Dismissed | Planned | Production unavailability | 2022-07-25T16:25:51+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-2 | 48W00000GRIFW-2Y | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007467_001 | Dismissed | Planned | Production unavailability | 2022-07-25T14:40:26+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007466_002 | Dismissed | Planned | Production unavailability | 2022-07-25T16:25:31+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_GRIFW-1 | 48W10000GRIFW-1N | GRIFFIN WIND FARM |
48X000000000072W | 0000000000000000000007466_001 | Dismissed | Planned | Production unavailability | 2022-07-25T14:38:43+01:00 | 2025-01-01T00:00:00+00:00 | 2025-01-01T00:01:00+00:00 | MW | 0 | 102 | 102 | Foreseen Maintenance | Testing |
Wind Onshore | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007461_001 | Dismissed | Unplanned | Consumption unavailability | 2022-07-22T15:27:41+01:00 | 2022-07-22T15:24:00+01:00 | 2022-07-22T17:30:00+01:00 | MW | 0 | 150 | 150 | Failure | Plant Fault - Control System |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000007460_001 | Dismissed | Unplanned | Production unavailability | 2022-07-22T15:25:58+01:00 | 2022-07-22T15:24:00+01:00 | 2022-07-22T17:30:00+01:00 | MW | 0 | 150 | 150 | Failure | Plant Fault - Control System |
Hydro Pumped Storage | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007362_002 | Dismissed | Planned | Production unavailability | 2022-07-04T17:34:10+01:00 | 2022-07-06T10:00:00+01:00 | 2022-07-06T11:30:00+01:00 | MW | 0 | 893 | 893 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007362_001 | Dismissed | Planned | Production unavailability | 2022-07-04T16:40:10+01:00 | 2022-07-06T10:00:00+01:00 | 2022-07-06T11:30:00+01:00 | MW | 0 | 893 | 893 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007160_001 | Dismissed | Planned | Production unavailability | 2022-06-06T20:01:30+01:00 | 2022-06-07T10:00:00+01:00 | 2022-06-07T10:30:00+01:00 | MW | 0 | 893 | 893 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007108_003 | Dismissed | Planned | Production unavailability | 2022-05-26T14:56:27+01:00 | 2022-05-26T16:00:00+01:00 | 2022-05-26T18:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007108_002 | Dismissed | Planned | Production unavailability | 2022-05-26T09:35:07+01:00 | 2022-05-26T16:00:00+01:00 | 2022-05-26T18:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007065_001 | Dismissed | Planned | Production unavailability | 2022-05-17T10:40:23+01:00 | 2022-05-19T05:30:00+01:00 | 2022-05-19T09:30:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007037_002 | Dismissed | Planned | Production unavailability | 2022-05-12T07:21:33+01:00 | 2022-05-11T20:42:00+01:00 | 2022-05-12T10:10:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007037_001 | Dismissed | Planned | Production unavailability | 2022-05-11T17:13:59+01:00 | 2022-05-11T20:42:00+01:00 | 2022-05-12T10:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007032_002 | Dismissed | Planned | Production unavailability | 2022-05-11T09:53:48+01:00 | 2022-05-13T11:00:00+01:00 | 2022-05-13T17:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007032_001 | Dismissed | Planned | Production unavailability | 2022-05-11T09:37:57+01:00 | 2022-05-13T11:00:00+01:00 | 2022-05-13T17:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007029_002 | Dismissed | Planned | Production unavailability | 2022-05-11T09:53:30+01:00 | 2022-05-12T10:00:00+01:00 | 2022-05-12T20:30:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000007029_001 | Dismissed | Planned | Production unavailability | 2022-05-11T09:31:58+01:00 | 2022-05-12T10:00:00+01:00 | 2022-05-12T20:30:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006934_001 | Dismissed | Planned | Production unavailability | 2022-04-22T16:28:21+01:00 | 2022-05-12T09:30:00+01:00 | 2022-05-12T11:30:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006932_001 | Dismissed | Planned | Production unavailability | 2022-04-22T16:19:47+01:00 | 2022-05-11T19:00:00+01:00 | 2022-05-12T04:00:00+01:00 | MW | 0 | 867 | 867 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |