Last update at: 2023-03-23T13:30:00+00:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 5 6 7 8 9 >
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007929_005 Dismissed Planned Production unavailability 2023-02-02T02:38:03+00:00 2023-02-02T09:00:00+00:00 2023-02-03T05:59:00+00:00 MW 168 190 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007929_004 Dismissed Planned Production unavailability 2023-02-02T02:31:44+00:00 2023-02-02T03:30:00+00:00 2023-02-03T05:59:00+00:00 MW 168 190 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007929_003 Dismissed Planned Production unavailability 2023-01-31T10:01:46+00:00 2023-02-02T12:00:00+00:00 2023-02-03T05:59:00+00:00 MW 168 190 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007929_002 Dismissed Planned Production unavailability 2023-01-31T05:40:15+00:00 2023-01-31T12:00:00+00:00 2023-02-03T05:59:00+00:00 MW 168 190 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007929_001 Dismissed Planned Production unavailability 2023-01-30T12:33:13+00:00 2023-01-31T06:00:00+00:00 2023-02-03T05:59:00+00:00 MW 168 190 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_029 Inactive Planned Production unavailability 2023-02-02T10:02:32+00:00 2022-11-28T08:01:00+00:00 2023-02-02T08:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_028 Dismissed Planned Production unavailability 2023-02-02T02:38:30+00:00 2022-11-28T08:01:00+00:00 2023-02-02T08:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_027 Dismissed Planned Production unavailability 2023-02-02T02:32:08+00:00 2022-11-28T08:01:00+00:00 2023-02-02T03:29:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_026 Dismissed Planned Production unavailability 2023-01-31T12:46:40+00:00 2022-11-28T08:01:00+00:00 2023-02-02T11:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_025 Dismissed Planned Production unavailability 2023-01-31T05:39:49+00:00 2022-11-28T08:01:00+00:00 2023-01-31T11:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_024 Dismissed Planned Production unavailability 2023-01-30T12:31:37+00:00 2022-11-28T08:01:00+00:00 2023-01-31T05:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_023 Dismissed Planned Production unavailability 2023-01-29T11:05:55+00:00 2022-11-28T08:01:00+00:00 2023-02-01T17:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_022 Dismissed Planned Production unavailability 2023-01-28T13:27:44+00:00 2022-11-28T08:01:00+00:00 2023-01-29T17:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_021 Dismissed Planned Production unavailability 2023-01-26T13:13:38+00:00 2022-11-28T08:01:00+00:00 2023-01-28T17:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_020 Dismissed Planned Production unavailability 2023-01-19T15:43:21+00:00 2022-11-28T08:01:00+00:00 2023-01-27T05:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_019 Dismissed Planned Production unavailability 2023-01-12T11:37:50+00:00 2022-11-28T08:01:00+00:00 2023-01-20T05:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_018 Dismissed Planned Production unavailability 2023-01-11T17:12:29+00:00 2022-11-28T08:01:00+00:00 2023-01-20T07:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_017 Dismissed Planned Production unavailability 2023-01-11T17:11:13+00:00 2022-11-28T08:01:00+00:00 2023-01-20T00:00:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_016 Dismissed Planned Production unavailability 2023-01-04T16:14:28+00:00 2022-11-28T08:01:00+00:00 2023-01-12T08:00:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_015 Dismissed Planned Production unavailability 2023-01-02T07:31:57+00:00 2022-11-28T08:01:00+00:00 2023-01-05T08:00:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_014 Dismissed Planned Production unavailability 2022-12-29T08:47:33+00:00 2022-11-28T08:01:00+00:00 2023-01-02T08:00:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_013 Dismissed Planned Production unavailability 2022-12-23T00:57:48+00:00 2022-11-28T08:01:00+00:00 2022-12-30T05:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_012 Dismissed Planned Production unavailability 2022-12-21T13:36:20+00:00 2022-11-28T08:01:00+00:00 2022-12-23T05:59:00+00:00 MW 248 110 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_011 Dismissed Planned Production unavailability 2022-12-14T15:43:19+00:00 2022-12-21T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 138 220 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_010 Dismissed Planned Production unavailability 2022-12-05T16:28:54+00:00 2022-12-12T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 118 240 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_009 Dismissed Planned Production unavailability 2022-11-29T14:26:55+00:00 2022-12-06T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 118 240 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_008 Dismissed Planned Production unavailability 2022-11-18T15:12:32+00:00 2022-12-03T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 118 240 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_007 Dismissed Planned Production unavailability 2022-11-14T17:00:29+00:00 2022-11-29T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 118 240 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_006 Dismissed Planned Production unavailability 2022-11-09T17:05:11+00:00 2022-11-21T06:00:00+00:00 2023-02-06T05:59:00+00:00 MW 118 240 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_005 Dismissed Planned Production unavailability 2022-11-04T13:13:01+00:00 2023-03-14T12:00:00+00:00 2023-05-10T11:59:00+01:00 MW 0 358 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_004 Dismissed Planned Production unavailability 2022-10-17T17:28:10+01:00 2023-01-16T06:00:00+00:00 2023-05-01T11:59:00+01:00 MW 0 358 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_003 Dismissed Planned Production unavailability 2022-09-20T12:16:29+01:00 2022-11-07T12:00:00+00:00 2022-11-11T11:59:00+00:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_002 Dismissed Planned Production unavailability 2022-08-17T10:38:49+01:00 2022-11-07T12:00:00+00:00 2022-11-11T11:59:00+00:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000007484_001 Dismissed Planned Production unavailability 2022-08-05T18:00:30+01:00 2022-11-07T12:00:00+00:00 2023-03-07T11:59:00+00:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007820_003 Dismissed Planned Production unavailability 2023-01-30T14:35:15+00:00 2023-02-02T06:00:00+00:00 2023-02-02T12:00:00+00:00 MW 362 531 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007820_002 Dismissed Planned Production unavailability 2023-01-18T12:14:01+00:00 2023-02-02T06:00:00+00:00 2023-02-02T12:00:00+00:00 MW 362 531 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007820_001 Dismissed Planned Production unavailability 2022-12-29T17:10:00+00:00 2023-02-04T06:00:00+00:00 2023-02-04T12:00:00+00:00 MW 362 531 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007826_003 Dismissed Planned Production unavailability 2023-01-30T14:34:07+00:00 2023-02-13T08:30:00+00:00 2023-02-14T00:00:00+00:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007826_002 Dismissed Planned Production unavailability 2023-01-18T12:17:23+00:00 2023-02-13T08:30:00+00:00 2023-02-14T00:00:00+00:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007826_001 Dismissed Planned Production unavailability 2023-01-03T13:28:36+00:00 2023-02-15T08:30:00+00:00 2023-02-16T00:00:00+00:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007800_004 Dismissed Planned Production unavailability 2023-01-27T20:49:16+00:00 2023-01-30T10:00:00+00:00 2023-01-30T19:00:00+00:00 MW 243 650 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007800_003 Dismissed Planned Production unavailability 2023-01-18T12:03:58+00:00 2023-01-30T10:00:00+00:00 2023-01-30T19:00:00+00:00 MW 243 650 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007800_002 Dismissed Planned Production unavailability 2022-12-29T17:07:05+00:00 2023-02-01T10:00:00+00:00 2023-02-01T19:00:00+00:00 MW 243 650 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007800_001 Dismissed Planned Production unavailability 2022-12-19T17:41:26+00:00 2023-02-11T08:30:00+00:00 2023-02-12T23:59:00+00:00 MW 893 0 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007925_002 Dismissed Planned Production unavailability 2023-01-27T17:44:54+00:00 2023-01-28T21:00:00+00:00 2023-01-28T22:30:00+00:00 MW 408 485 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007925_001 Dismissed Planned Production unavailability 2023-01-26T18:31:12+00:00 2023-01-28T21:00:00+00:00 2023-01-28T22:30:00+00:00 MW 408 485 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007924_002 Dismissed Planned Production unavailability 2023-01-27T17:44:33+00:00 2023-01-28T19:00:00+00:00 2023-01-28T21:00:00+00:00 MW 526 367 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007924_001 Dismissed Planned Production unavailability 2023-01-26T18:29:24+00:00 2023-01-28T19:00:00+00:00 2023-01-28T21:00:00+00:00 MW 526 367 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007923_002 Dismissed Planned Production unavailability 2023-01-27T17:44:08+00:00 2023-01-28T16:00:00+00:00 2023-01-28T18:00:00+00:00 MW 366 527 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007923_001 Dismissed Planned Production unavailability 2023-01-26T18:27:52+00:00 2023-01-28T16:00:00+00:00 2023-01-28T18:00:00+00:00 MW 366 527 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A