This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2023-09-25T01:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 4 5 6 7 8 >
T_SGRWO-4 48W00000SGRWO-4F
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008257_001 Dismissed Planned Production unavailability 2023-07-19T17:42:22+01:00 2023-07-28T17:01:00+01:00 2023-08-05T12:00:00+01:00 MW 30 110 140 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_017 Active Planned Production unavailability 2023-07-19T17:39:26+01:00 2023-06-03T14:26:00+01:00 2023-09-29T12:00:00+01:00 MW 300 0 300 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_016 Dismissed Planned Production unavailability 2023-06-23T17:20:51+01:00 2023-06-03T14:26:00+01:00 2023-08-07T12:00:00+01:00 MW 300 0 300 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_015 Dismissed Planned Production unavailability 2023-06-10T02:58:24+01:00 2023-06-03T14:26:00+01:00 2023-07-07T12:00:00+01:00 MW 300 0 300 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_014 Dismissed Planned Production unavailability 2023-06-09T15:32:19+01:00 2023-06-03T14:00:00+01:00 2023-07-07T12:00:00+01:00 MW 300 0 300 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_013 Dismissed Planned Production unavailability 2023-06-03T14:22:21+01:00 2023-06-03T14:00:00+01:00 2023-06-16T05:59:00+01:00 MW 300 0 300 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_012 Dismissed Planned Production unavailability 2023-06-03T14:15:37+01:00 2023-06-03T14:00:00+01:00 2023-06-16T05:59:00+01:00 MW 300 0 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_011 Dismissed Planned Production unavailability 2023-05-26T09:13:37+01:00 2023-05-26T12:30:00+01:00 2023-06-16T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_010 Dismissed Planned Production unavailability 2023-05-24T11:32:12+01:00 2023-05-28T13:00:00+01:00 2023-06-16T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_009 Dismissed Planned Production unavailability 2023-05-24T10:03:14+01:00 2023-06-04T00:00:00+01:00 2023-06-16T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_008 Dismissed Planned Production unavailability 2023-05-22T17:49:42+01:00 2023-05-25T13:00:00+01:00 2023-06-06T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_007 Dismissed Planned Production unavailability 2023-05-19T17:14:47+01:00 2023-05-23T13:00:00+01:00 2023-06-06T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_006 Dismissed Planned Production unavailability 2023-05-16T13:29:32+01:00 2023-05-23T14:00:00+01:00 2023-06-06T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_005 Dismissed Planned Production unavailability 2023-04-22T12:05:33+01:00 2023-04-23T12:01:00+01:00 2023-06-06T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_004 Dismissed Planned Production unavailability 2023-04-19T11:50:16+01:00 2023-04-23T14:01:00+01:00 2023-06-06T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_003 Dismissed Planned Production unavailability 2023-04-13T17:36:27+01:00 2023-04-23T14:01:00+01:00 2023-05-11T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-1 48W00000SGRWO-1L
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008067_002 Dismissed Planned Production unavailability 2023-04-05T16:27:14+01:00 2023-04-23T16:01:00+01:00 2023-05-11T05:59:00+01:00 MW 220 80 300 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-2 48W00000SGRWO-2J
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008168_004 Active Planned Production unavailability 2023-07-19T17:39:02+01:00 2023-06-03T14:26:00+01:00 2023-09-29T12:00:00+01:00 MW 80 0 80 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-2 48W00000SGRWO-2J
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008168_003 Dismissed Planned Production unavailability 2023-06-23T17:21:18+01:00 2023-06-03T14:26:00+01:00 2023-08-07T12:00:00+01:00 MW 80 0 80 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-2 48W00000SGRWO-2J
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008168_002 Dismissed Planned Production unavailability 2023-06-09T15:37:41+01:00 2023-06-03T14:26:00+01:00 2023-07-07T12:00:00+01:00 MW 80 0 80 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-2 48W00000SGRWO-2J
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008168_001 Dismissed Planned Production unavailability 2023-06-03T14:18:18+01:00 2023-06-03T14:00:00+01:00 2023-06-16T05:59:00+01:00 MW 80 0 80 Failure
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_009 Dismissed Planned Production unavailability 2023-07-17T09:47:44+01:00 2023-07-20T23:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_008 Dismissed Planned Production unavailability 2023-07-17T09:00:40+01:00 2023-07-20T23:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_007 Dismissed Planned Production unavailability 2023-07-13T17:02:54+01:00 2023-07-17T23:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_006 Dismissed Planned Production unavailability 2023-07-13T08:50:04+01:00 2023-07-14T23:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_005 Dismissed Planned Production unavailability 2023-07-12T08:58:34+01:00 2023-07-13T23:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_004 Dismissed Planned Production unavailability 2023-07-11T08:12:23+01:00 2023-07-12T12:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_003 Dismissed Planned Production unavailability 2023-07-10T08:46:54+01:00 2023-07-11T12:01:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_002 Dismissed Planned Production unavailability 2023-07-07T18:39:14+01:00 2023-07-10T15:00:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-6 48W00000SGRWO-6B
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008207_001 Dismissed Planned Production unavailability 2023-06-23T19:42:37+01:00 2023-06-03T14:26:00+01:00 2023-07-21T12:00:00+01:00 MW 28 330 358 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008237_002 Inactive Unplanned Production unavailability 2023-07-09T01:02:32+01:00 2023-07-08T01:00:00+01:00 2023-07-08T23:59:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008237_001 Dismissed Unplanned Production unavailability 2023-07-08T01:02:56+01:00 2023-07-08T01:00:00+01:00 2023-07-08T23:59:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008236_003 Dismissed Unplanned Production unavailability 2023-07-08T01:04:54+01:00 2023-07-07T20:12:00+01:00 2023-07-08T04:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008236_002 Dismissed Unplanned Production unavailability 2023-07-07T20:22:08+01:00 2023-07-07T20:12:00+01:00 2023-07-08T04:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008236_001 Dismissed Unplanned Production unavailability 2023-07-07T20:15:52+01:00 2023-07-07T20:12:00+01:00 2023-07-08T04:00:00+01:00 MW 710 0 710 Failure
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008231_003 Inactive Planned Production unavailability 2023-07-07T21:02:31+01:00 2023-07-07T14:38:00+01:00 2023-07-07T20:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008231_002 Dismissed Planned Production unavailability 2023-07-07T18:30:24+01:00 2023-07-07T14:38:00+01:00 2023-07-07T20:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008231_001 Dismissed Planned Production unavailability 2023-07-07T14:39:39+01:00 2023-07-07T14:38:00+01:00 2023-07-07T22:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008235_002 Dismissed Planned Production unavailability 2023-07-07T20:34:13+01:00 2023-07-07T20:01:00+01:00 2023-07-08T04:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008235_001 Dismissed Planned Production unavailability 2023-07-07T18:32:38+01:00 2023-07-07T20:01:00+01:00 2023-07-08T04:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_SGRWO-3 48W00000SGRWO-3H
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008222_003 Dismissed Planned Production unavailability 2023-07-07T18:25:52+01:00 2023-07-07T00:01:00+01:00 2023-07-09T03:00:00+01:00 MW 10 150 160 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-3 48W00000SGRWO-3H
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008222_002 Dismissed Planned Production unavailability 2023-07-06T16:43:37+01:00 2023-07-07T00:01:00+01:00 2023-07-09T03:00:00+01:00 MW 10 150 160 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_SGRWO-3 48W00000SGRWO-3H
Seagreen Wind Energy Ltd
48X000000000263P 0000000000000000000008222_001 Dismissed Planned Production unavailability 2023-07-05T13:42:15+01:00 2023-07-07T00:01:00+01:00 2023-07-09T06:00:00+01:00 MW 80 80 160 Foreseen Maintenance
Commissioning
Wind Offshore 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_006 Inactive Planned Production unavailability 2023-07-07T15:47:31+01:00 2023-07-07T06:00:00+01:00 2023-07-07T14:41:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_005 Dismissed Planned Production unavailability 2023-07-07T14:40:52+01:00 2023-07-07T06:00:00+01:00 2023-07-07T14:41:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_004 Dismissed Planned Production unavailability 2023-07-07T02:51:54+01:00 2023-07-07T06:00:00+01:00 2023-07-07T22:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_003 Dismissed Planned Production unavailability 2023-07-07T01:50:41+01:00 2023-07-07T05:00:00+01:00 2023-07-07T22:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_002 Dismissed Planned Production unavailability 2023-07-06T23:43:15+01:00 2023-07-07T04:00:00+01:00 2023-07-07T22:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008229_001 Dismissed Planned Production unavailability 2023-07-06T21:57:39+01:00 2023-07-07T06:00:00+01:00 2023-07-07T22:00:00+01:00 MW 370 340 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000008228_005 Inactive Planned Production unavailability 2023-07-07T07:02:31+01:00 2023-07-07T05:00:00+01:00 2023-07-07T06:00:00+01:00 MW 460 250 710 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A