Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 1 2 3 4 5 >
T_VKNGW-4 48W00000VKNGW-4Z
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009527_002 Dismissed Planned Production unavailability 2024-10-09T09:24:25+01:00 2024-10-10T08:00:00+01:00 2024-10-11T18:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_VKNGW-4 48W00000VKNGW-4Z
Viking Energy Wind Farm LLP
48X000000000314Y 0000000000000000000009527_001 Dismissed Planned Production unavailability 2024-10-09T07:19:12+01:00 2024-10-10T08:00:00+01:00 2024-10-11T18:00:00+01:00 MW 112 0 112 Foreseen Maintenance
Commissioning
Wind Onshore 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009526_004 Inactive Planned Production unavailability 2024-10-08T11:02:33+01:00 2024-10-08T09:21:00+01:00 2024-10-08T09:55:00+01:00 MW 590 250 840 Foreseen Maintenance
Plant Fault - Boiler
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009526_003 Dismissed Planned Production unavailability 2024-10-08T09:39:59+01:00 2024-10-08T09:21:00+01:00 2024-10-08T09:55:00+01:00 MW 590 250 840 Foreseen Maintenance
Plant Fault - Boiler
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009526_002 Dismissed Planned Production unavailability 2024-10-08T09:33:32+01:00 2024-10-08T09:21:00+01:00 2024-10-08T09:45:00+01:00 MW 590 250 840 Foreseen Maintenance
Plant Fault - Boiler
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009526_001 Dismissed Planned Production unavailability 2024-10-08T09:21:04+01:00 2024-10-08T09:21:00+01:00 2024-10-08T09:35:00+01:00 MW 590 250 840 Foreseen Maintenance
Plant Fault - Boiler
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009525_002 Inactive Planned Production unavailability 2024-10-08T09:32:32+01:00 2024-10-08T07:51:00+01:00 2024-10-08T08:30:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009525_001 Dismissed Planned Production unavailability 2024-10-08T07:55:24+01:00 2024-10-08T07:51:00+01:00 2024-10-08T08:30:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009524_002 Inactive Planned Production unavailability 2024-10-08T17:32:32+01:00 2024-10-08T15:30:00+01:00 2024-10-08T16:30:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009524_001 Dismissed Planned Production unavailability 2024-10-07T22:55:58+01:00 2024-10-08T15:30:00+01:00 2024-10-08T16:30:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009523_004 Inactive Planned Production unavailability 2024-10-08T13:32:32+01:00 2024-10-08T11:00:00+01:00 2024-10-08T12:30:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009523_003 Dismissed Planned Production unavailability 2024-10-08T09:01:00+01:00 2024-10-08T11:00:00+01:00 2024-10-08T12:30:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009523_002 Dismissed Planned Production unavailability 2024-10-08T08:27:14+01:00 2024-10-08T11:00:00+01:00 2024-10-08T12:46:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009523_001 Dismissed Planned Production unavailability 2024-10-07T22:53:41+01:00 2024-10-08T10:30:00+01:00 2024-10-08T12:00:00+01:00 MW 460 380 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009522_003 Inactive Planned Production unavailability 2024-10-07T22:17:32+01:00 2024-10-07T20:55:00+01:00 2024-10-07T21:15:00+01:00 MW 400 440 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009522_002 Dismissed Planned Production unavailability 2024-10-07T20:39:50+01:00 2024-10-07T20:55:00+01:00 2024-10-07T21:15:00+01:00 MW 400 440 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009522_001 Dismissed Planned Production unavailability 2024-10-07T20:34:55+01:00 2024-10-07T20:45:00+01:00 2024-10-07T21:15:00+01:00 MW 400 440 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009521_003 Inactive Planned Production unavailability 2024-10-07T22:02:33+01:00 2024-10-07T20:10:00+01:00 2024-10-07T20:55:00+01:00 MW 325 515 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009521_002 Dismissed Planned Production unavailability 2024-10-07T20:39:10+01:00 2024-10-07T20:10:00+01:00 2024-10-07T20:55:00+01:00 MW 325 515 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009521_001 Dismissed Planned Production unavailability 2024-10-07T19:51:09+01:00 2024-10-07T20:10:00+01:00 2024-10-07T20:40:00+01:00 MW 325 515 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009520_003 Inactive Planned Production unavailability 2024-10-07T21:17:32+01:00 2024-10-07T19:40:00+01:00 2024-10-07T20:10:00+01:00 MW 260 580 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009520_002 Dismissed Planned Production unavailability 2024-10-07T19:46:04+01:00 2024-10-07T19:40:00+01:00 2024-10-07T20:10:00+01:00 MW 260 580 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009520_001 Dismissed Planned Production unavailability 2024-10-07T19:26:28+01:00 2024-10-07T19:40:00+01:00 2024-10-07T20:10:00+01:00 MW 250 590 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009519_003 Inactive Planned Production unavailability 2024-10-07T20:47:32+01:00 2024-10-07T19:10:00+01:00 2024-10-07T19:40:00+01:00 MW 200 640 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009519_002 Dismissed Planned Production unavailability 2024-10-07T19:17:50+01:00 2024-10-07T19:10:00+01:00 2024-10-07T19:40:00+01:00 MW 200 640 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009519_001 Dismissed Planned Production unavailability 2024-10-07T19:07:59+01:00 2024-10-07T19:10:00+01:00 2024-10-07T19:40:00+01:00 MW 180 660 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009518_005 Inactive Planned Production unavailability 2024-10-07T20:17:33+01:00 2024-10-07T18:35:00+01:00 2024-10-07T19:10:00+01:00 MW 130 710 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009518_004 Dismissed Planned Production unavailability 2024-10-07T19:06:34+01:00 2024-10-07T18:35:00+01:00 2024-10-07T19:10:00+01:00 MW 130 710 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009518_003 Dismissed Planned Production unavailability 2024-10-07T19:00:55+01:00 2024-10-07T18:35:00+01:00 2024-10-07T19:30:00+01:00 MW 130 710 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009518_002 Dismissed Planned Production unavailability 2024-10-07T18:44:47+01:00 2024-10-07T18:35:00+01:00 2024-10-07T19:05:00+01:00 MW 130 710 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009518_001 Dismissed Planned Production unavailability 2024-10-07T18:36:16+01:00 2024-10-07T18:35:00+01:00 2024-10-07T19:05:00+01:00 MW 120 720 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009517_003 Dismissed Planned Production unavailability 2024-10-07T20:24:16+01:00 2024-10-08T02:00:00+01:00 2024-10-08T07:59:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009517_002 Dismissed Planned Production unavailability 2024-10-07T16:01:52+01:00 2024-10-08T02:00:00+01:00 2024-10-08T07:59:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009517_001 Dismissed Planned Production unavailability 2024-10-07T15:59:51+01:00 2024-10-08T02:00:00+01:00 2024-10-08T07:59:00+01:00 MW 0 840 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
RHODE1 47W000000000212Y
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009516_002 Inactive Planned Production unavailability 2024-10-07T15:59:00+01:00 2024-10-10T15:45:00+01:00 2024-10-10T15:46:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
RHODE1 47W000000000212Y
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009516_001 Dismissed Planned Production unavailability 2024-10-07T15:48:10+01:00 2024-10-10T15:45:00+01:00 2024-10-10T15:46:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009515_002 Inactive Planned Production unavailability 2024-10-07T17:02:32+01:00 2024-10-07T15:30:00+01:00 2024-10-07T15:50:00+01:00 MW 160 680 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009515_001 Dismissed Planned Production unavailability 2024-10-07T15:28:17+01:00 2024-10-07T15:30:00+01:00 2024-10-07T15:50:00+01:00 MW 160 680 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009514_002 Inactive Planned Production unavailability 2024-10-07T16:32:32+01:00 2024-10-07T15:10:00+01:00 2024-10-07T15:30:00+01:00 MW 250 590 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009514_001 Dismissed Planned Production unavailability 2024-10-07T15:01:47+01:00 2024-10-07T15:10:00+01:00 2024-10-07T15:30:00+01:00 MW 250 590 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009513_005 Inactive Planned Production unavailability 2024-10-07T16:17:32+01:00 2024-10-07T13:56:00+01:00 2024-10-07T15:10:00+01:00 MW 423 417 840 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009513_004 Dismissed Planned Production unavailability 2024-10-07T14:45:22+01:00 2024-10-07T13:56:00+01:00 2024-10-07T15:10:00+01:00 MW 423 417 840 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009513_003 Dismissed Planned Production unavailability 2024-10-07T14:28:55+01:00 2024-10-07T13:56:00+01:00 2024-10-07T15:00:00+01:00 MW 423 417 840 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009513_002 Dismissed Planned Production unavailability 2024-10-07T14:21:56+01:00 2024-10-07T13:56:00+01:00 2024-10-07T15:00:00+01:00 MW 600 240 840 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009513_001 Dismissed Planned Production unavailability 2024-10-07T13:55:59+01:00 2024-10-07T13:56:00+01:00 2024-10-07T14:30:00+01:00 MW 600 240 840 Foreseen Maintenance
Plant Fault - Auxiliary Equipment
Fossil Gas 10YGB----------A
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009512_002 Inactive Planned Production unavailability 2024-10-07T13:28:22+01:00 2024-10-10T13:20:00+01:00 2024-10-10T13:21:00+01:00 MW 0 52 52 Foreseen Maintenance
Testing
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009512_001 Dismissed Planned Production unavailability 2024-10-07T13:22:37+01:00 2024-10-10T13:20:00+01:00 2024-10-10T13:21:00+01:00 MW 0 52 52 Foreseen Maintenance
Testing
Fossil Gas 10Y1001A1001A59C
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009511_002 Dismissed Planned Production unavailability 2024-10-07T15:54:30+01:00 2024-10-08T11:30:00+01:00 2024-10-08T13:30:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009511_001 Dismissed Planned Production unavailability 2024-10-07T09:52:24+01:00 2024-10-08T11:30:00+01:00 2024-10-08T13:30:00+01:00 MW 840 0 840 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000009510_002 Inactive Unplanned Production unavailability 2024-10-07T09:32:32+01:00 2024-10-07T07:41:00+01:00 2024-10-07T08:30:00+01:00 MW 840 0 840 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A