Last update at: 2023-12-03T08:00:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | ||||||||||||||||||
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006323_001 | Dismissed | Planned | Production unavailability | 2021-10-06T12:00:21+01:00 | 2021-10-07T09:00:00+01:00 | 2021-10-07T16:00:00+01:00 | MW | 11 | 48 | 59 | Foreseen Maintenance | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006313_002 | Inactive | Planned | Production unavailability | 2021-10-01T21:02:31+01:00 | 2021-10-01T17:01:00+01:00 | 2021-10-01T20:00:00+01:00 | MW | 13 | 72 | 85 | Foreseen Maintenance | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006313_001 | Dismissed | Planned | Production unavailability | 2021-09-30T09:38:23+01:00 | 2021-10-01T17:01:00+01:00 | 2021-10-01T20:00:00+01:00 | MW | 13 | 72 | 85 | Foreseen Maintenance | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006312_002 | Inactive | Planned | Production unavailability | 2021-10-01T18:02:31+01:00 | 2021-10-01T08:00:00+01:00 | 2021-10-01T17:00:00+01:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006312_001 | Dismissed | Planned | Production unavailability | 2021-09-30T09:37:05+01:00 | 2021-10-01T08:00:00+01:00 | 2021-10-01T17:00:00+01:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006307_005 | Inactive | Unplanned | Production unavailability | 2021-09-30T21:02:32+01:00 | 2021-09-27T09:30:00+01:00 | 2021-09-30T20:00:00+01:00 | MW | 18 | 41 | 59 | Failure | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006307_004 | Dismissed | Unplanned | Production unavailability | 2021-09-29T16:02:08+01:00 | 2021-09-27T09:30:00+01:00 | 2021-09-30T20:00:00+01:00 | MW | 18 | 41 | 59 | Failure | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006307_003 | Dismissed | Unplanned | Production unavailability | 2021-09-28T18:34:31+01:00 | 2021-09-27T09:30:00+01:00 | 2021-09-30T17:00:00+01:00 | MW | 18 | 41 | 59 | Failure | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006307_002 | Dismissed | Unplanned | Production unavailability | 2021-09-28T13:24:55+01:00 | 2021-09-27T09:30:00+01:00 | 2021-09-29T15:00:00+01:00 | MW | 18 | 41 | 59 | Failure | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006307_001 | Dismissed | Unplanned | Production unavailability | 2021-09-27T09:51:51+01:00 | 2021-09-27T09:30:00+01:00 | 2021-09-28T14:00:00+01:00 | MW | 18 | 41 | 59 | Failure | Maintenance |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006217_004 | Inactive | Unplanned | Production unavailability | 2021-09-04T17:02:31+01:00 | 2021-07-22T17:15:00+01:00 | 2021-09-04T16:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006217_003 | Dismissed | Unplanned | Production unavailability | 2021-08-23T15:46:01+01:00 | 2021-07-22T17:15:00+01:00 | 2021-09-04T16:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006217_002 | Dismissed | Unplanned | Production unavailability | 2021-08-20T17:39:55+01:00 | 2021-07-22T17:15:00+01:00 | 2021-09-03T00:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006217_001 | Dismissed | Unplanned | Production unavailability | 2021-08-16T11:01:30+01:00 | 2021-07-22T17:15:00+01:00 | 2021-08-20T17:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006176_003 | Inactive | Unplanned | Production unavailability | 2021-08-13T18:02:32+01:00 | 2021-07-22T17:15:00+01:00 | 2021-08-13T17:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006176_002 | Dismissed | Unplanned | Production unavailability | 2021-07-30T16:07:44+01:00 | 2021-07-22T17:15:00+01:00 | 2021-08-13T17:00:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006176_001 | Dismissed | Unplanned | Production unavailability | 2021-07-26T10:11:03+01:00 | 2021-07-22T17:15:00+01:00 | 2021-08-01T00:01:00+01:00 | MW | 85 | 0 | 85 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006121_002 | Inactive | Planned | Production unavailability | 2021-07-15T18:01:53+01:00 | 2021-07-12T08:30:00+01:00 | 2021-07-15T17:00:00+01:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006121_001 | Dismissed | Planned | Production unavailability | 2021-06-23T12:00:09+01:00 | 2021-07-12T08:30:00+01:00 | 2021-07-15T17:00:00+01:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006107_002 | Inactive | Planned | Production unavailability | 2021-07-08T18:01:51+01:00 | 2021-07-08T08:30:00+01:00 | 2021-07-08T17:00:00+01:00 | MW | 59 | 0 | 59 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006107_001 | Dismissed | Planned | Production unavailability | 2021-06-14T10:13:52+01:00 | 2021-07-08T08:30:00+01:00 | 2021-07-08T17:00:00+01:00 | MW | 59 | 0 | 59 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000005568_002 | Inactive | Unplanned | Production unavailability | 2021-03-12T21:02:33+00:00 | 2021-03-12T16:32:00+00:00 | 2021-03-12T20:00:00+00:00 | MW | 59 | 0 | 59 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
Coomacheo | 47W0000000002784 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000005568_001 | Dismissed | Unplanned | Production unavailability | 2021-03-12T17:00:26+00:00 | 2021-03-12T16:32:00+00:00 | 2021-03-12T20:00:00+00:00 | MW | 59 | 0 | 59 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008652_003 | Inactive | Unplanned | Production unavailability | 2023-12-01T09:17:32+00:00 | 2023-12-01T06:24:00+00:00 | 2023-12-01T08:12:00+00:00 | MW | 0 | 52 | 52 | Failure | Plant Fault - Control System |
Fossil Gas | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008652_002 | Dismissed | Unplanned | Production unavailability | 2023-12-01T08:08:54+00:00 | 2023-12-01T06:24:00+00:00 | 2023-12-01T08:12:00+00:00 | MW | 0 | 52 | 52 | Failure | Plant Fault - Control System |
Fossil Gas | 10Y1001A1001A59C |
RHODE1 | 47W000000000212Y | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008652_001 | Dismissed | Unplanned | Production unavailability | 2023-12-01T06:46:43+00:00 | 2023-12-01T06:24:00+00:00 | 2023-12-01T10:00:00+00:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Control System |
Fossil Gas | 10Y1001A1001A59C |
TAWN3 | 47W000000000215S | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008642_001 | Active | Planned | Production unavailability | 2023-11-27T12:37:44+00:00 | 2024-07-06T09:00:00+01:00 | 2024-07-12T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008641_001 | Active | Planned | Production unavailability | 2023-11-27T12:35:21+00:00 | 2024-06-29T09:00:00+01:00 | 2024-07-05T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008563_003 | Inactive | Unplanned | Production unavailability | 2023-11-20T12:02:32+00:00 | 2023-11-18T20:58:00+00:00 | 2023-11-20T11:00:00+00:00 | MW | 0 | 52 | 52 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008563_002 | Dismissed | Unplanned | Production unavailability | 2023-11-20T10:50:57+00:00 | 2023-11-18T20:58:00+00:00 | 2023-11-20T11:00:00+00:00 | MW | 0 | 52 | 52 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008563_001 | Dismissed | Unplanned | Production unavailability | 2023-11-18T21:01:31+00:00 | 2023-11-18T20:58:00+00:00 | 2023-11-20T17:00:00+00:00 | MW | 52 | 0 | 52 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008161_003 | Active | Planned | Production unavailability | 2023-11-20T10:51:59+00:00 | 2024-05-25T08:00:00+01:00 | 2024-05-31T16:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008161_002 | Dismissed | Planned | Production unavailability | 2023-11-20T10:44:22+00:00 | 2024-05-25T08:00:00+01:00 | 2024-05-31T16:00:00+01:00 | MW | 0 | 52 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
RHODE2 | 47W000000000213W | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008161_001 | Dismissed | Planned | Production unavailability | 2023-05-29T16:06:45+01:00 | 2024-05-25T08:00:00+01:00 | 2024-05-31T16:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008560_003 | Inactive | Planned | Production unavailability | 2023-11-18T14:32:32+00:00 | 2023-11-18T10:00:00+00:00 | 2023-11-18T13:30:00+00:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Plant Fault - Fuel Supply |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008560_002 | Dismissed | Planned | Production unavailability | 2023-11-18T13:02:12+00:00 | 2023-11-18T10:00:00+00:00 | 2023-11-18T13:30:00+00:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Plant Fault - Fuel Supply |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008560_001 | Dismissed | Planned | Production unavailability | 2023-11-17T15:27:03+00:00 | 2023-11-18T10:00:00+00:00 | 2023-11-18T16:00:00+00:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Plant Fault - Fuel Supply |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008540_003 | Inactive | Planned | Production unavailability | 2023-11-14T23:02:32+00:00 | 2023-11-13T22:00:00+00:00 | 2023-11-14T22:00:00+00:00 | MW | 464 | 0 | 464 | Failure | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008540_002 | Dismissed | Planned | Production unavailability | 2023-11-14T16:33:09+00:00 | 2023-11-13T22:00:00+00:00 | 2023-11-14T22:00:00+00:00 | MW | 464 | 0 | 464 | Failure | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008540_001 | Dismissed | Planned | Production unavailability | 2023-11-13T09:37:48+00:00 | 2023-11-13T22:00:00+00:00 | 2023-11-14T23:59:00+00:00 | MW | 464 | 0 | 464 | Failure | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008537_002 | Inactive | Unplanned | Production unavailability | 2023-11-10T08:32:32+00:00 | 2023-11-10T05:58:00+00:00 | 2023-11-10T07:20:00+00:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008537_001 | Dismissed | Unplanned | Production unavailability | 2023-11-10T06:00:21+00:00 | 2023-11-10T05:58:00+00:00 | 2023-11-10T07:20:00+00:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Auxiliary Equipment |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_007 | Active | Planned | Production unavailability | 2023-10-20T15:18:38+01:00 | 2024-05-17T22:00:00+01:00 | 2024-06-16T22:00:00+01:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_006 | Dismissed | Planned | Production unavailability | 2023-05-31T15:15:31+01:00 | 2024-05-17T22:00:00+01:00 | 2024-06-09T22:00:00+01:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_005 | Dismissed | Planned | Production unavailability | 2022-08-05T15:14:33+01:00 | 2024-03-18T00:00:00+00:00 | 2024-04-08T00:00:00+01:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_004 | Dismissed | Planned | Production unavailability | 2022-03-23T10:54:49+00:00 | 2024-03-18T00:00:00+00:00 | 2024-04-08T00:00:00+01:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_003 | Dismissed | Planned | Production unavailability | 2021-07-28T08:46:33+01:00 | 2024-03-18T00:00:00+00:00 | 2024-04-08T00:00:00+01:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_002 | Dismissed | Planned | Production unavailability | 2020-11-24T11:00:34+00:00 | 2024-03-04T00:00:00+00:00 | 2024-03-25T00:00:00+00:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000005173_001 | Dismissed | Planned | Production unavailability | 2020-06-15T21:38:47+01:00 | 2024-03-04T00:00:00+00:00 | 2024-03-25T00:00:00+00:00 | MW | 464 | 0 | 464 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000008474_003 | Inactive | Planned | Production unavailability | 2023-10-07T04:02:32+01:00 | 2023-10-02T23:00:00+01:00 | 2023-10-07T03:00:00+01:00 | MW | 464 | 0 | 464 | Failure | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |