Last update at: 2024-05-17T19:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 1 2 3 4 5 > | ||||||||||||||||||
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007954_001 | Dismissed | Planned | Production unavailability | 2023-02-15T13:40:51+00:00 | 2023-02-15T13:40:00+00:00 | 2023-02-15T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007854_002 | Dismissed | Planned | Production unavailability | 2023-01-18T14:06:50+00:00 | 2023-01-18T13:30:00+00:00 | 2023-01-18T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000007854_001 | Dismissed | Planned | Production unavailability | 2023-01-18T13:25:48+00:00 | 2023-01-18T13:30:00+00:00 | 2023-01-18T14:00:00+00:00 | MW | 10 | 155 | 165 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009060_003 | Active | Planned | Production unavailability | 2024-05-16T17:32:51+01:00 | 2024-05-03T13:25:00+01:00 | 2024-05-24T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009060_002 | Dismissed | Planned | Production unavailability | 2024-05-08T10:08:48+01:00 | 2024-05-03T13:24:00+01:00 | 2024-05-24T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009060_001 | Dismissed | Planned | Production unavailability | 2024-05-03T13:25:15+01:00 | 2024-05-03T13:24:00+01:00 | 2024-05-17T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009061_002 | Active | Planned | Production unavailability | 2024-05-08T10:08:34+01:00 | 2024-05-03T13:25:00+01:00 | 2024-05-24T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009061_001 | Dismissed | Planned | Production unavailability | 2024-05-03T13:26:31+01:00 | 2024-05-03T13:25:00+01:00 | 2024-05-17T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009062_002 | Active | Planned | Production unavailability | 2024-05-08T10:08:19+01:00 | 2024-05-03T13:27:00+01:00 | 2024-05-24T08:00:00+01:00 | MW | 108 | 0 | 108 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009062_001 | Dismissed | Planned | Production unavailability | 2024-05-03T13:27:43+01:00 | 2024-05-03T13:27:00+01:00 | 2024-05-17T08:00:00+01:00 | MW | 108 | 0 | 108 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009063_002 | Active | Planned | Production unavailability | 2024-05-08T10:08:03+01:00 | 2024-05-03T13:28:00+01:00 | 2024-05-24T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009063_001 | Dismissed | Planned | Production unavailability | 2024-05-03T13:28:41+01:00 | 2024-05-03T13:28:00+01:00 | 2024-05-17T08:00:00+01:00 | MW | 112 | 0 | 112 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009028_002 | Dismissed | Planned | Production unavailability | 2024-04-17T16:54:52+01:00 | 2024-04-17T16:45:00+01:00 | 2024-04-17T16:50:00+01:00 | MW | 0 | 9 | 9 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009028_001 | Dismissed | Planned | Production unavailability | 2024-04-17T16:43:16+01:00 | 2024-04-17T16:45:00+01:00 | 2024-04-17T16:50:00+01:00 | MW | 9 | 0 | 9 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_003 | Dismissed | Planned | Production unavailability | 2024-04-16T14:05:58+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T14:00:00+01:00 | MW | 0 | 10 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_002 | Dismissed | Planned | Production unavailability | 2024-04-16T13:33:19+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T14:00:00+01:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-4 | 48W00000VKNGW-4Z | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000009021_001 | Dismissed | Planned | Production unavailability | 2024-04-16T13:00:49+01:00 | 2024-04-16T13:00:00+01:00 | 2024-04-16T13:30:00+01:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_003 | Dismissed | Planned | Production unavailability | 2024-03-22T11:46:50+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_002 | Dismissed | Planned | Production unavailability | 2024-03-22T11:10:29+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_001 | Dismissed | Planned | Production unavailability | 2024-03-22T10:24:43+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008915_002 | Dismissed | Planned | Production unavailability | 2024-03-06T17:00:02+00:00 | 2024-03-06T16:30:00+00:00 | 2024-03-06T17:00:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008915_001 | Dismissed | Planned | Production unavailability | 2024-03-06T16:27:55+00:00 | 2024-03-06T16:30:00+00:00 | 2024-03-06T17:00:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_003 | Dismissed | Planned | Production unavailability | 2024-02-26T15:27:37+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T15:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_002 | Dismissed | Planned | Production unavailability | 2024-02-26T10:19:17+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T15:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008880_001 | Dismissed | Planned | Production unavailability | 2024-02-26T09:38:02+00:00 | 2024-02-26T09:40:00+00:00 | 2024-02-26T10:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008852_002 | Dismissed | Planned | Production unavailability | 2024-02-15T16:30:32+00:00 | 2024-02-15T15:31:00+00:00 | 2024-02-15T15:51:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-2 | 48W00000VKNGW-22 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008852_001 | Dismissed | Planned | Production unavailability | 2024-02-15T15:32:03+00:00 | 2024-02-15T15:31:00+00:00 | 2024-02-15T15:51:00+00:00 | MW | 10 | 0 | 10 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008851_002 | Dismissed | Planned | Production unavailability | 2024-02-15T15:39:56+00:00 | 2024-02-15T15:10:00+00:00 | 2024-02-15T15:30:00+00:00 | MW | 0 | 0 | 0 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
VKNGW-1 | 48W00000VKNGW-14 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008851_001 | Dismissed | Planned | Production unavailability | 2024-02-15T15:10:53+00:00 | 2024-02-15T15:10:00+00:00 | 2024-02-15T15:30:00+00:00 | MW | 0 | 0 | 0 | Foreseen Maintenance | Commissioning |
Wind Onshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009066_004 | Active | Planned | Production unavailability | 2024-05-15T08:32:56+01:00 | 2024-05-05T10:00:00+01:00 | 2024-05-20T10:30:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009066_003 | Dismissed | Planned | Production unavailability | 2024-05-10T07:31:39+01:00 | 2024-05-05T10:00:00+01:00 | 2024-05-15T12:20:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009066_002 | Dismissed | Planned | Production unavailability | 2024-05-07T17:19:55+01:00 | 2024-05-05T10:00:00+01:00 | 2024-05-10T08:00:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009066_001 | Dismissed | Planned | Production unavailability | 2024-05-06T07:50:42+01:00 | 2024-05-05T10:00:00+01:00 | 2024-05-08T08:00:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009054_003 | Inactive | Planned | Production unavailability | 2024-05-05T11:02:32+01:00 | 2024-04-29T10:00:00+01:00 | 2024-05-05T10:00:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009054_002 | Dismissed | Planned | Production unavailability | 2024-05-01T13:03:03+01:00 | 2024-04-29T10:00:00+01:00 | 2024-05-05T10:00:00+01:00 | MW | 157 | 0 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009054_001 | Dismissed | Planned | Production unavailability | 2024-04-29T14:25:36+01:00 | 2024-04-29T10:00:00+01:00 | 2024-05-03T14:26:00+01:00 | MW | 105 | 52 | 157 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009043_003 | Inactive | Planned | Production unavailability | 2024-04-29T11:02:32+01:00 | 2024-04-23T09:00:00+01:00 | 2024-04-29T10:00:00+01:00 | MW | 103 | 54 | 157 | Shutdown | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009043_002 | Dismissed | Planned | Production unavailability | 2024-04-25T08:28:36+01:00 | 2024-04-23T09:00:00+01:00 | 2024-04-29T10:00:00+01:00 | MW | 103 | 54 | 157 | Shutdown | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000009043_001 | Dismissed | Planned | Production unavailability | 2024-04-23T10:11:51+01:00 | 2024-04-23T09:00:00+01:00 | 2024-04-26T10:11:00+01:00 | MW | 103 | 54 | 157 | Shutdown | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_006 | Inactive | Planned | Production unavailability | 2024-04-23T10:02:31+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 105 | 52 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_005 | Dismissed | Planned | Production unavailability | 2024-04-19T13:09:27+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 105 | 52 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_004 | Dismissed | Planned | Production unavailability | 2024-04-19T13:08:40+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 157 | 0 | 157 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_003 | Dismissed | Planned | Production unavailability | 2024-04-18T09:44:35+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-23T09:00:00+01:00 | MW | 250 | 52 | 302 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_002 | Dismissed | Planned | Production unavailability | 2024-04-11T08:37:44+01:00 | 2024-04-11T08:30:00+01:00 | 2024-04-19T09:00:00+01:00 | MW | 250 | 52 | 302 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008961_001 | Dismissed | Planned | Production unavailability | 2024-03-27T11:39:35+00:00 | 2024-04-10T12:00:00+01:00 | 2024-04-26T12:00:00+01:00 | MW | 146 | 156 | 302 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_034 | Dismissed | Planned | Production unavailability | 2024-04-19T13:07:03+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_033 | Dismissed | Planned | Production unavailability | 2024-04-19T13:04:31+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_032 | Dismissed | Planned | Production unavailability | 2024-04-19T13:03:21+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 138 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_031 | Dismissed | Planned | Production unavailability | 2024-04-19T13:02:21+01:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 0 | 0 | 0 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
DBAWO-5 | 48W00000DBAWO-5B | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008256_030 | Dismissed | Planned | Production unavailability | 2024-03-22T08:16:23+00:00 | 2023-07-18T14:00:00+01:00 | 2024-11-11T10:00:00+00:00 | MW | 138 | 0 | 138 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |