Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 6 7 8 9 10 > | ||||||||||||||||||
TB2 | 47W000000000208P | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006342_001 | Dismissed | Unplanned | Production unavailability | 2021-10-14T08:35:42+01:00 | 2021-10-14T00:00:00+01:00 | 2021-10-28T00:00:00+01:00 | MW | 54 | 0 | 54 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006378_003 | Inactive | Planned | Production unavailability | 2021-10-28T15:02:32+01:00 | 2021-10-28T08:00:00+01:00 | 2021-10-28T14:00:00+01:00 | MW | 380 | 800 | 1180 | Failure | Maintenance |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006378_002 | Dismissed | Planned | Production unavailability | 2021-10-28T12:30:22+01:00 | 2021-10-28T08:00:00+01:00 | 2021-10-28T14:00:00+01:00 | MW | 380 | 800 | 1180 | Failure | Maintenance |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006378_001 | Dismissed | Planned | Production unavailability | 2021-10-28T07:46:40+01:00 | 2021-10-28T08:00:00+01:00 | 2021-10-28T16:00:00+01:00 | MW | 380 | 800 | 1180 | Failure | Maintenance |
Fossil Gas | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006375_002 | Dismissed | Unplanned | Production unavailability | 2021-10-27T10:04:36+01:00 | 2021-10-27T09:30:00+01:00 | 2021-10-28T23:00:00+01:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE GENERATION |
48X000000000077M | 0000000000000000000005232_003 | Dismissed | Planned | Production unavailability | 2021-03-12T12:14:31+00:00 | 2021-09-03T23:00:00+01:00 | 2021-10-28T23:00:00+01:00 | MW | 1180 | 0 | 1180 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006253_002 | Dismissed | Planned | Production unavailability | 2021-10-19T16:36:20+01:00 | 2021-10-27T00:00:00+01:00 | 2021-10-28T23:59:00+01:00 | MW | 734 | 112 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006253_001 | Dismissed | Planned | Production unavailability | 2021-09-07T10:55:30+01:00 | 2021-10-27T00:00:00+01:00 | 2021-10-28T23:59:00+01:00 | MW | 734 | 112 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006374_001 | Dismissed | Unplanned | Production unavailability | 2021-10-25T16:11:50+01:00 | 2021-10-25T11:32:00+01:00 | 2021-10-29T17:00:00+01:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Turbine |
Fossil Oil | 10Y1001A1001A59C |
T_BHLAW-1 | 48W00000BHLAW-15 | SSE GENERATION |
48X000000000077M | 0000000000000000000006276_002 | Dismissed | Planned | Production unavailability | 2021-10-05T16:41:58+01:00 | 2021-10-20T08:00:00+01:00 | 2021-10-29T17:00:00+01:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
T_BHLAW-1 | 48W00000BHLAW-15 | SSE GENERATION |
48X000000000077M | 0000000000000000000006276_001 | Dismissed | Planned | Production unavailability | 2021-09-09T15:01:52+01:00 | 2021-10-20T08:00:00+01:00 | 2021-10-29T17:00:00+01:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Grid |
Wind Onshore | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006375_006 | Inactive | Unplanned | Production unavailability | 2021-10-29T18:47:32+01:00 | 2021-10-27T09:30:00+01:00 | 2021-10-29T17:45:00+01:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006375_005 | Dismissed | Unplanned | Production unavailability | 2021-10-29T17:43:42+01:00 | 2021-10-27T09:30:00+01:00 | 2021-10-29T17:45:00+01:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006341_002 | Dismissed | Planned | Production unavailability | 2021-10-15T14:14:43+01:00 | 2021-10-18T08:00:00+01:00 | 2021-10-29T18:00:00+01:00 | MW | 400 | 780 | 1180 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006375_003 | Dismissed | Unplanned | Production unavailability | 2021-10-28T09:18:02+01:00 | 2021-10-27T09:30:00+01:00 | 2021-10-29T23:00:00+01:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006195_004 | Dismissed | Planned | Production unavailability | 2021-10-19T16:28:45+01:00 | 2020-11-24T00:00:00+00:00 | 2021-10-29T23:59:00+01:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006103_002 | Dismissed | Planned | Production unavailability | 2021-08-05T15:05:53+01:00 | 2021-10-15T00:00:00+01:00 | 2021-10-29T23:59:00+01:00 | MW | 286 | 560 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006103_001 | Dismissed | Planned | Production unavailability | 2021-06-10T12:24:25+01:00 | 2021-10-15T00:00:00+01:00 | 2021-10-29T23:59:00+01:00 | MW | 286 | 560 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006379_004 | Dismissed | Planned | Production unavailability | 2021-10-30T04:03:05+01:00 | 2021-10-28T11:59:00+01:00 | 2021-10-30T12:00:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006379_003 | Dismissed | Planned | Production unavailability | 2021-10-30T00:19:47+01:00 | 2021-10-28T11:59:00+01:00 | 2021-10-30T12:00:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006379_002 | Dismissed | Planned | Production unavailability | 2021-10-29T10:49:01+01:00 | 2021-10-28T11:59:00+01:00 | 2021-10-30T12:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006379_001 | Dismissed | Planned | Production unavailability | 2021-10-28T11:49:59+01:00 | 2021-10-28T11:59:00+01:00 | 2021-10-30T12:00:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
Great Island | 47W0000000001024 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006375_004 | Dismissed | Unplanned | Production unavailability | 2021-10-29T09:13:21+01:00 | 2021-10-27T09:30:00+01:00 | 2021-10-30T23:00:00+01:00 | MW | 464 | 0 | 464 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_002 | Dismissed | Planned | Production unavailability | 2021-10-19T16:31:00+01:00 | 2021-10-30T00:00:00+01:00 | 2021-10-30T23:59:00+01:00 | MW | 734 | 112 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006104_002 | Dismissed | Planned | Production unavailability | 2021-08-05T15:08:41+01:00 | 2021-10-30T00:00:00+01:00 | 2021-10-30T23:59:00+01:00 | MW | 186 | 660 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006104_001 | Dismissed | Planned | Production unavailability | 2021-06-10T12:25:45+01:00 | 2021-10-30T00:00:00+01:00 | 2021-10-30T23:59:00+01:00 | MW | 186 | 660 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006195_007 | Inactive | Planned | Production unavailability | 2021-10-31T11:32:34+00:00 | 2020-11-24T00:00:00+00:00 | 2021-10-31T10:29:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006195_006 | Dismissed | Planned | Production unavailability | 2021-10-28T16:22:42+01:00 | 2020-11-24T00:00:00+00:00 | 2021-10-31T10:29:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006195_005 | Dismissed | Planned | Production unavailability | 2021-10-27T09:19:07+01:00 | 2020-11-24T00:00:00+00:00 | 2021-10-31T10:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_001 | Dismissed | Planned | Production unavailability | 2021-10-31T10:26:49+00:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T11:30:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_002 | Dismissed | Planned | Production unavailability | 2021-10-31T11:19:47+00:00 | 2021-10-31T11:29:00+00:00 | 2021-10-31T12:29:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_003 | Dismissed | Planned | Production unavailability | 2021-10-31T12:14:34+00:00 | 2021-10-31T11:29:00+00:00 | 2021-10-31T13:29:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_004 | Dismissed | Planned | Production unavailability | 2021-10-31T13:12:28+00:00 | 2021-10-31T11:29:00+00:00 | 2021-10-31T14:29:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_006 | Inactive | Planned | Production unavailability | 2021-10-31T14:43:14+00:00 | 2021-10-31T11:29:00+00:00 | 2021-10-31T14:38:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006392_005 | Dismissed | Planned | Production unavailability | 2021-10-31T14:21:24+00:00 | 2021-10-31T11:29:00+00:00 | 2021-10-31T14:59:00+00:00 | MW | 846 | 0 | 846 | Failure | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_008 | Inactive | Planned | Production unavailability | 2021-10-31T18:47:32+00:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T17:35:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_007 | Dismissed | Planned | Production unavailability | 2021-10-31T17:33:35+00:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T17:35:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006393_003 | Inactive | Planned | Production unavailability | 2021-10-31T18:47:32+00:00 | 2021-10-31T17:11:00+00:00 | 2021-10-31T17:35:00+00:00 | MW | 761 | 85 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006393_002 | Dismissed | Planned | Production unavailability | 2021-10-31T17:33:08+00:00 | 2021-10-31T17:11:00+00:00 | 2021-10-31T17:35:00+00:00 | MW | 761 | 85 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_004 | Dismissed | Planned | Production unavailability | 2021-10-28T16:34:23+01:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T18:00:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_003 | Dismissed | Planned | Production unavailability | 2021-10-27T09:25:18+01:00 | 2021-10-31T11:00:00+00:00 | 2021-10-31T18:00:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006374_004 | Dismissed | Unplanned | Production unavailability | 2021-10-31T12:03:54+00:00 | 2021-10-25T11:32:00+01:00 | 2021-10-31T18:00:00+00:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Turbine |
Fossil Oil | 10Y1001A1001A59C |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006374_003 | Dismissed | Unplanned | Production unavailability | 2021-10-29T10:51:53+01:00 | 2021-10-25T11:32:00+01:00 | 2021-10-31T18:00:00+00:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Turbine |
Fossil Oil | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_005 | Dismissed | Planned | Production unavailability | 2021-10-31T14:00:30+00:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T22:00:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006247_006 | Dismissed | Planned | Production unavailability | 2021-10-31T14:19:43+00:00 | 2021-10-31T10:30:00+00:00 | 2021-10-31T22:30:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006393_001 | Dismissed | Planned | Production unavailability | 2021-10-31T17:12:38+00:00 | 2021-10-31T17:11:00+00:00 | 2021-10-31T22:30:00+00:00 | MW | 761 | 85 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006372_003 | Dismissed | Unplanned | Production unavailability | 2021-10-24T10:06:40+01:00 | 2021-10-22T16:28:00+01:00 | 2021-11-01T12:00:00+00:00 | MW | 370 | 340 | 710 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000006394_002 | Inactive | Planned | Consumption unavailability | 2021-11-01T15:02:32+00:00 | 2021-11-01T10:00:00+00:00 | 2021-11-01T14:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000006394_001 | Dismissed | Planned | Consumption unavailability | 2021-11-01T09:43:01+00:00 | 2021-11-01T10:00:00+00:00 | 2021-11-01T14:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
TB3 | 47W0000000000994 | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006374_002 | Dismissed | Unplanned | Production unavailability | 2021-10-28T11:41:28+01:00 | 2021-10-25T11:32:00+01:00 | 2021-11-01T17:00:00+00:00 | MW | 241 | 0 | 241 | Failure | Plant Fault - Turbine |
Fossil Oil | 10Y1001A1001A59C |