Last update at: 2024-11-03T07:00:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 2 3 4 5 > | ||||||||||||||||||
TB1 | 47W000000000207R | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006395_003 | Inactive | Unplanned | Production unavailability | 2021-11-03T18:17:32+00:00 | 2021-11-01T00:00:00+00:00 | 2021-11-03T17:05:00+00:00 | MW | 17 | 37 | 54 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
TB1 | 47W000000000207R | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006395_002 | Dismissed | Unplanned | Production unavailability | 2021-11-03T17:01:32+00:00 | 2021-11-01T00:00:00+00:00 | 2021-11-03T17:05:00+00:00 | MW | 17 | 37 | 54 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006252_004 | Dismissed | Planned | Production unavailability | 2021-10-27T12:30:23+01:00 | 2021-10-31T18:01:00+00:00 | 2021-11-03T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006255_002 | Dismissed | Planned | Production unavailability | 2021-10-19T16:37:53+01:00 | 2021-11-03T00:00:00+00:00 | 2021-11-03T23:59:00+00:00 | MW | 586 | 260 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006252_005 | Dismissed | Planned | Production unavailability | 2021-10-29T09:40:42+01:00 | 2021-10-31T18:01:00+00:00 | 2021-11-04T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006407_003 | Inactive | Unplanned | Production unavailability | 2021-11-04T18:32:34+00:00 | 2021-11-04T09:00:00+00:00 | 2021-11-04T17:30:00+00:00 | MW | 370 | 340 | 710 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006407_002 | Dismissed | Unplanned | Production unavailability | 2021-11-04T17:18:15+00:00 | 2021-11-04T09:00:00+00:00 | 2021-11-04T17:30:00+00:00 | MW | 370 | 340 | 710 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006382_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:19:29+00:00 | 2021-11-04T10:00:00+00:00 | 2021-11-04T18:00:00+00:00 | MW | 696 | 150 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006382_001 | Dismissed | Planned | Production unavailability | 2021-10-29T09:51:30+01:00 | 2021-11-04T10:00:00+00:00 | 2021-11-04T18:00:00+00:00 | MW | 696 | 150 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006255_003 | Dismissed | Planned | Production unavailability | 2021-10-20T10:39:02+01:00 | 2021-11-03T00:00:00+00:00 | 2021-11-04T23:59:00+00:00 | MW | 734 | 112 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006254_002 | Dismissed | Planned | Production unavailability | 2021-10-19T16:34:57+01:00 | 2021-10-29T00:00:00+01:00 | 2021-11-04T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006254_001 | Dismissed | Planned | Production unavailability | 2021-09-07T11:01:01+01:00 | 2021-10-29T00:00:00+01:00 | 2021-11-04T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006383_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:19:07+00:00 | 2021-11-04T18:01:00+00:00 | 2021-11-05T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006383_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:00:47+01:00 | 2021-11-04T18:01:00+00:00 | 2021-11-05T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006372_004 | Dismissed | Unplanned | Production unavailability | 2021-10-28T18:36:10+01:00 | 2021-10-22T16:28:00+01:00 | 2021-11-05T10:00:00+00:00 | MW | 370 | 340 | 710 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006384_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:18:49+00:00 | 2021-11-05T10:00:00+00:00 | 2021-11-05T18:00:00+00:00 | MW | 746 | 100 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006384_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:03:37+01:00 | 2021-11-05T10:00:00+00:00 | 2021-11-05T18:00:00+00:00 | MW | 746 | 100 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000006407_001 | Dismissed | Unplanned | Production unavailability | 2021-11-04T09:01:40+00:00 | 2021-11-04T09:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 370 | 340 | 710 | Failure | Plant Fault - Gas Turbine |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006255_005 | Dismissed | Planned | Production unavailability | 2021-10-29T11:36:37+01:00 | 2021-11-04T00:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006255_004 | Dismissed | Planned | Production unavailability | 2021-10-27T12:35:07+01:00 | 2021-11-04T00:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 726 | 120 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006255_001 | Dismissed | Planned | Production unavailability | 2021-09-07T11:06:24+01:00 | 2021-11-05T00:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 586 | 260 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006358_002 | Dismissed | Planned | Production unavailability | 2021-10-27T13:15:11+01:00 | 2021-11-05T00:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006358_001 | Dismissed | Planned | Production unavailability | 2021-10-20T10:53:50+01:00 | 2021-11-05T00:00:00+00:00 | 2021-11-05T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006385_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:18:33+00:00 | 2021-11-05T18:01:00+00:00 | 2021-11-06T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006385_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:10:31+01:00 | 2021-11-05T18:01:00+00:00 | 2021-11-06T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006386_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:18:10+00:00 | 2021-11-06T10:00:00+00:00 | 2021-11-06T18:00:00+00:00 | MW | 546 | 300 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006386_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:14:48+01:00 | 2021-11-06T10:00:00+00:00 | 2021-11-06T18:00:00+00:00 | MW | 546 | 300 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006387_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:17:50+00:00 | 2021-11-06T18:01:00+00:00 | 2021-11-07T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006387_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:25:53+01:00 | 2021-11-06T18:01:00+00:00 | 2021-11-07T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006408_001 | Dismissed | Unplanned | Production unavailability | 2021-11-05T08:17:16+00:00 | 2021-11-05T08:15:00+00:00 | 2021-11-07T12:00:00+00:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006388_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:16:53+00:00 | 2021-11-07T10:00:00+00:00 | 2021-11-07T18:00:00+00:00 | MW | 396 | 450 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006388_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:29:10+01:00 | 2021-11-07T10:00:00+00:00 | 2021-11-07T18:00:00+00:00 | MW | 396 | 450 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006258_002 | Dismissed | Planned | Production unavailability | 2021-10-20T11:07:32+01:00 | 2021-11-06T00:00:00+00:00 | 2021-11-07T23:59:00+00:00 | MW | 466 | 380 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006257_003 | Dismissed | Planned | Production unavailability | 2021-10-20T11:21:08+01:00 | 2021-11-04T00:00:00+00:00 | 2021-11-07T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006257_002 | Dismissed | Planned | Production unavailability | 2021-10-19T16:38:40+01:00 | 2021-11-04T00:00:00+00:00 | 2021-11-07T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006257_001 | Dismissed | Planned | Production unavailability | 2021-09-07T11:15:04+01:00 | 2021-11-06T00:00:00+00:00 | 2021-11-07T23:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006389_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:16:29+00:00 | 2021-11-07T18:01:00+00:00 | 2021-11-08T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006389_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:33:06+01:00 | 2021-11-07T18:01:00+00:00 | 2021-11-08T09:59:00+00:00 | MW | 846 | 0 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
TB1 | 47W000000000207R | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000006406_001 | Dismissed | Unplanned | Production unavailability | 2021-11-03T17:07:16+00:00 | 2021-11-03T17:06:00+00:00 | 2021-11-08T17:00:00+00:00 | MW | 54 | 0 | 54 | Failure | Plant Fault - Boiler |
Fossil Oil | 10Y1001A1001A59C |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006390_002 | Dismissed | Planned | Production unavailability | 2021-11-03T12:15:58+00:00 | 2021-11-08T10:00:00+00:00 | 2021-11-08T18:00:00+00:00 | MW | 396 | 450 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006390_001 | Dismissed | Planned | Production unavailability | 2021-10-29T10:35:21+01:00 | 2021-11-08T10:00:00+00:00 | 2021-11-08T18:00:00+00:00 | MW | 396 | 450 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006408_006 | Inactive | Unplanned | Production unavailability | 2021-11-08T23:01:53+00:00 | 2021-11-05T08:15:00+00:00 | 2021-11-08T22:00:00+00:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006408_005 | Dismissed | Unplanned | Production unavailability | 2021-11-08T19:49:25+00:00 | 2021-11-05T08:15:00+00:00 | 2021-11-08T22:00:00+00:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006258_004 | Dismissed | Planned | Production unavailability | 2021-10-29T11:37:21+01:00 | 2021-11-06T00:00:00+00:00 | 2021-11-08T23:59:00+00:00 | MW | 566 | 280 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000006258_003 | Dismissed | Planned | Production unavailability | 2021-10-27T12:37:48+01:00 | 2021-11-06T00:00:00+00:00 | 2021-11-08T23:59:00+00:00 | MW | 566 | 280 | 846 | Foreseen Maintenance | Commissioning |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006408_004 | Dismissed | Unplanned | Production unavailability | 2021-11-08T14:33:21+00:00 | 2021-11-05T08:15:00+00:00 | 2021-11-09T00:00:00+00:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_PEHE-1 | 48W000000PEHE-15 | SSE Thermal Generation (Scotland) Ltd |
48X0000000003024 | 0000000000000000000006408_003 | Dismissed | Unplanned | Production unavailability | 2021-11-08T08:21:06+00:00 | 2021-11-05T08:15:00+00:00 | 2021-11-09T06:00:00+00:00 | MW | 400 | 780 | 1180 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006409_002 | Inactive | Planned | Production unavailability | 2021-11-09T16:01:53+00:00 | 2021-11-09T08:30:00+00:00 | 2021-11-09T15:00:00+00:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
Meentycat | 47W000000000272G | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000006409_001 | Dismissed | Planned | Production unavailability | 2021-11-05T09:37:12+00:00 | 2021-11-09T08:30:00+00:00 | 2021-11-09T15:00:00+00:00 | MW | 85 | 0 | 85 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10Y1001A1001A59C |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000006233_004 | Dismissed | Planned | Production unavailability | 2021-11-09T15:29:28+00:00 | 2021-11-09T08:00:00+00:00 | 2021-11-09T15:30:00+00:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Planned Outage |
Hydro Water Reservoir | 10YGB----------A |