This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-05-03T13:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 3 4 5 6 7 >
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000005522_001 Dismissed Planned Production unavailability 2021-02-04T12:46:25+00:00 2021-05-19T00:00:00+01:00 2021-05-20T00:00:00+01:00 MW 755 0 755 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005882_002 Dismissed Planned Production unavailability 2021-05-07T15:29:03+01:00 2021-05-19T20:00:00+01:00 2021-05-20T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005882_001 Dismissed Planned Production unavailability 2021-03-19T17:41:47+00:00 2021-05-19T20:00:00+01:00 2021-05-20T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005688_002 Dismissed Planned Production unavailability 2021-05-07T14:32:37+01:00 2021-05-20T07:00:00+01:00 2021-05-20T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005688_001 Dismissed Planned Production unavailability 2021-03-18T20:24:44+00:00 2021-05-20T07:00:00+01:00 2021-05-20T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006036_003 Dismissed Planned Production unavailability 2021-05-14T11:32:28+01:00 2021-04-12T09:00:00+01:00 2021-05-20T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006049_004 Inactive Unplanned Production unavailability 2021-05-20T18:01:53+01:00 2021-05-17T17:00:00+01:00 2021-05-20T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006049_003 Dismissed Unplanned Production unavailability 2021-05-19T16:09:59+01:00 2021-05-17T17:00:00+01:00 2021-05-20T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005883_002 Dismissed Planned Production unavailability 2021-05-07T15:29:39+01:00 2021-05-20T09:00:00+01:00 2021-05-20T17:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005883_001 Dismissed Planned Production unavailability 2021-03-19T17:43:32+00:00 2021-05-20T09:00:00+01:00 2021-05-20T17:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005690_002 Dismissed Planned Production unavailability 2021-05-07T14:33:05+01:00 2021-05-20T17:00:00+01:00 2021-05-20T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005690_001 Dismissed Planned Production unavailability 2021-03-18T20:26:06+00:00 2021-05-20T17:00:00+01:00 2021-05-20T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005884_002 Dismissed Planned Production unavailability 2021-05-07T15:30:06+01:00 2021-05-20T20:00:00+01:00 2021-05-21T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005884_001 Dismissed Planned Production unavailability 2021-03-19T17:44:42+00:00 2021-05-20T20:00:00+01:00 2021-05-21T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005692_002 Dismissed Planned Production unavailability 2021-05-07T14:34:32+01:00 2021-05-21T07:00:00+01:00 2021-05-21T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005692_001 Dismissed Planned Production unavailability 2021-03-18T20:27:30+00:00 2021-05-21T07:00:00+01:00 2021-05-21T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000006054_004 Inactive Planned Production unavailability 2021-05-21T15:01:53+01:00 2021-05-21T02:00:00+01:00 2021-05-21T14:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000006054_003 Dismissed Planned Production unavailability 2021-05-20T12:33:05+01:00 2021-05-21T02:00:00+01:00 2021-05-21T14:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000006054_002 Dismissed Planned Production unavailability 2021-05-20T12:32:36+01:00 2021-05-21T02:00:00+01:00 2021-05-21T14:00:00+01:00 MW 0 710 710 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000006054_001 Dismissed Planned Production unavailability 2021-05-20T09:36:39+01:00 2021-05-21T02:00:00+01:00 2021-05-21T14:00:00+01:00 MW 340 370 710 Foreseen Maintenance
Testing
Fossil Gas 10YGB----------A
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006055_003 Dismissed Unplanned Production unavailability 2021-05-21T14:42:45+01:00 2021-05-20T17:05:00+01:00 2021-05-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006055_002 Dismissed Unplanned Production unavailability 2021-05-20T19:26:21+01:00 2021-05-20T17:05:00+01:00 2021-05-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006055_001 Dismissed Unplanned Production unavailability 2021-05-20T19:23:38+01:00 2021-05-20T17:00:00+01:00 2021-05-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005885_002 Dismissed Planned Production unavailability 2021-05-07T15:31:55+01:00 2021-05-21T09:00:00+01:00 2021-05-21T17:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005885_001 Dismissed Planned Production unavailability 2021-03-19T17:47:19+00:00 2021-05-21T09:00:00+01:00 2021-05-21T17:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005695_002 Dismissed Planned Production unavailability 2021-05-07T14:35:11+01:00 2021-05-21T17:00:00+01:00 2021-05-21T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005695_001 Dismissed Planned Production unavailability 2021-03-18T20:28:57+00:00 2021-05-21T17:00:00+01:00 2021-05-21T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000006052_002 Dismissed Planned Production unavailability 2021-05-20T08:59:36+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00 MW 800 380 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000006052_001 Dismissed Planned Production unavailability 2021-05-18T10:36:28+01:00 2021-05-19T08:00:00+01:00 2021-05-21T23:00:00+01:00 MW 780 400 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
TB2 47W000000000208P
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005100_002 Dismissed Planned Production unavailability 2020-11-24T11:00:34+00:00 2021-05-15T00:00:00+01:00 2021-05-22T00:00:00+01:00 MW 54 0 54 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
TB2 47W000000000208P
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005100_001 Dismissed Planned Production unavailability 2020-03-31T11:30:42+01:00 2021-05-15T00:00:00+01:00 2021-05-22T00:00:00+01:00 MW 54 0 54 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
TB1 47W000000000207R
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005099_002 Dismissed Planned Production unavailability 2020-11-24T11:00:34+00:00 2021-05-15T00:00:00+01:00 2021-05-22T00:00:00+01:00 MW 54 0 54 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
TB1 47W000000000207R
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005099_001 Dismissed Planned Production unavailability 2020-03-31T11:29:13+01:00 2021-05-15T00:00:00+01:00 2021-05-22T00:00:00+01:00 MW 54 0 54 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005886_002 Dismissed Planned Production unavailability 2021-05-07T15:33:10+01:00 2021-05-21T20:00:00+01:00 2021-05-22T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Grid
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005886_001 Dismissed Planned Production unavailability 2021-03-19T17:49:06+00:00 2021-05-21T20:00:00+01:00 2021-05-22T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Grid
Hydro Water Reservoir 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005697_002 Dismissed Planned Production unavailability 2021-05-07T14:36:23+01:00 2021-05-22T07:00:00+01:00 2021-05-22T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005697_001 Dismissed Planned Production unavailability 2021-03-18T20:30:19+00:00 2021-05-22T07:00:00+01:00 2021-05-22T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006036_004 Dismissed Planned Production unavailability 2021-05-18T12:47:07+01:00 2021-04-12T09:00:00+01:00 2021-05-22T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Outage Overrun
Fossil Gas 10Y1001A1001A59C
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005887_002 Dismissed Planned Production unavailability 2021-05-07T15:34:02+01:00 2021-05-22T09:00:00+01:00 2021-05-22T17:00:00+01:00 MW 0 100 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005887_001 Dismissed Planned Production unavailability 2021-03-19T17:58:13+00:00 2021-05-22T09:00:00+01:00 2021-05-22T17:00:00+01:00 MW 0 100 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000006058_003 Dismissed Unplanned Production unavailability 2021-05-22T18:24:19+01:00 2021-05-22T15:01:00+01:00 2021-05-22T20:00:00+01:00 MW 405 350 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000006058_002 Dismissed Unplanned Production unavailability 2021-05-22T18:08:28+01:00 2021-05-22T15:01:00+01:00 2021-05-22T20:00:00+01:00 MW 640 115 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000006058_001 Dismissed Unplanned Production unavailability 2021-05-22T15:04:19+01:00 2021-05-22T15:01:00+01:00 2021-05-22T20:00:00+01:00 MW 405 350 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005698_002 Dismissed Planned Production unavailability 2021-05-07T14:36:46+01:00 2021-05-22T17:00:00+01:00 2021-05-22T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_BHLAW-1 48W00000BHLAW-15
SSE GENERATION
48X000000000077M 0000000000000000000005698_001 Dismissed Planned Production unavailability 2021-03-18T20:32:01+00:00 2021-05-22T17:00:00+01:00 2021-05-22T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000006052_004 Inactive Planned Production unavailability 2021-05-23T00:01:54+01:00 2021-05-19T08:00:00+01:00 2021-05-22T23:00:00+01:00 MW 800 380 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000006052_003 Dismissed Planned Production unavailability 2021-05-20T11:04:15+01:00 2021-05-19T08:00:00+01:00 2021-05-22T23:00:00+01:00 MW 800 380 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000006058_004 Dismissed Unplanned Production unavailability 2021-05-22T19:46:05+01:00 2021-05-22T15:01:00+01:00 2021-05-22T23:30:00+01:00 MW 405 350 755 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005888_002 Dismissed Planned Production unavailability 2021-05-07T15:35:11+01:00 2021-05-22T20:00:00+01:00 2021-05-23T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A
T_GLNDO-1 48W00000GLNDO-1G
SSE GENERATION
48X000000000077M 0000000000000000000005888_001 Dismissed Planned Production unavailability 2021-03-19T17:59:03+00:00 2021-05-22T20:00:00+01:00 2021-05-23T07:00:00+01:00 MW 100 0 100 Foreseen Maintenance
Planned Outage
Hydro Water Reservoir 10YGB----------A