Last update at: 2023-09-26T18:00:00+01:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 3 4 5 6 7 > | ||||||||||||||||||
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008180_003 | Inactive | Planned | Consumption unavailability | 2023-06-09T09:02:31+01:00 | 2023-06-08T14:30:00+01:00 | 2023-06-09T08:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008181_002 | Inactive | Planned | Consumption unavailability | 2023-06-09T00:02:32+01:00 | 2023-06-08T16:00:00+01:00 | 2023-06-08T23:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008175_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008176_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 358 | 0 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008171_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 300 | 0 | 300 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008172_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008173_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008174_004 | Inactive | Planned | Production unavailability | 2023-06-07T18:02:32+01:00 | 2023-06-07T07:00:00+01:00 | 2023-06-07T17:00:00+01:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008177_002 | Inactive | Unplanned | Production unavailability | 2023-06-06T07:47:32+01:00 | 2023-06-06T04:36:00+01:00 | 2023-06-06T06:36:00+01:00 | MW | 710 | 0 | 710 | Failure | Plant Fault - HRSG |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008170_002 | Inactive | Planned | Production unavailability | 2023-06-05T08:32:32+01:00 | 2023-06-05T06:13:00+01:00 | 2023-06-05T07:28:00+01:00 | MW | 610 | 230 | 840 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_KEAD-2 | 48W000000KEAD-23 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008123_003 | Inactive | Planned | Production unavailability | 2023-06-04T22:02:31+01:00 | 2023-06-02T23:59:00+01:00 | 2023-06-04T21:00:00+01:00 | MW | 840 | 0 | 840 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008169_002 | Inactive | Unplanned | Production unavailability | 2023-06-04T18:47:31+01:00 | 2023-06-04T16:30:00+01:00 | 2023-06-04T17:47:00+01:00 | MW | 632 | 78 | 710 | Foreseen Maintenance | Plant Fault - Control System |
Fossil Gas | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008166_003 | Inactive | Planned | Production unavailability | 2023-05-31T13:02:32+01:00 | 2023-05-31T10:00:00+01:00 | 2023-05-31T12:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Grid |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008167_003 | Inactive | Planned | Consumption unavailability | 2023-05-31T13:02:32+01:00 | 2023-05-31T10:00:00+01:00 | 2023-05-31T12:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Grid |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008164_003 | Inactive | Planned | Production unavailability | 2023-05-31T13:02:32+01:00 | 2023-05-31T10:00:00+01:00 | 2023-05-31T12:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Grid |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008165_003 | Inactive | Planned | Consumption unavailability | 2023-05-31T13:02:32+01:00 | 2023-05-31T10:00:00+01:00 | 2023-05-31T12:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Grid |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008148_003 | Inactive | Planned | Production unavailability | 2023-05-31T07:02:32+01:00 | 2023-05-26T12:30:00+01:00 | 2023-05-31T05:59:00+01:00 | MW | 80 | 60 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008162_002 | Inactive | Planned | Production unavailability | 2023-05-30T17:32:31+01:00 | 2023-05-30T09:30:00+01:00 | 2023-05-30T16:30:00+01:00 | MW | 710 | 0 | 710 | Foreseen Maintenance | Maintenance |
Fossil Gas | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008159_003 | Inactive | Planned | Consumption unavailability | 2023-05-29T10:02:31+01:00 | 2023-05-28T15:15:00+01:00 | 2023-05-29T09:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008127_008 | Inactive | Unplanned | Production unavailability | 2023-05-28T13:32:32+01:00 | 2023-05-16T10:56:00+01:00 | 2023-05-28T12:29:00+01:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008157_005 | Inactive | Planned | Consumption unavailability | 2023-05-28T08:32:32+01:00 | 2023-05-27T16:00:00+01:00 | 2023-05-28T07:30:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008158_004 | Inactive | Planned | Consumption unavailability | 2023-05-28T02:02:32+01:00 | 2023-05-27T18:30:00+01:00 | 2023-05-28T01:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008128_008 | Inactive | Planned | Production unavailability | 2023-05-26T14:02:32+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 28 | 330 | 358 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008143_006 | Inactive | Planned | Production unavailability | 2023-05-26T14:02:32+01:00 | 2023-05-21T12:01:00+01:00 | 2023-05-26T12:59:00+01:00 | MW | 100 | 40 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008126_008 | Inactive | Unplanned | Production unavailability | 2023-05-26T13:32:32+01:00 | 2023-05-16T12:29:00+01:00 | 2023-05-26T12:29:00+01:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008146_002 | Inactive | Planned | Consumption unavailability | 2023-05-24T16:02:32+01:00 | 2023-05-24T04:45:00+01:00 | 2023-05-24T15:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008147_003 | Inactive | Planned | Consumption unavailability | 2023-05-24T12:02:32+01:00 | 2023-05-24T04:30:00+01:00 | 2023-05-24T11:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008129_004 | Inactive | Planned | Production unavailability | 2023-05-23T15:02:32+01:00 | 2023-05-16T13:20:00+01:00 | 2023-05-23T13:59:00+01:00 | MW | 0 | 80 | 80 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008137_006 | Inactive | Planned | Production unavailability | 2023-05-22T01:02:32+01:00 | 2023-05-17T22:00:00+01:00 | 2023-05-22T00:01:00+01:00 | MW | 405 | 350 | 755 | Failure | Plant Fault - Boiler |
Fossil Gas | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008142_002 | Inactive | Planned | Production unavailability | 2023-05-21T13:02:32+01:00 | 2023-04-06T16:01:00+01:00 | 2023-05-21T12:00:00+01:00 | MW | 60 | 80 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_GRGBW-2 | 48W00000GRGBW-2T | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008141_003 | Inactive | Unplanned | Production unavailability | 2023-05-19T16:32:31+01:00 | 2023-05-18T20:00:00+01:00 | 2023-05-19T15:30:00+01:00 | MW | 131 | 34 | 165 | Failure | Outage Overrun |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008136_003 | Inactive | Planned | Production unavailability | 2023-05-19T13:02:32+01:00 | 2023-04-06T16:01:00+01:00 | 2023-05-19T12:00:00+01:00 | MW | 80 | 80 | 160 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008100_002 | Inactive | Planned | Production unavailability | 2023-05-18T21:02:32+01:00 | 2023-05-18T06:00:00+01:00 | 2023-05-18T20:00:00+01:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_GRGBW-2 | 48W00000GRGBW-2T | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008101_002 | Inactive | Planned | Production unavailability | 2023-05-18T21:02:32+01:00 | 2023-05-18T06:00:00+01:00 | 2023-05-18T20:00:00+01:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_GRGBW-3 | 48W00000GRGBW-3R | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008102_002 | Inactive | Planned | Production unavailability | 2023-05-18T21:02:32+01:00 | 2023-05-18T06:00:00+01:00 | 2023-05-18T20:00:00+01:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008138_003 | Inactive | Unplanned | Consumption unavailability | 2023-05-17T20:32:32+01:00 | 2023-05-17T14:42:00+01:00 | 2023-05-17T19:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Control System |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008139_003 | Inactive | Unplanned | Production unavailability | 2023-05-17T20:32:32+01:00 | 2023-05-17T14:42:00+01:00 | 2023-05-17T19:30:00+01:00 | MW | 150 | 0 | 150 | Failure | Plant Fault - Control System |
Hydro Pumped Storage | 10YGB----------A |
T_GRGBW-1 | 48W00000GRGBW-1V | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008098_002 | Inactive | Planned | Production unavailability | 2023-05-16T21:02:32+01:00 | 2023-05-16T06:00:00+01:00 | 2023-05-16T20:00:00+01:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_GRGBW-2 | 48W00000GRGBW-2T | Greater Gabbard Offshore Winds Limited |
48X000000000331Y | 0000000000000000000008099_002 | Inactive | Planned | Production unavailability | 2023-05-16T21:02:32+01:00 | 2023-05-16T06:00:00+01:00 | 2023-05-16T20:00:00+01:00 | MW | 165 | 0 | 165 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008125_002 | Inactive | Planned | Production unavailability | 2023-05-16T01:02:32+01:00 | 2023-04-23T14:01:00+01:00 | 2023-05-15T23:59:00+01:00 | MW | 148 | 210 | 358 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008087_002 | Inactive | Planned | Production unavailability | 2023-05-15T13:02:32+01:00 | 2023-04-06T16:01:00+01:00 | 2023-05-15T12:00:00+01:00 | MW | 80 | 80 | 160 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008047_004 | Inactive | Planned | Production unavailability | 2023-05-15T07:02:32+01:00 | 2023-04-06T08:01:00+01:00 | 2023-05-15T05:59:00+01:00 | MW | 60 | 80 | 140 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008085_004 | Inactive | Planned | Production unavailability | 2023-05-11T13:02:32+01:00 | 2023-04-23T12:01:00+01:00 | 2023-05-11T12:00:00+01:00 | MW | 148 | 210 | 358 | Foreseen Maintenance | Commissioning |
Wind Offshore | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008117_004 | Inactive | Planned | Consumption unavailability | 2023-05-08T19:02:32+01:00 | 2023-05-08T04:00:00+01:00 | 2023-05-08T18:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000008116_003 | Inactive | Planned | Production unavailability | 2023-05-07T15:02:32+01:00 | 2023-05-07T11:30:00+01:00 | 2023-05-07T14:00:00+01:00 | MW | 100 | 0 | 100 | Failure | Testing |
Hydro Water Reservoir | 10YGB----------A |
T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000008108_005 | Inactive | Unplanned | Production unavailability | 2023-05-07T12:32:31+01:00 | 2023-05-02T13:01:00+01:00 | 2023-05-07T11:30:00+01:00 | MW | 100 | 0 | 100 | Failure | Plant Fault - Electrical Equipment |
Hydro Water Reservoir | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008114_003 | Inactive | Unplanned | Consumption unavailability | 2023-05-06T11:02:32+01:00 | 2023-05-05T13:50:00+01:00 | 2023-05-06T10:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008115_004 | Inactive | Planned | Consumption unavailability | 2023-05-06T06:32:32+01:00 | 2023-05-05T16:00:00+01:00 | 2023-05-06T05:30:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
T_KEAD-1 | 48W000000KEAD-15 | KEADBY GEN. LTD |
48X000000000073U | 0000000000000000000008113_006 | Inactive | Planned | Production unavailability | 2023-05-05T11:02:32+01:00 | 2023-05-05T07:41:00+01:00 | 2023-05-05T10:00:00+01:00 | MW | 755 | 0 | 755 | Failure | Plant Fault - Turbine |
Fossil Gas | 10YGB----------A |
T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008111_003 | Inactive | Unplanned | Consumption unavailability | 2023-05-05T11:02:32+01:00 | 2023-05-04T18:09:00+01:00 | 2023-05-05T10:00:00+01:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |