Last update at: 2025-12-10T12:30:00+00:00
**Please note that the last update time shown is rounded to the next market interval of 30 minutes
All times are in UTC.
| Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 2 3 4 5 > | ||||||||||||||||||
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010701_001 | Inactive | Planned | Production unavailability | 2025-11-25T13:37:17+00:00 | 2025-11-29T13:36:29+00:00 | 2025-11-30T13:36:36+00:00 | MW | 0 | 300 | 300 | Foreseen Maintenance | Testing |
Wind Offshore | 10YGB----------A |
| T_GRIFW-2 | 48W00000GRIFW-2Y | Griffin Wind Farm Limited |
48X000000000072W | 0000000000000000000010698_003 | Inactive | Planned | Production unavailability | 2025-11-24T17:02:32+00:00 | 2025-11-24T14:33:00+00:00 | 2025-11-24T15:50:00+00:00 | MW | 102 | 0 | 102 | Foreseen Maintenance | Maintenance |
Wind Onshore | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010695_004 | Inactive | Planned | Consumption unavailability | 2025-11-22T12:02:32+00:00 | 2025-11-21T16:15:00+00:00 | 2025-11-22T11:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010694_004 | Inactive | Planned | Consumption unavailability | 2025-11-22T10:32:32+00:00 | 2025-11-21T15:00:00+00:00 | 2025-11-22T09:30:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010685_006 | Inactive | Unplanned | Production unavailability | 2025-11-18T16:32:32+00:00 | 2025-11-15T15:00:00+00:00 | 2025-11-18T15:25:00+00:00 | MW | 100 | 200 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010682_003 | Inactive | Planned | Production unavailability | 2025-11-15T16:02:32+00:00 | 2025-11-15T07:30:00+00:00 | 2025-11-15T15:00:00+00:00 | MW | 300 | 0 | 300 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010683_003 | Inactive | Planned | Production unavailability | 2025-11-15T16:02:32+00:00 | 2025-11-15T07:30:00+00:00 | 2025-11-15T15:00:00+00:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010684_003 | Inactive | Planned | Production unavailability | 2025-11-15T15:18:51+00:00 | 2025-11-15T15:00:00+00:00 | 2025-11-16T16:00:00+00:00 | MW | 100 | 200 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010680_007 | Inactive | Planned | Consumption unavailability | 2025-11-15T13:02:31+00:00 | 2025-11-13T04:20:35+00:00 | 2025-11-15T12:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010681_009 | Inactive | Planned | Consumption unavailability | 2025-11-15T12:17:31+00:00 | 2025-11-13T05:00:34+00:00 | 2025-11-15T11:05:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010650_011 | Inactive | Planned | Production unavailability | 2025-11-12T23:02:32+00:00 | 2025-11-05T06:00:38+00:00 | 2025-11-12T22:00:54+00:00 | MW | 300 | 0 | 300 | Failure | Grid |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010651_010 | Inactive | Planned | Production unavailability | 2025-11-12T23:02:32+00:00 | 2025-11-05T06:00:56+00:00 | 2025-11-12T22:00:07+00:00 | MW | 80 | 0 | 80 | Failure | Grid |
Wind Offshore | 10YGB----------A |
| T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009674_007 | Inactive | Planned | Production unavailability | 2025-11-07T17:02:32+00:00 | 2025-11-07T06:00:00+00:00 | 2025-11-07T16:00:00+00:00 | MW | 358 | 0 | 358 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009671_006 | Inactive | Planned | Production unavailability | 2025-11-06T17:02:32+00:00 | 2025-11-06T06:00:00+00:00 | 2025-11-06T16:00:00+00:00 | MW | 160 | 0 | 160 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009673_006 | Inactive | Planned | Production unavailability | 2025-11-06T17:02:32+00:00 | 2025-11-06T06:00:00+00:00 | 2025-11-06T16:00:00+00:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000009672_006 | Inactive | Planned | Production unavailability | 2025-11-06T17:02:32+00:00 | 2025-11-06T06:00:00+00:00 | 2025-11-06T16:00:00+00:00 | MW | 140 | 0 | 140 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010666_007 | Inactive | Planned | Consumption unavailability | 2025-11-05T13:32:31+00:00 | 2025-11-03T12:00:00+00:00 | 2025-11-05T12:30:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010667_007 | Inactive | Planned | Consumption unavailability | 2025-11-05T13:32:31+00:00 | 2025-11-03T12:00:00+00:00 | 2025-11-05T12:30:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010665_003 | Inactive | Planned | Consumption unavailability | 2025-11-03T07:32:32+00:00 | 2025-11-02T16:30:09+00:00 | 2025-11-03T06:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010664_003 | Inactive | Planned | Consumption unavailability | 2025-11-03T07:32:32+00:00 | 2025-11-02T13:00:52+00:00 | 2025-11-03T06:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010661_002 | Inactive | Planned | Consumption unavailability | 2025-11-02T01:02:32+00:00 | 2025-11-01T15:00:44+00:00 | 2025-11-01T23:59:01+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010662_002 | Inactive | Planned | Consumption unavailability | 2025-11-02T01:02:32+00:00 | 2025-11-01T16:05:21+00:00 | 2025-11-01T23:59:26+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010657_004 | Inactive | Planned | Consumption unavailability | 2025-11-01T10:02:31+00:00 | 2025-10-31T09:15:00+00:00 | 2025-11-01T09:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010659_004 | Inactive | Planned | Consumption unavailability | 2025-11-01T10:02:31+00:00 | 2025-10-31T11:00:00+00:00 | 2025-11-01T09:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010654_003 | Inactive | Planned | Production unavailability | 2025-10-31T14:47:32+00:00 | 2025-10-31T13:00:50+00:00 | 2025-10-31T13:45:01+00:00 | MW | 320 | 38 | 358 | Shutdown | Testing |
Wind Offshore | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010653_004 | Inactive | Planned | Production unavailability | 2025-10-31T14:02:32+00:00 | 2025-10-31T12:10:16+00:00 | 2025-10-31T13:00:02+00:00 | MW | 270 | 30 | 300 | Shutdown | Testing |
Wind Offshore | 10YGB----------A |
| Yellow River | 47W0000000004914 | SSE Airtricity Limited |
23X--140207ALT-9 | 0000000000000000000010639_006 | Inactive | Unplanned | Production unavailability | 2025-10-30T19:02:32+00:00 | 2025-10-24T12:03:00+00:00 | 2025-10-30T18:00:00+00:00 | MW | 101 | 0 | 101 | Failure | Grid |
Wind Onshore | 10Y1001A1001A59C |
| T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000010385_003 | Inactive | Planned | Production unavailability | 2025-10-28T13:02:32+00:00 | 2025-10-28T09:00:00+00:00 | 2025-10-28T12:00:00+00:00 | MW | 100 | 0 | 100 | Foreseen Maintenance | Maintenance |
Hydro Water Reservoir | 10YGB----------A |
| T_VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000010616_005 | Inactive | Planned | Production unavailability | 2025-10-27T20:02:31+00:00 | 2025-10-27T08:00:00+00:00 | 2025-10-27T19:00:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010645_004 | Inactive | Planned | Consumption unavailability | 2025-10-27T18:02:31+00:00 | 2025-10-27T02:00:02+00:00 | 2025-10-27T17:00:17+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010644_004 | Inactive | Planned | Consumption unavailability | 2025-10-27T18:02:31+00:00 | 2025-10-27T01:00:35+00:00 | 2025-10-27T17:00:42+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010640_006 | Inactive | Planned | Consumption unavailability | 2025-10-26T16:32:31+00:00 | 2025-10-25T07:25:40+00:00 | 2025-10-26T15:30:47+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010641_005 | Inactive | Planned | Consumption unavailability | 2025-10-26T16:32:31+00:00 | 2025-10-25T10:00:54+00:00 | 2025-10-26T15:30:06+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010638_003 | Inactive | Planned | Production unavailability | 2025-10-24T02:32:32+00:00 | 2025-10-23T19:01:39+00:00 | 2025-10-24T01:30:52+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000010635_004 | Inactive | Unplanned | Production unavailability | 2025-10-22T13:17:31+00:00 | 2025-10-22T10:28:39+00:00 | 2025-10-22T12:05:47+00:00 | MW | 100 | 0 | 100 | Failure | Plant Fault - Generator |
Hydro Water Reservoir | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010457_004 | Inactive | Planned | Production unavailability | 2025-10-22T12:32:31+00:00 | 2025-10-22T10:00:00+00:00 | 2025-10-22T11:30:46+00:00 | MW | 300 | 0 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010458_004 | Inactive | Planned | Production unavailability | 2025-10-22T12:32:31+00:00 | 2025-10-22T10:00:53+00:00 | 2025-10-22T11:30:09+00:00 | MW | 160 | 0 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010460_004 | Inactive | Planned | Production unavailability | 2025-10-22T12:32:31+00:00 | 2025-10-22T10:00:00+00:00 | 2025-10-22T11:30:00+00:00 | MW | 358 | 0 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010459_004 | Inactive | Planned | Production unavailability | 2025-10-22T12:32:31+00:00 | 2025-10-22T10:00:00+00:00 | 2025-10-22T11:30:10+00:00 | MW | 140 | 0 | 140 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_GLNDO-1 | 48W00000GLNDO-1G | SSE GENERATION |
48X000000000077M | 0000000000000000000010630_003 | Inactive | Unplanned | Production unavailability | 2025-10-21T07:32:32+00:00 | 2025-10-21T00:35:32+00:00 | 2025-10-21T06:30:46+00:00 | MW | 100 | 0 | 100 | Failure | Plant Fault - Electrical Equipment |
Hydro Water Reservoir | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010627_004 | Inactive | Planned | Consumption unavailability | 2025-10-20T18:17:32+00:00 | 2025-10-19T20:00:40+00:00 | 2025-10-20T17:15:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010628_004 | Inactive | Planned | Consumption unavailability | 2025-10-20T18:17:32+00:00 | 2025-10-20T00:30:29+00:00 | 2025-10-20T17:15:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000010617_005 | Inactive | Planned | Production unavailability | 2025-10-19T06:02:32+00:00 | 2025-10-17T18:00:40+00:00 | 2025-10-19T05:00:50+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010619_005 | Inactive | Planned | Production unavailability | 2025-10-19T05:02:31+00:00 | 2025-10-17T19:30:39+00:00 | 2025-10-19T04:00:54+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010605_007 | Inactive | Unplanned | Production unavailability | 2025-10-14T20:32:31+00:00 | 2025-10-13T21:30:24+00:00 | 2025-10-14T19:30:00+00:00 | MW | 300 | 0 | 300 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010606_007 | Inactive | Unplanned | Production unavailability | 2025-10-14T20:32:31+00:00 | 2025-10-13T21:30:36+00:00 | 2025-10-14T19:30:00+00:00 | MW | 80 | 0 | 80 | Failure | Plant Fault - Auxiliary Equipment |
Wind Offshore | 10YGB----------A |
| T_SGRWO-1 | 48W00000SGRWO-1L | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010463_006 | Inactive | Planned | Production unavailability | 2025-10-13T22:32:31+00:00 | 2025-10-13T08:00:00+00:00 | 2025-10-13T21:30:00+00:00 | MW | 300 | 0 | 300 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_SGRWO-2 | 48W00000SGRWO-2J | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000010464_005 | Inactive | Planned | Production unavailability | 2025-10-13T21:32:31+00:00 | 2025-10-13T08:00:00+00:00 | 2025-10-13T20:30:00+00:00 | MW | 80 | 0 | 80 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_BHLAW-1 | 48W00000BHLAW-15 | SSE GENERATION |
48X000000000077M | 0000000000000000000010553_007 | Inactive | Planned | Production unavailability | 2025-10-13T14:32:31+00:00 | 2025-10-13T10:00:00+00:00 | 2025-10-13T13:30:00+00:00 | MW | 108 | 0 | 108 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000010600_002 | Inactive | Planned | Consumption unavailability | 2025-10-13T13:02:31+00:00 | 2025-10-13T05:30:05+00:00 | 2025-10-13T12:00:13+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |