Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 2 3 4 5 6 >
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003937_003 Dismissed Unplanned Production unavailability 2018-08-30T17:29:29+01:00 2018-08-30T14:45:00+01:00 2018-08-30T18:00:00+01:00 MW 250 930 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003937_002 Dismissed Unplanned Production unavailability 2018-08-30T17:03:14+01:00 2018-08-30T14:45:00+01:00 2018-08-30T17:30:00+01:00 MW 330 850 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003937_001 Dismissed Unplanned Production unavailability 2018-08-30T16:12:40+01:00 2018-08-30T14:45:00+01:00 2018-08-30T17:00:00+01:00 MW 400 780 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_007 Dismissed Planned Production unavailability 2018-08-30T16:13:00+01:00 2018-08-29T22:00:00+01:00 2018-08-30T16:13:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_006 Dismissed Planned Production unavailability 2018-08-30T15:36:04+01:00 2018-08-29T22:00:00+01:00 2018-08-30T16:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_005 Dismissed Planned Production unavailability 2018-08-30T15:21:19+01:00 2018-08-29T22:00:00+01:00 2018-08-30T16:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_004 Dismissed Planned Production unavailability 2018-08-30T13:03:51+01:00 2018-08-29T22:00:00+01:00 2018-08-30T14:45:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_003 Dismissed Planned Production unavailability 2018-08-29T20:38:06+01:00 2018-08-29T22:00:00+01:00 2018-08-30T17:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_002 Dismissed Planned Production unavailability 2018-08-29T20:18:05+01:00 2018-08-29T22:00:00+01:00 2018-08-30T15:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003936_001 Dismissed Planned Production unavailability 2018-08-29T19:56:36+01:00 2018-08-29T21:00:00+01:00 2018-08-30T15:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003935_003 Dismissed Unplanned Production unavailability 2018-08-30T14:27:48+01:00 2018-08-29T12:30:00+01:00 2018-08-30T14:30:00+01:00 MW 710 0 710 Failure
Plant Fault - Generator
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003935_002 Dismissed Unplanned Production unavailability 2018-08-29T21:17:25+01:00 2018-08-29T12:30:00+01:00 2018-08-30T20:00:00+01:00 MW 710 0 710 Failure
Plant Fault - Generator
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003935_001 Dismissed Unplanned Production unavailability 2018-08-29T12:37:19+01:00 2018-08-29T12:30:00+01:00 2018-08-29T23:59:00+01:00 MW 710 0 710 Failure
Plant Fault - Generator
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_008 Dismissed Unplanned Production unavailability 2018-08-29T09:57:33+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 480 700 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_007 Dismissed Unplanned Production unavailability 2018-08-29T09:55:05+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 520 660 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_006 Dismissed Unplanned Production unavailability 2018-08-29T09:42:54+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 650 530 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_005 Dismissed Unplanned Production unavailability 2018-08-29T09:13:26+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 680 500 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_004 Dismissed Unplanned Production unavailability 2018-08-29T09:02:46+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 750 430 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_003 Dismissed Unplanned Production unavailability 2018-08-29T08:42:41+01:00 2018-08-29T08:00:00+01:00 2018-08-29T10:00:00+01:00 MW 780 400 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_002 Dismissed Unplanned Production unavailability 2018-08-29T08:25:34+01:00 2018-08-29T08:00:00+01:00 2018-08-29T08:55:00+01:00 MW 810 370 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003934_001 Dismissed Unplanned Production unavailability 2018-08-29T08:17:29+01:00 2018-08-29T08:00:00+01:00 2018-08-29T08:30:00+01:00 MW 810 370 1180 Failure
Plant Fault - Electrical Equipment
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_008 Dismissed Planned Production unavailability 2018-08-28T10:48:17+01:00 2018-08-28T07:00:00+01:00 2018-08-29T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_007 Dismissed Planned Production unavailability 2018-08-28T10:47:56+01:00 2018-08-28T07:00:00+01:00 2018-08-29T08:00:00+01:00 MW 410 770 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_006 Dismissed Planned Production unavailability 2018-08-28T08:33:10+01:00 2018-08-28T07:00:00+01:00 2018-08-28T23:59:00+01:00 MW 410 770 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_005 Dismissed Planned Production unavailability 2018-08-28T08:07:41+01:00 2018-08-28T07:00:00+01:00 2018-08-28T08:30:00+01:00 MW 410 770 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_004 Dismissed Planned Production unavailability 2018-08-28T07:51:30+01:00 2018-08-28T07:00:00+01:00 2018-08-28T08:30:00+01:00 MW 550 630 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_003 Dismissed Planned Production unavailability 2018-08-28T07:04:47+01:00 2018-08-28T07:00:00+01:00 2018-08-28T08:30:00+01:00 MW 630 550 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_002 Dismissed Planned Production unavailability 2018-08-27T21:11:21+01:00 2018-08-27T08:00:00+01:00 2018-08-28T08:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003930_001 Dismissed Planned Production unavailability 2018-08-24T13:44:58+01:00 2018-08-27T08:00:00+01:00 2018-09-01T21:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_009 Dismissed Planned Production unavailability 2018-08-27T16:33:54+01:00 2018-08-27T13:30:00+01:00 2018-08-27T16:50:00+01:00 MW 480 700 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_008 Dismissed Planned Production unavailability 2018-08-27T16:17:21+01:00 2018-08-27T13:30:00+01:00 2018-08-27T16:30:00+01:00 MW 520 660 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_007 Dismissed Planned Production unavailability 2018-08-27T15:55:03+01:00 2018-08-27T13:30:00+01:00 2018-08-27T16:10:00+01:00 MW 580 600 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_006 Dismissed Planned Production unavailability 2018-08-27T15:24:12+01:00 2018-08-27T13:30:00+01:00 2018-08-27T15:50:00+01:00 MW 620 560 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_005 Dismissed Planned Production unavailability 2018-08-27T14:58:41+01:00 2018-08-27T13:30:00+01:00 2018-08-27T15:15:00+01:00 MW 700 480 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_004 Dismissed Planned Production unavailability 2018-08-27T14:46:36+01:00 2018-08-27T13:30:00+01:00 2018-08-27T15:15:00+01:00 MW 765 415 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_003 Dismissed Planned Production unavailability 2018-08-27T14:27:04+01:00 2018-08-27T13:30:00+01:00 2018-08-27T14:45:00+01:00 MW 810 370 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_002 Dismissed Planned Production unavailability 2018-08-27T14:05:31+01:00 2018-08-27T13:30:00+01:00 2018-08-27T14:15:00+01:00 MW 810 370 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003931_001 Dismissed Planned Production unavailability 2018-08-27T13:06:31+01:00 2018-08-27T13:30:00+01:00 2018-08-27T14:00:00+01:00 MW 810 370 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_008 Dismissed Planned Production unavailability 2018-08-24T13:49:25+01:00 2018-08-25T23:01:00+01:00 2018-08-27T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Operational Activities
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_007 Dismissed Planned Production unavailability 2018-07-16T14:22:42+01:00 2018-08-25T23:01:00+01:00 2018-08-30T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_006 Dismissed Planned Production unavailability 2018-07-10T11:19:39+01:00 2018-08-25T23:01:00+01:00 2018-08-30T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_005 Dismissed Planned Production unavailability 2018-03-02T12:12:35+00:00 2018-08-24T23:01:00+01:00 2018-08-30T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_004 Dismissed Planned Production unavailability 2018-01-04T09:06:24+00:00 2018-08-24T23:01:00+01:00 2018-08-30T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_003 Dismissed Planned Production unavailability 2017-11-17T09:22:09+00:00 2018-09-07T23:01:00+01:00 2018-09-19T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_002 Dismissed Planned Production unavailability 2017-11-17T09:15:07+00:00 2018-09-07T23:01:00+01:00 2018-09-19T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003396_001 Dismissed Planned Production unavailability 2017-11-07T14:17:19+00:00 2018-09-07T23:01:00+01:00 2018-09-19T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003395_008 Dismissed Planned Production unavailability 2018-08-25T23:03:31+01:00 2018-08-10T23:01:00+01:00 2018-08-26T02:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Plant Fault - Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003395_007 Dismissed Planned Production unavailability 2018-07-16T14:22:42+01:00 2018-08-10T23:01:00+01:00 2018-08-25T23:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003395_006 Dismissed Planned Production unavailability 2018-07-10T11:18:45+01:00 2018-08-10T23:01:00+01:00 2018-08-25T23:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000003395_005 Dismissed Planned Production unavailability 2018-03-02T12:12:35+00:00 2018-08-10T23:01:00+01:00 2018-08-24T23:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A