This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2023-05-31T15:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 1 2 3 4 5 >
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_006 Dismissed Planned Production unavailability 2018-07-16T14:22:18+01:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_005 Dismissed Planned Production unavailability 2018-03-02T12:09:30+00:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_004 Dismissed Planned Production unavailability 2017-11-17T09:21:19+00:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_003 Dismissed Planned Production unavailability 2017-11-17T09:14:32+00:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_002 Dismissed Planned Production unavailability 2017-07-20T15:30:37+01:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000003169_001 Dismissed Planned Production unavailability 2017-04-07T13:49:56+01:00 2020-04-06T08:00:00+01:00 2020-06-12T16:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Maintenance
Hydro Pumped Storage 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_010 Dismissed Planned Production unavailability 2019-12-24T15:05:18+00:00 2020-05-14T23:00:00+01:00 2020-07-31T00:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
TB3 47W0000000000994
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005158_002 Inactive Unplanned Production unavailability 2020-06-02T10:02:44+01:00 2020-05-31T19:30:00+01:00 2020-06-02T09:00:00+01:00 MW 51 190 241 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
TB3 47W0000000000994
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005158_001 Dismissed Unplanned Production unavailability 2020-05-31T19:53:49+01:00 2020-05-31T19:30:00+01:00 2020-06-02T09:00:00+01:00 MW 51 190 241 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005030_002 Dismissed Planned Production unavailability 2020-04-29T12:01:29+01:00 2020-05-31T23:00:00+01:00 2020-06-30T23:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005030_001 Dismissed Planned Production unavailability 2020-02-11T10:19:21+00:00 2020-05-31T23:00:00+01:00 2020-06-30T23:00:00+01:00 MW 1180 0 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_BEATO-1 48W00000BEATO-1T
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005146_001 Dismissed Planned Production unavailability 2020-05-13T21:58:40+01:00 2020-06-01T08:00:00+01:00 2020-06-06T17:00:00+01:00 MW 126 0 126 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_BEATO-3 48W00000BEATO-3P
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005147_001 Dismissed Planned Production unavailability 2020-05-13T22:00:35+01:00 2020-06-01T08:00:00+01:00 2020-06-06T17:00:00+01:00 MW 168 0 168 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005160_003 Inactive Planned Production unavailability 2020-06-02T17:17:41+01:00 2020-06-02T08:00:00+01:00 2020-06-02T16:15:00+01:00 MW 400 780 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005160_002 Dismissed Planned Production unavailability 2020-06-02T16:01:21+01:00 2020-06-02T08:00:00+01:00 2020-06-02T16:15:00+01:00 MW 400 780 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005160_001 Dismissed Planned Production unavailability 2020-06-01T10:10:06+01:00 2020-06-02T08:00:00+01:00 2020-06-02T16:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Grid
Fossil Gas 10YGB----------A
TB3 47W0000000000994
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005155_002 Inactive Planned Production unavailability 2020-06-09T18:02:30+01:00 2020-06-02T09:00:00+01:00 2020-06-09T17:00:00+01:00 MW 241 0 241 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
TB3 47W0000000000994
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005155_001 Dismissed Planned Production unavailability 2020-05-27T10:22:53+01:00 2020-06-02T09:00:00+01:00 2020-06-09T17:00:00+01:00 MW 241 0 241 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
RHODE1 47W000000000212Y
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005161_002 Dismissed Unplanned Production unavailability 2020-06-02T22:29:36+01:00 2020-06-02T21:10:00+01:00 2020-06-03T10:00:00+01:00 MW 52 0 52 Failure
Plant Fault - Control System
Fossil Gas 10Y1001A1001A59C
RHODE1 47W000000000212Y
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005161_001 Dismissed Unplanned Production unavailability 2020-06-02T21:31:49+01:00 2020-06-02T21:10:00+01:00 2020-06-03T10:00:00+01:00 MW 52 0 52 Failure
Plant Fault - Control System
Fossil Gas 10Y1001A1001A59C
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_011 Dismissed Planned Production unavailability 2020-01-15T16:34:12+00:00 2020-06-04T23:00:00+01:00 2020-06-28T23:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005166_002 Inactive Unplanned Production unavailability 2020-06-05T16:47:38+01:00 2020-06-05T15:01:00+01:00 2020-06-05T15:40:00+01:00 MW 1040 140 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005166_001 Dismissed Unplanned Production unavailability 2020-06-05T15:02:08+01:00 2020-06-05T15:01:00+01:00 2020-06-05T15:40:00+01:00 MW 1040 140 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005167_002 Inactive Planned Production unavailability 2020-06-05T17:02:32+01:00 2020-06-05T15:40:00+01:00 2020-06-05T16:00:00+01:00 MW 990 190 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005167_001 Dismissed Planned Production unavailability 2020-06-05T15:40:10+01:00 2020-06-05T15:40:00+01:00 2020-06-05T16:00:00+01:00 MW 990 190 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005168_002 Inactive Unplanned Production unavailability 2020-06-05T19:02:32+01:00 2020-06-05T17:00:00+01:00 2020-06-05T17:50:00+01:00 MW 990 190 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000005168_001 Dismissed Unplanned Production unavailability 2020-06-05T17:01:54+01:00 2020-06-05T17:00:00+01:00 2020-06-05T17:50:00+01:00 MW 990 190 1180 Failure
Plant Fault - Control System
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_009 Dismissed Planned Production unavailability 2019-01-25T14:03:35+00:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_008 Dismissed Planned Production unavailability 2018-10-26T09:01:14+01:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_007 Dismissed Planned Production unavailability 2018-10-05T07:46:17+01:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_006 Dismissed Planned Production unavailability 2018-07-16T14:22:18+01:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_005 Dismissed Planned Production unavailability 2018-03-02T12:09:30+00:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_004 Dismissed Planned Production unavailability 2017-11-17T09:21:19+00:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_003 Dismissed Planned Production unavailability 2017-11-17T09:14:32+00:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_002 Dismissed Planned Production unavailability 2017-07-20T15:30:03+01:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_MEDP-1 48W000000MEDP-12
MEDWAY POWER LTD
48X000000000076O 0000000000000000000003181_001 Dismissed Planned Production unavailability 2017-05-08T11:49:57+01:00 2020-06-05T23:00:00+01:00 2020-07-19T12:00:00+01:00 MW 710 0 710 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_BEATO-4 48W00000BEATO-4N
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005149_001 Dismissed Planned Production unavailability 2020-05-13T22:03:44+01:00 2020-06-08T08:00:00+01:00 2020-06-13T17:00:00+01:00 MW 168 0 168 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_BEATO-2 48W00000BEATO-2R
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005148_001 Dismissed Planned Production unavailability 2020-05-13T22:02:28+01:00 2020-06-08T08:00:00+01:00 2020-06-13T17:00:00+01:00 MW 126 0 126 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_CLDNW-1 48W00000CLDNW-1Q
CLYDE WIND FARM
48X000000000071Y 0000000000000000000005169_002 Dismissed Planned Production unavailability 2020-06-11T10:01:31+01:00 2020-06-11T10:00:00+01:00 2020-06-11T11:00:00+01:00 MW 187 0 187 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_CLDNW-1 48W00000CLDNW-1Q
CLYDE WIND FARM
48X000000000071Y 0000000000000000000005169_001 Dismissed Planned Production unavailability 2020-06-11T09:48:04+01:00 2020-06-11T10:00:00+01:00 2020-06-11T11:00:00+01:00 MW 187 0 187 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005171_002 Inactive Unplanned Production unavailability 2020-06-12T13:05:14+01:00 2020-06-12T11:00:00+01:00 2020-06-12T13:00:00+01:00 MW 0 243 243 Failure
Plant Fault - Generator
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005171_001 Dismissed Unplanned Production unavailability 2020-06-12T11:55:03+01:00 2020-06-12T11:00:00+01:00 2020-06-12T13:00:00+01:00 MW 243 0 243 Failure
Plant Fault - Generator
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000004899_001 Dismissed Planned Production unavailability 2019-12-17T09:17:06+00:00 2020-06-14T00:00:00+01:00 2020-06-21T00:00:00+01:00 MW 243 0 243 Foreseen Maintenance
Planned Outage
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000003883_001 Dismissed Planned Production unavailability 2018-07-16T14:32:26+01:00 2020-06-14T00:00:00+01:00 2020-06-21T00:00:00+01:00 MW 243 0 243 Foreseen Maintenance
Planned Operational Activities
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005172_004 Inactive Unplanned Production unavailability 2020-06-26T17:21:31+01:00 2020-06-14T13:25:00+01:00 2020-06-26T17:00:00+01:00 MW 0 243 243 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005172_003 Dismissed Unplanned Production unavailability 2020-06-19T14:34:58+01:00 2020-06-14T13:25:00+01:00 2020-06-26T17:00:00+01:00 MW 243 0 243 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005172_002 Dismissed Unplanned Production unavailability 2020-06-18T16:28:11+01:00 2020-06-14T13:25:00+01:00 2020-06-22T17:00:00+01:00 MW 243 0 243 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
TB4 47W0000000001008
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005172_001 Dismissed Unplanned Production unavailability 2020-06-14T14:10:38+01:00 2020-06-14T13:25:00+01:00 2020-06-19T17:00:00+01:00 MW 243 0 243 Failure
Plant Fault - Boiler
Fossil Oil 10Y1001A1001A59C
T_BEATO-1 48W00000BEATO-1T
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005146_004 Inactive Planned Production unavailability 2020-06-21T11:32:32+01:00 2020-06-15T08:00:00+01:00 2020-06-21T10:20:00+01:00 MW 126 0 126 Foreseen Maintenance
Planned Outage
Wind Offshore 10YGB----------A
T_BEATO-3 48W00000BEATO-3P
Beatrice Offshore Windfarm
48X000000000208X 0000000000000000000005147_004 Inactive Planned Production unavailability 2020-06-21T11:32:32+01:00 2020-06-15T08:00:00+01:00 2020-06-21T10:20:00+01:00 MW 168 0 168 Foreseen Maintenance
Planned Outage