Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
1 2 3 4 5 >
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_010 Active Planned Production unavailability 2019-01-25T14:03:35+00:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_009 Dismissed Planned Production unavailability 2018-10-26T09:01:14+01:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_008 Dismissed Planned Production unavailability 2018-10-05T07:46:17+01:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_007 Dismissed Planned Production unavailability 2018-07-16T14:22:18+01:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_006 Dismissed Planned Production unavailability 2018-03-02T12:09:30+00:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_005 Dismissed Planned Production unavailability 2017-11-17T09:21:19+00:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_004 Dismissed Planned Production unavailability 2017-11-17T09:14:32+00:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_003 Dismissed Planned Production unavailability 2017-07-20T15:44:43+01:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-4 48W000000FERR-44
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001025_002 Dismissed Planned Production unavailability 2015-05-20T06:40:00+01:00 2015-05-20T07:00:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000001732_004 Dismissed Planned Production unavailability 2016-01-22T16:19:01+00:00 2016-01-01T00:00:00+00:00 2018-03-31T23:59:00+01:00 MW 780 400 1180 Shutdown
Maintenance
Fossil Gas 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_011 Active Planned Production unavailability 2019-01-25T14:03:35+00:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_010 Dismissed Planned Production unavailability 2018-10-26T09:01:14+01:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_009 Dismissed Planned Production unavailability 2018-10-05T07:46:17+01:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_008 Dismissed Planned Production unavailability 2018-07-16T14:22:18+01:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_007 Dismissed Planned Production unavailability 2018-03-02T12:09:30+00:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_006 Dismissed Planned Production unavailability 2017-11-17T09:21:19+00:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_005 Dismissed Planned Production unavailability 2017-11-17T09:14:32+00:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_004 Dismissed Planned Production unavailability 2017-07-20T15:43:47+01:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_003 Dismissed Planned Production unavailability 2016-02-17T12:41:04+00:00 2016-03-23T13:00:00+00:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_FERR-3 48W000000FERR-36
KEADBY GEN. LTD
48X000000000073U 0000000000000000000001023_002 Dismissed Planned Production unavailability 2015-05-20T06:42:19+01:00 2016-03-31T23:59:00+01:00 2050-01-01T00:00:00+00:00 MW 490 0 490 Shutdown
Maintenance
Fossil Hard coal 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000001732_007 Dismissed Planned Production unavailability 2016-10-13T10:55:11+01:00 2016-06-14T03:30:00+01:00 2018-03-31T23:59:00+01:00 MW 780 400 1180 Shutdown
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000001732_006 Dismissed Planned Production unavailability 2016-10-13T09:59:40+01:00 2016-06-14T03:30:00+01:00 2018-03-31T23:59:00+01:00 MW 780 400 1180 Shutdown
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000001732_005 Dismissed Planned Production unavailability 2016-06-13T11:11:38+01:00 2016-06-14T03:30:00+01:00 2018-03-31T23:59:00+01:00 MW 780 400 1180 Shutdown
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_004 Dismissed Planned Production unavailability 2017-05-05T11:53:58+01:00 2017-05-05T23:00:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_007 Dismissed Planned Production unavailability 2017-05-06T22:38:28+01:00 2017-05-06T22:59:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_005 Dismissed Planned Production unavailability 2017-05-05T21:30:08+01:00 2017-05-06T23:00:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_006 Dismissed Planned Production unavailability 2017-05-06T11:29:56+01:00 2017-05-06T23:59:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_008 Dismissed Planned Production unavailability 2017-05-06T23:46:12+01:00 2017-05-07T01:30:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_009 Dismissed Planned Production unavailability 2017-05-07T02:02:31+01:00 2017-05-07T02:30:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_010 Dismissed Planned Production unavailability 2017-05-07T02:43:44+01:00 2017-05-07T03:30:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_011 Dismissed Planned Production unavailability 2017-05-07T03:36:39+01:00 2017-05-07T04:00:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_013 Dismissed Planned Production unavailability 2017-05-07T04:18:55+01:00 2017-05-07T04:20:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_012 Dismissed Planned Production unavailability 2017-05-07T04:01:38+01:00 2017-05-07T04:30:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_003 Dismissed Planned Production unavailability 2017-03-23T14:50:31+00:00 2017-05-08T23:01:00+01:00 2018-03-31T23:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_002 Dismissed Planned Production unavailability 2016-11-15T15:05:28+00:00 2017-05-08T23:01:00+01:00 2018-09-16T22:59:00+01:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE GENERATION
48X000000000077M 0000000000000000000002940_001 Dismissed Planned Production unavailability 2016-11-02T12:09:25+00:00 2017-05-08T23:01:00+01:00 2019-12-02T00:00:00+00:00 MW 800 380 1180 Shutdown
Planned Outage
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003225_006 Dismissed Planned Production unavailability 2017-09-04T11:27:25+01:00 2017-07-06T23:59:00+01:00 2017-10-29T23:59:00+00:00 MW 405 350 755 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003225_014 Dismissed Planned Production unavailability 2017-09-18T15:04:02+01:00 2017-09-08T21:17:00+01:00 2017-10-23T08:00:00+01:00 MW 405 350 755 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_003 Dismissed Planned Production unavailability 2014-12-19T12:36:18+00:00 2017-09-25T08:00:00+01:00 2017-10-20T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Generator
Hydro Pumped Storage 10YGB----------A
T_FOYE-1 48W000000FOYE-14
SSE GENERATION
48X000000000077M 0000000000000000000001012_006 Dismissed Planned Production unavailability 2017-07-20T16:37:59+01:00 2017-10-02T08:00:00+01:00 2017-10-27T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Generator
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_012 Inactive Planned Production unavailability 2017-10-22T18:02:31+01:00 2017-10-07T20:25:00+01:00 2017-10-22T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Commissioning
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_011 Dismissed Planned Production unavailability 2017-10-22T16:57:09+01:00 2017-10-07T20:25:00+01:00 2017-10-22T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Commissioning
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_010 Dismissed Planned Production unavailability 2017-10-22T12:25:33+01:00 2017-10-07T20:25:00+01:00 2017-10-23T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Commissioning
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_009 Dismissed Planned Production unavailability 2017-10-07T20:13:56+01:00 2017-10-07T20:25:00+01:00 2017-10-23T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Generator
Hydro Pumped Storage 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_008 Dismissed Planned Production unavailability 2017-08-08T10:23:31+01:00 2017-10-08T08:00:00+01:00 2017-10-23T17:00:00+01:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Generator
Hydro Pumped Storage 10YGB----------A
T_FIDL-1 48W000000FIDL-16
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003338_003 Inactive Planned Production unavailability 2017-11-08T09:02:32+00:00 2017-10-12T00:00:00+01:00 2017-11-08T07:50:00+00:00 MW 485 0 485 Shutdown
Planned Operational Activities
Fossil Hard coal 10YGB----------A
T_FIDL-1 48W000000FIDL-16
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003338_002 Dismissed Planned Production unavailability 2017-11-08T07:47:59+00:00 2017-10-12T00:00:00+01:00 2017-11-08T07:50:00+00:00 MW 485 0 485 Shutdown
Planned Operational Activities
Fossil Hard coal 10YGB----------A
T_FIDL-1 48W000000FIDL-16
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003338_001 Dismissed Planned Production unavailability 2017-10-11T23:46:29+01:00 2017-10-12T00:00:00+01:00 2017-12-31T00:00:00+00:00 MW 485 0 485 Shutdown
Planned Operational Activities
Fossil Hard coal 10YGB----------A
T_FOYE-2 48W000000FOYE-22
SSE GENERATION
48X000000000077M 0000000000000000000001014_007 Dismissed Planned Production unavailability 2017-07-20T16:39:32+01:00 2017-10-15T08:00:00+01:00 2017-11-12T17:00:00+00:00 MW 150 0 150 Foreseen Maintenance
Plant Fault - Generator
Hydro Pumped Storage 10YGB----------A
T_KEAD-1 48W000000KEAD-15
KEADBY GEN. LTD
48X000000000073U 0000000000000000000003315_003 Dismissed Planned Production unavailability 2017-09-21T01:31:35+01:00 2017-10-16T00:00:00+01:00 2017-10-23T08:00:00+01:00 MW 405 350 755 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A