This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-05-11T17:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 7 8 9 10 11 >
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008325_003 Dismissed Planned Production unavailability 2023-08-18T19:17:29+01:00 2023-08-18T18:00:00+01:00 2023-08-18T20:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008325_002 Dismissed Planned Production unavailability 2023-08-18T14:51:55+01:00 2023-08-18T18:00:00+01:00 2023-08-20T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008325_001 Dismissed Planned Production unavailability 2023-08-18T13:26:35+01:00 2023-08-18T16:30:00+01:00 2023-08-20T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008313_004 Inactive Planned Production unavailability 2023-08-18T14:32:32+01:00 2023-08-17T15:00:00+01:00 2023-08-18T13:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008313_003 Dismissed Planned Production unavailability 2023-08-18T12:20:07+01:00 2023-08-17T15:00:00+01:00 2023-08-18T13:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008313_002 Dismissed Planned Production unavailability 2023-08-17T12:00:23+01:00 2023-08-17T15:00:00+01:00 2023-08-20T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008313_001 Dismissed Planned Production unavailability 2023-08-17T09:28:17+01:00 2023-08-18T08:00:00+01:00 2023-08-20T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008302_001 Dismissed Planned Production unavailability 2023-08-13T12:09:34+01:00 2023-08-16T08:00:00+01:00 2023-08-18T08:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008263_002 Dismissed Planned Production unavailability 2023-08-04T17:33:11+01:00 2023-08-18T23:00:00+01:00 2023-08-20T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008263_001 Dismissed Planned Production unavailability 2023-07-21T15:00:17+01:00 2023-08-11T09:00:00+01:00 2023-08-13T09:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008059_003 Inactive Planned Production unavailability 2023-04-03T14:32:32+01:00 2023-04-03T09:15:00+01:00 2023-04-03T13:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008059_002 Dismissed Planned Production unavailability 2023-04-03T13:23:48+01:00 2023-04-03T09:15:00+01:00 2023-04-03T13:30:00+01:00 MW 400 780 1180 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008059_001 Dismissed Planned Production unavailability 2023-04-03T09:11:18+01:00 2023-04-03T09:15:00+01:00 2023-04-03T20:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Maintenance
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008041_004 Inactive Unplanned Production unavailability 2023-03-27T11:17:32+01:00 2023-03-27T08:50:00+01:00 2023-03-27T10:10:00+01:00 MW 400 780 1180 Failure
Plant Fault - Fuel Supply
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008041_003 Dismissed Unplanned Production unavailability 2023-03-27T10:08:24+01:00 2023-03-27T08:50:00+01:00 2023-03-27T10:10:00+01:00 MW 400 780 1180 Failure
Plant Fault - Fuel Supply
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008041_002 Dismissed Unplanned Production unavailability 2023-03-27T09:36:47+01:00 2023-03-27T08:50:00+01:00 2023-03-27T10:00:00+01:00 MW 400 780 1180 Failure
Plant Fault - Fuel Supply
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000008041_001 Dismissed Unplanned Production unavailability 2023-03-27T08:53:28+01:00 2023-03-27T08:50:00+01:00 2023-03-27T11:00:00+01:00 MW 400 780 1180 Failure
Plant Fault - Fuel Supply
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007959_003 Inactive Unplanned Production unavailability 2023-02-16T07:32:32+00:00 2023-02-15T22:50:00+00:00 2023-02-16T06:30:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007959_002 Dismissed Unplanned Production unavailability 2023-02-16T04:59:47+00:00 2023-02-15T22:50:00+00:00 2023-02-16T06:30:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007959_001 Dismissed Unplanned Production unavailability 2023-02-15T22:51:20+00:00 2023-02-15T22:50:00+00:00 2023-02-16T12:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007941_005 Inactive Unplanned Production unavailability 2023-02-08T01:02:31+00:00 2023-02-05T10:00:00+00:00 2023-02-07T23:59:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007941_004 Dismissed Unplanned Production unavailability 2023-02-07T23:02:00+00:00 2023-02-05T10:00:00+00:00 2023-02-07T23:59:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007941_003 Dismissed Unplanned Production unavailability 2023-02-07T08:23:07+00:00 2023-02-05T10:00:00+00:00 2023-02-08T23:59:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007941_002 Dismissed Unplanned Production unavailability 2023-02-05T10:07:21+00:00 2023-02-05T10:00:00+00:00 2023-02-08T17:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007941_001 Dismissed Unplanned Production unavailability 2023-02-05T10:03:30+00:00 2023-02-05T10:00:00+00:00 2023-02-08T00:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007937_004 Inactive Unplanned Production unavailability 2023-02-03T13:32:32+00:00 2023-02-02T18:37:00+00:00 2023-02-03T12:30:00+00:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007937_003 Dismissed Unplanned Production unavailability 2023-02-03T12:07:35+00:00 2023-02-02T18:37:00+00:00 2023-02-03T12:30:00+00:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007937_002 Dismissed Unplanned Production unavailability 2023-02-03T11:51:00+00:00 2023-02-02T18:37:00+00:00 2023-02-03T16:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007937_001 Dismissed Unplanned Production unavailability 2023-02-02T18:38:58+00:00 2023-02-02T18:37:00+00:00 2023-02-03T12:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - HRSG
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007896_007 Inactive Planned Production unavailability 2023-01-24T19:17:31+00:00 2023-01-24T17:35:00+00:00 2023-01-24T18:15:00+00:00 MW 113 780 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007896_006 Dismissed Planned Production unavailability 2023-01-24T18:09:57+00:00 2023-01-24T17:35:00+00:00 2023-01-24T18:15:00+00:00 MW 113 780 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007896_005 Dismissed Planned Production unavailability 2023-01-24T18:06:18+00:00 2023-01-24T17:35:00+00:00 2023-01-24T19:30:00+00:00 MW 113 780 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_KEAD-2 48W000000KEAD-23
KEADBY GEN. LTD
48X000000000073U 0000000000000000000007896_004 Dismissed Planned Production unavailability 2023-01-24T17:51:26+00:00 2023-01-24T17:35:00+00:00 2023-01-24T18:30:00+00:00 MW 113 780 893 Foreseen Maintenance
Commissioning
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007695_003 Inactive Unplanned Production unavailability 2022-11-01T11:47:33+00:00 2022-11-01T08:00:00+00:00 2022-11-01T10:45:00+00:00 MW 400 780 1180 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007695_002 Dismissed Unplanned Production unavailability 2022-11-01T10:40:07+00:00 2022-11-01T08:00:00+00:00 2022-11-01T10:45:00+00:00 MW 400 780 1180 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007695_001 Dismissed Unplanned Production unavailability 2022-11-01T08:12:41+00:00 2022-11-01T08:00:00+00:00 2022-11-01T15:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007693_004 Inactive Unplanned Production unavailability 2022-10-31T06:02:33+00:00 2022-10-29T19:30:00+01:00 2022-10-31T05:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007693_003 Dismissed Unplanned Production unavailability 2022-10-31T01:58:45+00:00 2022-10-29T19:30:00+01:00 2022-10-31T05:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007693_002 Dismissed Unplanned Production unavailability 2022-10-30T21:12:07+00:00 2022-10-29T19:30:00+01:00 2022-10-31T06:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000007693_001 Dismissed Unplanned Production unavailability 2022-10-29T19:41:11+01:00 2022-10-29T19:30:00+01:00 2022-10-31T04:00:00+00:00 MW 400 780 1180 Failure
Plant Fault - Gas Turbine
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006399_004 Dismissed Planned Production unavailability 2022-10-26T10:24:27+01:00 2024-04-05T23:00:00+01:00 2024-05-22T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006399_003 Dismissed Planned Production unavailability 2022-08-05T15:14:33+01:00 2024-04-05T23:00:00+01:00 2024-05-22T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006399_002 Dismissed Planned Production unavailability 2022-03-23T10:54:49+00:00 2024-04-05T23:00:00+01:00 2024-05-22T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006399_001 Dismissed Planned Production unavailability 2021-11-03T11:26:27+00:00 2024-04-05T23:00:00+01:00 2024-05-22T23:00:00+01:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006758_005 Dismissed Planned Production unavailability 2022-10-26T10:16:20+01:00 2026-12-01T23:00:00+00:00 2026-12-08T23:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006758_004 Dismissed Planned Production unavailability 2022-08-05T15:14:33+01:00 2026-12-01T23:00:00+00:00 2026-12-08T23:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006758_003 Dismissed Planned Production unavailability 2022-03-23T10:54:49+00:00 2026-12-01T23:00:00+00:00 2026-12-08T23:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006758_002 Dismissed Planned Production unavailability 2022-02-08T14:57:12+00:00 2026-12-01T23:00:00+00:00 2026-12-08T23:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006758_001 Dismissed Planned Production unavailability 2022-02-08T14:31:03+00:00 2026-12-01T00:00:00+00:00 2026-12-08T00:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A
T_PEHE-1 48W000000PEHE-15
SSE Thermal Generation (Scotland) Ltd
48X0000000003024 0000000000000000000006402_004 Dismissed Planned Production unavailability 2022-10-26T10:14:27+01:00 2026-01-23T23:00:00+00:00 2026-01-30T23:00:00+00:00 MW 400 780 1180 Foreseen Maintenance
Planned Outage
Fossil Gas 10YGB----------A