Last update at: 2022-06-30T01:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
1 2 3 4 5 >
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007126_003 Inactive Unplanned Production unavailability 2022-05-29T05:32:33+01:00 2022-05-29T02:12:00+01:00 2022-05-29T04:30:00+01:00 MW 102 0 102 Failure
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007126_002 Dismissed Unplanned Production unavailability 2022-05-29T04:23:01+01:00 2022-05-29T02:12:00+01:00 2022-05-29T04:30:00+01:00 MW 102 0 102 Failure
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007126_001 Dismissed Unplanned Production unavailability 2022-05-29T03:31:41+01:00 2022-05-29T02:12:00+01:00 2022-05-29T06:00:00+01:00 MW 102 0 102 Failure
Grid
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007071_002 Inactive Planned Production unavailability 2022-05-24T13:02:33+01:00 2022-05-24T11:00:00+01:00 2022-05-24T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007071_001 Dismissed Planned Production unavailability 2022-05-18T15:15:40+01:00 2022-05-24T11:00:00+01:00 2022-05-24T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007070_002 Inactive Planned Production unavailability 2022-05-20T11:02:31+01:00 2022-05-20T09:00:00+01:00 2022-05-20T10:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007070_001 Dismissed Planned Production unavailability 2022-05-18T15:13:55+01:00 2022-05-20T09:00:00+01:00 2022-05-20T10:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007010_002 Inactive Planned Production unavailability 2022-05-19T19:02:32+01:00 2022-05-19T17:00:00+01:00 2022-05-19T18:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007010_001 Dismissed Planned Production unavailability 2022-05-06T17:12:02+01:00 2022-05-19T17:00:00+01:00 2022-05-19T18:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007009_003 Inactive Planned Production unavailability 2022-05-09T14:16:53+01:00 2022-05-09T11:00:00+01:00 2022-05-09T13:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007009_002 Dismissed Planned Production unavailability 2022-05-09T11:50:43+01:00 2022-05-09T11:00:00+01:00 2022-05-09T13:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000007009_001 Dismissed Planned Production unavailability 2022-05-06T17:10:46+01:00 2022-05-09T11:00:00+01:00 2022-05-09T12:00:00+01:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000006803_002 Inactive Planned Production unavailability 2022-03-10T13:01:53+00:00 2022-03-10T10:00:00+00:00 2022-03-10T12:00:00+00:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_GRIFW-1 48W10000GRIFW-1N
GRIFFIN WIND FARM
48X000000000072W 0000000000000000000006803_001 Dismissed Planned Production unavailability 2022-02-25T14:18:23+00:00 2022-03-10T10:00:00+00:00 2022-03-10T12:00:00+00:00 MW 102 0 102 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006868_002 Dismissed Planned Production unavailability 2022-06-07T13:43:44+01:00 2022-06-07T08:00:00+01:00 2022-06-08T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006868_001 Dismissed Planned Production unavailability 2022-03-25T16:06:59+00:00 2022-06-07T08:00:00+01:00 2022-06-08T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006405_005 Inactive Planned Production unavailability 2021-11-29T12:01:53+00:00 2021-11-29T08:00:00+00:00 2021-11-29T11:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006405_004 Dismissed Planned Production unavailability 2021-11-16T15:12:08+00:00 2021-11-29T08:00:00+00:00 2021-11-29T11:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006405_003 Dismissed Planned Production unavailability 2021-11-09T15:02:42+00:00 2021-11-22T07:00:00+00:00 2021-11-22T10:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006405_002 Dismissed Planned Production unavailability 2021-11-09T12:30:18+00:00 2021-11-22T07:00:00+00:00 2021-11-22T09:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006405_001 Dismissed Planned Production unavailability 2021-11-03T14:09:16+00:00 2021-11-15T07:00:00+00:00 2021-11-15T09:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006346_002 Dismissed Planned Production unavailability 2021-10-22T08:35:37+01:00 2021-10-26T07:00:00+01:00 2021-10-26T08:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006346_001 Dismissed Planned Production unavailability 2021-10-15T10:26:38+01:00 2021-10-26T07:00:00+01:00 2021-10-26T08:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006156_002 Inactive Planned Production unavailability 2021-07-23T17:02:31+01:00 2021-07-19T08:00:00+01:00 2021-07-23T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006156_001 Dismissed Planned Production unavailability 2021-07-13T17:24:11+01:00 2021-07-19T08:00:00+01:00 2021-07-23T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006158_002 Dismissed Planned Production unavailability 2021-07-22T11:12:45+01:00 2021-07-26T08:00:00+01:00 2021-07-30T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006158_001 Dismissed Planned Production unavailability 2021-07-13T17:31:15+01:00 2021-07-26T08:00:00+01:00 2021-07-30T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_012 Inactive Planned Production unavailability 2021-06-09T23:01:51+01:00 2021-06-09T07:00:00+01:00 2021-06-09T22:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_011 Dismissed Planned Production unavailability 2021-06-09T19:02:27+01:00 2021-06-09T07:00:00+01:00 2021-06-09T22:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_010 Dismissed Planned Production unavailability 2021-06-09T16:48:57+01:00 2021-06-09T07:00:00+01:00 2021-06-09T20:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_009 Dismissed Planned Production unavailability 2021-06-09T13:36:55+01:00 2021-06-09T07:00:00+01:00 2021-06-09T17:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_008 Dismissed Planned Production unavailability 2021-06-09T12:32:00+01:00 2021-06-09T07:00:00+01:00 2021-06-09T13:30:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_007 Dismissed Planned Production unavailability 2021-06-09T11:34:50+01:00 2021-06-09T07:00:00+01:00 2021-06-09T12:30:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_006 Dismissed Planned Production unavailability 2021-06-09T10:52:33+01:00 2021-06-09T07:00:00+01:00 2021-06-09T11:30:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_005 Dismissed Planned Production unavailability 2021-06-09T09:50:40+01:00 2021-06-09T07:00:00+01:00 2021-06-09T11:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_004 Dismissed Planned Production unavailability 2021-06-09T08:57:40+01:00 2021-06-09T07:00:00+01:00 2021-06-09T10:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_003 Dismissed Planned Production unavailability 2021-06-09T08:06:33+01:00 2021-06-09T07:00:00+01:00 2021-06-09T09:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_002 Dismissed Planned Production unavailability 2021-06-09T08:02:31+01:00 2021-06-09T07:00:00+01:00 2021-06-09T08:30:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000006096_001 Dismissed Planned Production unavailability 2021-06-08T16:06:27+01:00 2021-06-09T07:00:00+01:00 2021-06-09T08:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000005272_003 Inactive Planned Production unavailability 2020-11-27T17:31:52+00:00 2020-09-07T09:00:00+01:00 2020-11-27T16:30:00+00:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000005272_002 Dismissed Planned Production unavailability 2020-10-01T18:36:24+01:00 2020-09-07T09:00:00+01:00 2020-11-27T16:30:00+00:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000005272_001 Dismissed Planned Production unavailability 2020-08-21T16:53:04+01:00 2020-09-07T09:00:00+01:00 2020-11-30T16:30:00+00:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000004824_002 Inactive Planned Production unavailability 2019-11-19T18:02:31+00:00 2019-11-19T08:00:00+00:00 2019-11-19T17:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000004824_001 Dismissed Planned Production unavailability 2019-11-18T13:21:45+00:00 2019-11-19T08:00:00+00:00 2019-11-19T17:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Planned Outage
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000004612_002 Inactive Planned Production unavailability 2019-09-05T18:02:31+01:00 2019-09-02T08:00:00+01:00 2019-09-05T17:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-3 48W00000STLGW-3A
SSE GENERATION
48X000000000077M 0000000000000000000004612_001 Dismissed Planned Production unavailability 2019-08-30T08:08:11+01:00 2019-09-02T08:00:00+01:00 2019-09-05T17:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Grid
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
SSE GENERATION
48X000000000077M 0000000000000000000006867_002 Dismissed Planned Production unavailability 2022-06-07T13:44:14+01:00 2022-06-07T08:00:00+01:00 2022-06-08T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
SSE GENERATION
48X000000000077M 0000000000000000000006867_001 Dismissed Planned Production unavailability 2022-03-25T16:05:36+00:00 2022-06-07T08:00:00+01:00 2022-06-08T16:00:00+01:00 MW 108 0 108 Foreseen Maintenance
Maintenance
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
SSE GENERATION
48X000000000077M 0000000000000000000006404_005 Inactive Planned Production unavailability 2021-11-29T12:01:53+00:00 2021-11-29T08:00:00+00:00 2021-11-29T11:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing
Wind Onshore 10YGB----------A
T_STLGW-2 48W00000STLGW-2C
SSE GENERATION
48X000000000077M 0000000000000000000006404_004 Dismissed Planned Production unavailability 2021-11-16T15:11:40+00:00 2021-11-29T08:00:00+00:00 2021-11-29T11:00:00+00:00 MW 108 0 108 Foreseen Maintenance
Testing