This site is optimised for modern web browsers, and does not fully support your Internet Browser version.

Last update at: 2024-10-13T13:30:00+01:00

**Please note that the last update time shown is rounded to the next market interval of 30 minutes

All times are in UTC.

  

Filter Options

Date of event: From date:
To date:
Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 5 6 7 8 9 >
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005299_005 Dismissed Planned Production unavailability 2022-07-13T10:37:04+01:00 2022-08-19T13:00:00+01:00 2022-08-26T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005299_004 Dismissed Planned Production unavailability 2022-03-23T10:54:49+00:00 2022-08-13T00:00:00+01:00 2022-08-20T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005299_003 Dismissed Planned Production unavailability 2021-04-01T13:15:38+01:00 2022-08-13T00:00:00+01:00 2022-08-20T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000213W
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005299_002 Dismissed Planned Production unavailability 2020-11-24T11:00:34+00:00 2022-08-13T00:00:00+01:00 2022-08-20T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000213W
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000005299_001 Dismissed Planned Production unavailability 2020-09-11T11:54:22+01:00 2022-08-13T00:00:00+01:00 2022-08-20T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_006 Inactive Planned Production unavailability 2022-02-24T16:02:33+00:00 2022-02-23T09:00:00+00:00 2022-02-24T14:50:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_005 Dismissed Planned Production unavailability 2022-02-24T14:47:48+00:00 2022-02-23T09:00:00+00:00 2022-02-24T14:50:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_004 Dismissed Planned Production unavailability 2022-02-23T09:08:01+00:00 2022-02-23T09:00:00+00:00 2022-02-24T17:00:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_003 Dismissed Planned Production unavailability 2022-02-23T09:05:22+00:00 2022-02-23T09:00:00+00:00 2022-02-25T17:00:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_002 Dismissed Planned Production unavailability 2022-02-21T16:54:04+00:00 2022-02-28T09:00:00+00:00 2022-03-01T17:00:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN3 47W000000000215S
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006781_001 Dismissed Planned Production unavailability 2022-02-16T11:48:28+00:00 2022-02-23T09:00:00+00:00 2022-02-24T17:00:00+00:00 MW 52 0 52 Foreseen Maintenance
Plant Fault - Electrical Equipment
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008996_003 Active Planned Production unavailability 2024-10-09T09:04:22+01:00 2027-06-14T00:00:00+01:00 2027-06-21T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008996_002 Dismissed Planned Production unavailability 2024-10-03T12:23:19+01:00 2027-06-14T00:00:00+01:00 2027-06-21T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008996_001 Dismissed Planned Production unavailability 2024-04-08T15:34:58+01:00 2027-06-14T00:00:00+01:00 2027-06-21T00:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008060_005 Active Planned Production unavailability 2024-10-09T09:04:22+01:00 2026-04-04T09:00:00+01:00 2026-08-31T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008060_004 Dismissed Planned Production unavailability 2024-10-03T12:23:19+01:00 2026-04-04T09:00:00+01:00 2026-08-31T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008060_003 Dismissed Planned Production unavailability 2024-03-28T16:07:39+00:00 2026-04-04T09:00:00+01:00 2026-08-31T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008060_002 Dismissed Planned Production unavailability 2023-09-06T10:24:18+01:00 2026-06-27T09:00:00+01:00 2026-09-26T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008060_001 Dismissed Planned Production unavailability 2023-04-04T12:20:38+01:00 2024-06-29T09:00:00+01:00 2024-09-28T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008967_003 Active Planned Production unavailability 2024-10-09T09:04:22+01:00 2025-06-14T09:00:00+01:00 2025-06-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008967_002 Dismissed Planned Production unavailability 2024-10-03T12:23:18+01:00 2025-06-14T09:00:00+01:00 2025-06-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008967_001 Dismissed Planned Production unavailability 2024-03-27T16:08:25+00:00 2025-06-14T09:00:00+01:00 2025-06-21T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009512_002 Inactive Planned Production unavailability 2024-10-07T13:28:22+01:00 2024-10-10T13:20:00+01:00 2024-10-10T13:21:00+01:00 MW 0 52 52 Foreseen Maintenance
Testing
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009512_001 Dismissed Planned Production unavailability 2024-10-07T13:22:37+01:00 2024-10-10T13:20:00+01:00 2024-10-10T13:21:00+01:00 MW 0 52 52 Foreseen Maintenance
Testing
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_006 Inactive Planned Production unavailability 2024-07-19T19:32:32+01:00 2024-07-08T13:00:00+01:00 2024-07-19T18:30:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_005 Dismissed Planned Production unavailability 2024-07-19T18:15:49+01:00 2024-07-08T13:00:00+01:00 2024-07-19T18:30:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_004 Dismissed Planned Production unavailability 2024-07-19T16:48:02+01:00 2024-07-08T13:00:00+01:00 2024-07-19T19:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_003 Dismissed Planned Production unavailability 2024-07-07T10:29:27+01:00 2024-07-08T13:00:00+01:00 2024-07-19T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_002 Dismissed Planned Production unavailability 2024-03-27T15:22:28+00:00 2024-07-08T09:00:00+01:00 2024-07-19T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008838_001 Dismissed Planned Production unavailability 2024-02-09T09:42:37+00:00 2024-06-29T09:00:00+01:00 2024-07-05T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_009 Inactive Planned Production unavailability 2024-04-12T12:47:32+01:00 2024-01-23T10:00:00+00:00 2024-04-12T11:40:00+01:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_008 Dismissed Planned Production unavailability 2024-04-12T11:36:40+01:00 2024-01-23T10:00:00+00:00 2024-04-12T11:40:00+01:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_007 Dismissed Planned Production unavailability 2024-03-27T11:50:42+00:00 2024-01-23T10:00:00+00:00 2024-04-12T17:00:00+01:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_006 Dismissed Planned Production unavailability 2024-03-14T09:18:29+00:00 2024-01-23T10:00:00+00:00 2024-03-29T17:00:00+00:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_005 Dismissed Planned Production unavailability 2024-03-13T22:55:04+00:00 2024-01-23T10:00:00+00:00 2024-05-15T00:00:00+01:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_004 Dismissed Planned Production unavailability 2024-02-09T09:59:42+00:00 2024-01-23T10:00:00+00:00 2024-03-15T00:00:00+00:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_003 Dismissed Planned Production unavailability 2024-01-23T09:58:32+00:00 2024-01-23T10:00:00+00:00 2024-02-29T17:00:00+00:00 MW 26 26 52 Foreseen Maintenance
Plant Fault - Gas Turbine
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_002 Dismissed Planned Production unavailability 2024-01-22T13:32:41+00:00 2024-06-29T09:00:00+01:00 2024-07-05T17:00:00+01:00 MW 26 26 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008641_001 Dismissed Planned Production unavailability 2023-11-27T12:35:21+00:00 2024-06-29T09:00:00+01:00 2024-07-05T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008778_003 Inactive Unplanned Production unavailability 2024-01-22T12:47:32+00:00 2024-01-21T17:00:00+00:00 2024-01-22T11:40:00+00:00 MW 52 0 52 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008778_002 Dismissed Unplanned Production unavailability 2024-01-22T11:36:18+00:00 2024-01-21T17:00:00+00:00 2024-01-22T11:40:00+00:00 MW 52 0 52 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008778_001 Dismissed Unplanned Production unavailability 2024-01-21T17:56:33+00:00 2024-01-21T17:00:00+00:00 2024-01-22T12:00:00+00:00 MW 52 0 52 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000007844_002 Inactive Planned Production unavailability 2023-09-01T18:02:32+01:00 2023-08-25T09:00:00+01:00 2023-09-01T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000007844_001 Dismissed Planned Production unavailability 2023-01-12T15:06:33+00:00 2023-08-25T09:00:00+01:00 2023-09-01T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008188_003 Inactive Unplanned Production unavailability 2023-06-12T10:02:32+01:00 2023-06-12T00:00:00+01:00 2023-06-12T09:00:00+01:00 MW 52 0 52 Failure
Plant Fault - Fuel Supply
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008188_002 Dismissed Unplanned Production unavailability 2023-06-12T08:52:30+01:00 2023-06-12T00:00:00+01:00 2023-06-12T09:00:00+01:00 MW 52 0 52 Failure
Plant Fault - Fuel Supply
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000008188_001 Dismissed Unplanned Production unavailability 2023-06-12T08:30:37+01:00 2023-06-12T00:00:00+01:00 2023-06-13T01:00:00+01:00 MW 52 0 52 Failure
Plant Fault - Fuel Supply
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006877_003 Inactive Planned Production unavailability 2022-11-30T16:25:28+00:00 2023-07-01T09:00:00+01:00 2023-09-30T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006877_002 Dismissed Planned Production unavailability 2022-08-05T15:14:33+01:00 2023-07-01T09:00:00+01:00 2023-09-30T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C
TAWN1 47W000000000214U
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000006877_001 Dismissed Planned Production unavailability 2022-03-30T12:21:51+01:00 2023-07-01T09:00:00+01:00 2023-09-30T17:00:00+01:00 MW 52 0 52 Foreseen Maintenance
Planned Outage
Fossil Gas 10Y1001A1001A59C