Event Status Type Of Unavailability Type of Event
Fuel Type Affected Asset or Unit Affected Asset or Unit EIC Code
Affected Unit Affected Unit EIC Code Market Participant Market Participant Code Message ID Event Status Type Of Unavailability Type Of Event Publication Date Event Start Event Stop Unit of Measurement Unavailable Capacity Available Capacity Installed Capacity Reason Of Unavailability Remarks Fuel Type Bidding Zone
< 5 6 7 8 9 >
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_008 Dismissed Planned Production unavailability 2023-08-22T11:16:32+01:00 2023-07-18T14:00:00+01:00 2023-08-28T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_007 Dismissed Planned Production unavailability 2023-08-18T09:15:29+01:00 2023-07-18T14:00:00+01:00 2023-08-23T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_006 Dismissed Planned Production unavailability 2023-08-14T14:35:59+01:00 2023-07-18T14:00:00+01:00 2023-08-20T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_005 Dismissed Planned Production unavailability 2023-08-09T17:28:46+01:00 2023-07-18T14:00:00+01:00 2023-08-15T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_004 Dismissed Planned Production unavailability 2023-08-04T15:44:04+01:00 2023-07-18T14:00:00+01:00 2023-08-11T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_003 Dismissed Planned Production unavailability 2023-07-28T15:56:54+01:00 2023-07-18T14:00:00+01:00 2023-08-07T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_002 Dismissed Planned Production unavailability 2023-07-24T10:48:46+01:00 2023-07-18T14:00:00+01:00 2023-08-02T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-4 48W00000DBAWO-4D
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008255_001 Dismissed Planned Production unavailability 2023-07-18T13:51:42+01:00 2023-07-18T14:00:00+01:00 2023-07-28T07:00:00+01:00 MW 153 0 153 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_034 Dismissed Planned Production unavailability 2024-04-19T13:07:03+01:00 2023-07-18T14:00:00+01:00 2024-11-11T10:00:00+00:00 MW 0 0 0 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_033 Dismissed Planned Production unavailability 2024-04-19T13:04:31+01:00 2023-07-18T14:00:00+01:00 2024-11-11T10:00:00+00:00 MW 0 0 0 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_032 Dismissed Planned Production unavailability 2024-04-19T13:03:21+01:00 2023-07-18T14:00:00+01:00 2024-11-11T10:00:00+00:00 MW 0 138 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_031 Dismissed Planned Production unavailability 2024-04-19T13:02:21+01:00 2023-07-18T14:00:00+01:00 2024-11-11T10:00:00+00:00 MW 0 0 0 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_030 Dismissed Planned Production unavailability 2024-03-22T08:16:23+00:00 2023-07-18T14:00:00+01:00 2024-11-11T10:00:00+00:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_029 Dismissed Planned Production unavailability 2024-03-22T07:35:55+00:00 2023-07-18T14:00:00+01:00 2024-11-11T09:00:00+00:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_028 Dismissed Planned Production unavailability 2024-03-22T07:33:55+00:00 2023-07-18T14:00:00+01:00 2025-01-08T09:00:00+00:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_027 Dismissed Planned Production unavailability 2024-03-19T12:11:06+00:00 2023-07-18T14:00:00+01:00 2024-10-11T09:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_026 Dismissed Planned Production unavailability 2024-02-21T13:57:18+00:00 2023-07-18T14:00:00+01:00 2024-10-07T09:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_025 Dismissed Planned Production unavailability 2024-01-10T12:56:50+00:00 2023-07-18T14:00:00+01:00 2024-09-14T09:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_024 Dismissed Planned Production unavailability 2023-11-07T13:10:23+00:00 2023-07-18T14:00:00+01:00 2024-08-17T00:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_023 Dismissed Planned Production unavailability 2023-09-28T14:43:55+01:00 2023-07-18T14:00:00+01:00 2024-07-24T00:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_022 Dismissed Planned Production unavailability 2023-09-28T14:30:35+01:00 2023-07-18T14:00:00+01:00 2023-09-29T19:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_021 Dismissed Planned Production unavailability 2023-09-27T15:22:28+01:00 2023-07-18T14:00:00+01:00 2023-09-28T19:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_020 Dismissed Planned Production unavailability 2023-09-26T15:41:35+01:00 2023-07-18T14:00:00+01:00 2023-09-27T19:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_019 Dismissed Planned Production unavailability 2023-09-25T17:40:25+01:00 2023-07-18T14:00:00+01:00 2023-09-27T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_018 Dismissed Planned Production unavailability 2023-09-23T12:49:34+01:00 2023-07-18T14:00:00+01:00 2023-09-26T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_017 Dismissed Planned Production unavailability 2023-09-22T17:39:07+01:00 2023-07-18T14:00:00+01:00 2023-09-23T19:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_016 Dismissed Planned Production unavailability 2023-09-19T18:29:26+01:00 2023-07-18T14:00:00+01:00 2023-09-23T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_015 Dismissed Planned Production unavailability 2023-09-18T17:40:03+01:00 2023-07-18T14:00:00+01:00 2023-09-20T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_014 Dismissed Planned Production unavailability 2023-09-17T18:17:56+01:00 2023-07-18T14:00:00+01:00 2023-09-19T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_013 Dismissed Planned Production unavailability 2023-09-14T21:25:51+01:00 2023-07-18T14:00:00+01:00 2023-09-18T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_012 Dismissed Planned Production unavailability 2023-09-12T08:42:35+01:00 2023-07-18T14:00:00+01:00 2023-09-15T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_011 Dismissed Planned Production unavailability 2023-09-05T17:39:29+01:00 2023-07-18T14:00:00+01:00 2023-09-13T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_010 Dismissed Planned Production unavailability 2023-08-30T16:04:51+01:00 2023-07-18T14:00:00+01:00 2023-09-06T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_009 Dismissed Planned Production unavailability 2023-08-25T10:10:26+01:00 2023-07-18T14:00:00+01:00 2023-08-31T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_008 Dismissed Planned Production unavailability 2023-08-22T11:17:03+01:00 2023-07-18T14:00:00+01:00 2023-08-28T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_007 Dismissed Planned Production unavailability 2023-08-18T09:14:39+01:00 2023-07-18T14:00:00+01:00 2023-08-23T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_006 Dismissed Planned Production unavailability 2023-08-14T14:36:20+01:00 2023-07-18T14:00:00+01:00 2023-08-20T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_005 Dismissed Planned Production unavailability 2023-08-09T17:28:26+01:00 2023-07-18T14:00:00+01:00 2023-08-15T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_004 Dismissed Planned Production unavailability 2023-08-04T15:44:28+01:00 2023-07-18T14:00:00+01:00 2023-08-11T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_003 Dismissed Planned Production unavailability 2023-07-28T15:57:12+01:00 2023-07-18T14:00:00+01:00 2023-08-07T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_002 Dismissed Planned Production unavailability 2023-07-24T10:48:23+01:00 2023-07-18T14:00:00+01:00 2023-08-02T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
DBAWO-5 48W00000DBAWO-5B
Doggerbank Offshore Wind Farm Project 1 Projco Limited
48X0000000003113 0000000000000000000008256_001 Dismissed Planned Production unavailability 2023-07-18T13:52:45+01:00 2023-07-18T14:00:00+01:00 2023-07-28T07:00:00+01:00 MW 138 0 138 Shutdown
Planned Outage
Wind Offshore 10YGB----------A
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009048_003 Active Planned Production unavailability 2024-04-26T17:16:19+01:00 2024-04-26T17:20:00+01:00 2024-05-01T23:57:00+01:00 MW 290 174 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009048_002 Dismissed Planned Production unavailability 2024-04-26T12:59:20+01:00 2024-04-26T16:00:00+01:00 2024-05-01T23:57:00+01:00 MW 164 300 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009048_001 Dismissed Planned Production unavailability 2024-04-26T10:05:20+01:00 2024-04-26T23:58:00+01:00 2024-05-01T23:57:00+01:00 MW 164 300 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009047_004 Inactive Unplanned Production unavailability 2024-04-26T17:02:31+01:00 2024-04-25T23:30:00+01:00 2024-04-26T16:00:00+01:00 MW 464 0 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009047_003 Dismissed Unplanned Production unavailability 2024-04-26T12:56:21+01:00 2024-04-25T23:30:00+01:00 2024-04-26T16:00:00+01:00 MW 464 0 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009047_002 Dismissed Unplanned Production unavailability 2024-04-26T08:58:43+01:00 2024-04-25T23:30:00+01:00 2024-04-26T23:57:00+01:00 MW 464 0 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009047_001 Dismissed Unplanned Production unavailability 2024-04-25T23:40:13+01:00 2024-04-25T23:30:00+01:00 2024-04-26T18:00:00+01:00 MW 464 0 464 Failure
Plant Fault - Auxiliary Equipment
Fossil Gas 10Y1001A1001A59C
Great Island 47W0000000001024
SSE Generation Ireland Ltd
47X0000000000592 0000000000000000000009020_003 Inactive Unplanned Production unavailability 2024-04-16T07:02:32+01:00 2024-04-16T03:30:00+01:00 2024-04-16T06:00:00+01:00 MW 464 0 464 Failure
Plant Fault - HRSG