| Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| < 96 97 98 99 100 > | ||||||||||||||||||
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008884_001 | Dismissed | Planned | Production unavailability | 2024-02-27T08:09:56+00:00 | 2024-03-25T08:00:00+00:00 | 2024-03-25T11:00:00+00:00 | MW | 0 | 126 | 126 | Foreseen Maintenance | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008954_003 | Inactive | Planned | Consumption unavailability | 2024-03-22T15:02:32+00:00 | 2024-03-22T09:00:00+00:00 | 2024-03-22T14:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008954_002 | Dismissed | Planned | Consumption unavailability | 2024-03-22T11:38:16+00:00 | 2024-03-22T09:00:00+00:00 | 2024-03-22T14:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008954_001 | Dismissed | Planned | Consumption unavailability | 2024-03-22T06:43:27+00:00 | 2024-03-22T09:00:00+00:00 | 2024-03-22T12:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_003 | Dismissed | Planned | Production unavailability | 2024-03-22T11:46:50+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
| VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_002 | Dismissed | Planned | Production unavailability | 2024-03-22T11:10:29+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:30:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
| VKNGW-3 | 48W00000VKNGW-30 | Viking Energy Wind Farm LLP |
48X000000000314Y | 0000000000000000000008955_001 | Dismissed | Planned | Production unavailability | 2024-03-22T10:24:43+00:00 | 2024-03-22T10:30:00+00:00 | 2024-03-22T11:00:00+00:00 | MW | 10 | 0 | 10 | Shutdown | Commissioning |
Wind Onshore | 10YGB----------A |
| T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008893_003 | Dismissed | Planned | Production unavailability | 2024-03-20T15:03:55+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008893_002 | Dismissed | Planned | Production unavailability | 2024-03-20T12:38:08+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-4 | 48W00000BEATO-4N | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008893_001 | Dismissed | Planned | Production unavailability | 2024-02-27T08:27:49+00:00 | 2024-04-21T17:00:00+00:00 | 2024-04-21T21:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008892_003 | Dismissed | Planned | Production unavailability | 2024-03-20T15:02:52+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008892_002 | Dismissed | Planned | Production unavailability | 2024-03-20T12:39:03+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008892_001 | Dismissed | Planned | Production unavailability | 2024-02-27T08:26:46+00:00 | 2024-04-21T17:00:00+00:00 | 2024-04-21T21:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008891_003 | Dismissed | Planned | Production unavailability | 2024-03-20T15:02:29+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008891_002 | Dismissed | Planned | Production unavailability | 2024-03-20T12:39:41+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-2 | 48W00000BEATO-2R | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008891_001 | Dismissed | Planned | Production unavailability | 2024-02-27T08:25:34+00:00 | 2024-04-21T17:00:00+00:00 | 2024-04-21T21:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008890_003 | Dismissed | Planned | Production unavailability | 2024-03-20T15:01:53+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008890_002 | Dismissed | Planned | Production unavailability | 2024-03-20T12:40:37+00:00 | 2024-04-22T07:00:00+00:00 | 2024-04-22T11:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008890_001 | Dismissed | Planned | Production unavailability | 2024-02-27T08:21:09+00:00 | 2024-04-21T17:00:00+00:00 | 2024-04-21T21:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Maintenance |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_009 | Inactive | Planned | Production unavailability | 2024-03-18T09:02:32+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-18T08:00:00+00:00 | MW | 26 | 0 | 26 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_008 | Dismissed | Planned | Production unavailability | 2024-03-17T17:49:29+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-18T08:00:00+00:00 | MW | 26 | 0 | 26 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_007 | Dismissed | Planned | Production unavailability | 2024-03-15T15:15:14+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-18T08:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_006 | Dismissed | Planned | Production unavailability | 2024-03-14T07:45:54+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-20T10:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_005 | Dismissed | Planned | Production unavailability | 2024-03-11T11:57:07+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-14T10:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_004 | Dismissed | Planned | Production unavailability | 2024-03-08T08:34:08+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-12T10:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_003 | Dismissed | Planned | Production unavailability | 2024-03-06T13:28:20+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-10T10:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_002 | Dismissed | Planned | Production unavailability | 2024-03-04T12:05:31+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-07T10:00:00+00:00 | MW | 289 | 13 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| DBAWO-1 | 48W00000DBAWO-1J | Doggerbank Offshore Wind Farm Project 1 Projco Limited |
48X0000000003113 | 0000000000000000000008871_001 | Dismissed | Planned | Production unavailability | 2024-02-22T13:51:00+00:00 | 2024-03-04T10:00:00+00:00 | 2024-03-07T10:00:00+00:00 | MW | 224 | 78 | 302 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008939_002 | Inactive | Planned | Consumption unavailability | 2024-03-16T11:02:31+00:00 | 2024-03-15T20:00:00+00:00 | 2024-03-16T10:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008939_001 | Dismissed | Planned | Consumption unavailability | 2024-03-15T19:56:36+00:00 | 2024-03-15T20:00:00+00:00 | 2024-03-16T10:00:00+00:00 | MW | 150 | 0 | 150 | Shutdown | Water Management |
Hydro Pumped Storage | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008917_002 | Dismissed | Planned | Production unavailability | 2024-03-15T14:42:23+00:00 | 2024-03-19T07:00:00+00:00 | 2024-03-19T19:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
| T_BEATO-3 | 48W00000BEATO-3P | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008917_001 | Dismissed | Planned | Production unavailability | 2024-03-08T14:48:32+00:00 | 2024-03-19T07:00:00+00:00 | 2024-03-19T19:00:00+00:00 | MW | 168 | 0 | 168 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008916_002 | Dismissed | Planned | Production unavailability | 2024-03-15T14:41:57+00:00 | 2024-03-19T07:00:00+00:00 | 2024-03-19T19:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
| T_BEATO-1 | 48W00000BEATO-1T | Beatrice Offshore Windfarm Limited (BOWL) |
48X000000000208X | 0000000000000000000008916_001 | Dismissed | Planned | Production unavailability | 2024-03-08T14:47:05+00:00 | 2024-03-19T07:00:00+00:00 | 2024-03-19T19:00:00+00:00 | MW | 126 | 0 | 126 | Foreseen Maintenance | Grid |
Wind Offshore | 10YGB----------A |
| T_CLDCW-1 | 48W00000CLDCW-17 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008938_002 | Inactive | Planned | Production unavailability | 2024-03-14T17:02:32+00:00 | 2024-03-14T14:30:00+00:00 | 2024-03-14T16:00:00+00:00 | MW | 187 | 0 | 187 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDCW-1 | 48W00000CLDCW-17 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008938_001 | Dismissed | Planned | Production unavailability | 2024-03-14T08:59:12+00:00 | 2024-03-14T14:30:00+00:00 | 2024-03-14T16:00:00+00:00 | MW | 187 | 0 | 187 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008860_002 | Dismissed | Planned | Production unavailability | 2024-03-14T15:43:58+00:00 | 2024-03-14T16:00:00+00:00 | 2024-03-14T17:00:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008860_001 | Dismissed | Planned | Production unavailability | 2024-02-20T14:59:20+00:00 | 2024-03-14T16:00:00+00:00 | 2024-03-14T17:00:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDNW-1 | 48W00000CLDNW-1Q | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008937_002 | Inactive | Planned | Production unavailability | 2024-03-14T15:02:32+00:00 | 2024-03-14T12:30:00+00:00 | 2024-03-14T14:00:00+00:00 | MW | 187 | 0 | 187 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDNW-1 | 48W00000CLDNW-1Q | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008937_001 | Dismissed | Planned | Production unavailability | 2024-03-14T08:57:21+00:00 | 2024-03-14T12:30:00+00:00 | 2024-03-14T14:00:00+00:00 | MW | 187 | 0 | 187 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008859_005 | Inactive | Planned | Production unavailability | 2024-03-14T14:02:32+00:00 | 2024-03-14T08:00:00+00:00 | 2024-03-14T13:00:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008859_004 | Dismissed | Planned | Production unavailability | 2024-03-14T12:25:03+00:00 | 2024-03-14T08:00:00+00:00 | 2024-03-14T13:00:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008859_003 | Dismissed | Planned | Production unavailability | 2024-03-14T11:25:09+00:00 | 2024-03-14T08:00:00+00:00 | 2024-03-14T12:30:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008859_002 | Dismissed | Planned | Production unavailability | 2024-03-14T08:10:53+00:00 | 2024-03-14T08:00:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_CLDSW-1 | 48W00000CLDSW-11 | Clyde Windfarm (Scotland) Limited |
48X000000000071Y | 0000000000000000000008859_001 | Dismissed | Planned | Production unavailability | 2024-02-20T14:58:12+00:00 | 2024-03-14T08:00:00+00:00 | 2024-03-14T09:00:00+00:00 | MW | 129 | 0 | 129 | Foreseen Maintenance | Planned Outage |
Wind Onshore | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008933_002 | Inactive | Planned | Consumption unavailability | 2024-03-14T12:32:32+00:00 | 2024-03-14T10:30:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008934_002 | Inactive | Planned | Production unavailability | 2024-03-14T12:32:32+00:00 | 2024-03-14T10:30:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 130 | 20 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008931_002 | Inactive | Planned | Consumption unavailability | 2024-03-14T12:32:32+00:00 | 2024-03-14T10:30:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008932_002 | Inactive | Planned | Production unavailability | 2024-03-14T12:32:32+00:00 | 2024-03-14T10:30:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
| T_FOYE-2 | 48W000000FOYE-22 | SSE GENERATION |
48X000000000077M | 0000000000000000000008932_001 | Dismissed | Planned | Production unavailability | 2024-03-13T16:07:31+00:00 | 2024-03-14T10:30:00+00:00 | 2024-03-14T11:30:00+00:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Testing |