Affected Unit | Affected Unit EIC Code | Market Participant | Market Participant Code | Message ID | Event Status | Type Of Unavailability | Type Of Event | Publication Date | Event Start | Event Stop | Unit of Measurement | Unavailable Capacity | Available Capacity | Installed Capacity | Reason Of Unavailability | Remarks | Fuel Type | Bidding Zone |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
< 7 8 9 10 11 > | ||||||||||||||||||
T_SGRWO-4 | 48W00000SGRWO-4F | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008357_001 | Dismissed | Planned | Production unavailability | 2023-08-28T19:00:26+01:00 | 2023-08-28T19:00:00+01:00 | 2023-08-30T23:00:00+01:00 | MW | 50 | 90 | 140 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008367_001 | Dismissed | Planned | Production unavailability | 2023-08-31T11:55:52+01:00 | 2023-09-02T07:01:00+01:00 | 2023-09-02T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008375_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:18:37+01:00 | 2023-09-02T07:01:00+01:00 | 2023-09-02T23:00:00+01:00 | MW | 102 | 198 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008381_003 | Inactive | Planned | Production unavailability | 2023-09-02T08:02:32+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 68 | 290 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008381_002 | Dismissed | Planned | Production unavailability | 2023-08-31T12:39:41+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 68 | 290 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008366_002 | Inactive | Planned | Production unavailability | 2023-09-02T08:02:32+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008374_002 | Inactive | Planned | Production unavailability | 2023-09-02T08:02:32+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 140 | 160 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008374_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:17:11+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 140 | 160 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008366_001 | Dismissed | Planned | Production unavailability | 2023-08-31T11:53:45+01:00 | 2023-09-01T23:01:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008381_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:34:37+01:00 | 2023-09-01T23:00:00+01:00 | 2023-09-02T07:00:00+01:00 | MW | 68 | 290 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008369_003 | Dismissed | Planned | Production unavailability | 2023-09-02T05:12:41+01:00 | 2023-09-03T07:01:00+01:00 | 2023-09-03T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008369_002 | Dismissed | Planned | Production unavailability | 2023-09-01T18:33:19+01:00 | 2023-09-03T07:01:00+01:00 | 2023-09-03T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008369_001 | Dismissed | Planned | Production unavailability | 2023-08-31T11:59:34+01:00 | 2023-09-03T07:01:00+01:00 | 2023-09-03T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008373_002 | Inactive | Planned | Production unavailability | 2023-09-02T00:02:32+01:00 | 2023-09-01T07:01:00+01:00 | 2023-09-01T23:00:00+01:00 | MW | 102 | 198 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008365_002 | Inactive | Planned | Production unavailability | 2023-09-02T00:02:32+01:00 | 2023-09-01T07:01:00+01:00 | 2023-09-01T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008365_001 | Dismissed | Planned | Production unavailability | 2023-08-31T11:51:56+01:00 | 2023-09-01T07:01:00+01:00 | 2023-09-01T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008373_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:15:30+01:00 | 2023-09-01T07:01:00+01:00 | 2023-09-01T23:00:00+01:00 | MW | 102 | 198 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_007 | Inactive | Planned | Production unavailability | 2023-09-01T21:02:32+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T20:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_006 | Dismissed | Planned | Production unavailability | 2023-09-01T19:44:55+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T20:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_005 | Dismissed | Planned | Production unavailability | 2023-09-01T19:42:53+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T19:46:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_004 | Dismissed | Planned | Production unavailability | 2023-09-01T18:03:38+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T20:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_003 | Dismissed | Planned | Production unavailability | 2023-09-01T17:00:37+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T19:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_002 | Dismissed | Planned | Production unavailability | 2023-09-01T16:04:26+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T18:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000008362_001 | Dismissed | Planned | Production unavailability | 2023-08-30T10:45:09+01:00 | 2023-09-01T13:00:00+01:00 | 2023-09-01T17:00:00+01:00 | MW | 0 | 150 | 150 | Foreseen Maintenance | Testing |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008371_002 | Dismissed | Planned | Production unavailability | 2023-09-01T18:34:02+01:00 | 2023-09-04T07:01:00+01:00 | 2023-09-04T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008371_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:05:16+01:00 | 2023-09-04T07:01:00+01:00 | 2023-09-04T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008370_002 | Dismissed | Planned | Production unavailability | 2023-09-01T18:33:48+01:00 | 2023-09-03T23:01:00+01:00 | 2023-09-04T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008370_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:01:52+01:00 | 2023-09-03T23:01:00+01:00 | 2023-09-04T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007844_002 | Inactive | Planned | Production unavailability | 2023-09-01T18:02:32+01:00 | 2023-08-25T09:00:00+01:00 | 2023-09-01T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
TAWN1 | 47W000000000214U | SSE Generation Ireland Ltd |
47X0000000000592 | 0000000000000000000007844_001 | Dismissed | Planned | Production unavailability | 2023-01-12T15:06:33+00:00 | 2023-08-25T09:00:00+01:00 | 2023-09-01T17:00:00+01:00 | MW | 52 | 0 | 52 | Foreseen Maintenance | Planned Outage |
Fossil Gas | 10Y1001A1001A59C |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008384_003 | Dismissed | Planned | Production unavailability | 2023-09-01T14:51:17+01:00 | 2023-09-01T13:33:00+01:00 | 2023-09-01T15:33:00+01:00 | MW | 680 | 30 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008384_002 | Dismissed | Planned | Production unavailability | 2023-09-01T09:26:04+01:00 | 2023-09-01T13:33:00+01:00 | 2023-09-01T15:33:00+01:00 | MW | 680 | 30 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_MEDP-1 | 48W000000MEDP-12 | MEDWAY POWER LTD |
48X000000000076O | 0000000000000000000008384_001 | Dismissed | Planned | Production unavailability | 2023-09-01T08:57:25+01:00 | 2023-09-01T15:33:00+01:00 | 2023-09-01T17:33:00+01:00 | MW | 680 | 30 | 710 | Foreseen Maintenance | Testing |
Fossil Gas | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007531_003 | Inactive | Planned | Consumption unavailability | 2023-09-01T14:02:32+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T13:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007530_003 | Inactive | Planned | Production unavailability | 2023-09-01T14:02:32+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T13:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007531_002 | Dismissed | Planned | Consumption unavailability | 2023-08-30T10:43:09+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T13:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007530_002 | Dismissed | Planned | Production unavailability | 2023-08-30T10:43:40+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T13:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007531_001 | Dismissed | Planned | Consumption unavailability | 2022-08-23T13:56:21+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T17:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_FOYE-1 | 48W000000FOYE-14 | SSE GENERATION |
48X000000000077M | 0000000000000000000007530_001 | Dismissed | Planned | Production unavailability | 2022-08-23T13:52:23+01:00 | 2023-08-14T08:00:00+01:00 | 2023-09-01T17:00:00+01:00 | MW | 150 | 0 | 150 | Foreseen Maintenance | Maintenance |
Hydro Pumped Storage | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008380_002 | Inactive | Planned | Production unavailability | 2023-09-01T08:02:32+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 68 | 290 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008372_002 | Inactive | Planned | Production unavailability | 2023-09-01T08:02:32+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 140 | 160 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008364_002 | Inactive | Planned | Production unavailability | 2023-09-01T08:02:32+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008364_001 | Dismissed | Planned | Production unavailability | 2023-08-31T11:49:27+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 120 | 40 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008372_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:14:14+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 140 | 160 | 300 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008380_001 | Dismissed | Planned | Production unavailability | 2023-08-31T12:31:19+01:00 | 2023-08-31T23:01:00+01:00 | 2023-09-01T07:00:00+01:00 | MW | 68 | 290 | 358 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-3 | 48W00000SGRWO-3H | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008359_002 | Inactive | Planned | Production unavailability | 2023-09-01T00:02:31+01:00 | 2023-08-31T07:01:00+01:00 | 2023-08-31T23:00:00+01:00 | MW | 90 | 70 | 160 | Shutdown | Planned Outage |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008352_002 | Inactive | Planned | Production unavailability | 2023-09-01T00:02:31+01:00 | 2023-08-31T07:01:00+01:00 | 2023-08-31T23:00:00+01:00 | MW | 102 | 198 | 300 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008347_002 | Inactive | Planned | Production unavailability | 2023-09-01T00:02:31+01:00 | 2023-08-31T07:01:00+01:00 | 2023-08-31T23:00:00+01:00 | MW | 0 | 358 | 358 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-6 | 48W00000SGRWO-6B | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008347_001 | Dismissed | Planned | Production unavailability | 2023-08-25T19:43:05+01:00 | 2023-08-31T07:01:00+01:00 | 2023-08-31T23:00:00+01:00 | MW | 0 | 358 | 358 | Shutdown | Commissioning |
Wind Offshore | 10YGB----------A |
T_SGRWO-5 | 48W00000SGRWO-5D | Seagreen Wind Energy Ltd |
48X000000000263P | 0000000000000000000008352_001 | Dismissed | Planned | Production unavailability | 2023-08-25T20:52:29+01:00 | 2023-08-31T07:01:00+01:00 | 2023-08-31T23:00:00+01:00 | MW | 102 | 198 | 300 | Shutdown | Commissioning |